Dear All TVT had received information about the drawing (23.April.2015 dịch - Dear All TVT had received information about the drawing (23.April.2015 Việt làm thế nào để nói

Dear All TVT had received informati

Dear All

TVT had received information about the drawing (23.April.2015) from Mr.Duy & depend on this updated drawing, TVT comments some issues:

1/ F.G WAREHOUSE
- Change receiving trench cap. (revised & added D350 piles follow drawing 23.April.2015)
- Implement detail of boiler house and coal storage.(not update detail to drawing 23.April.2015).
2/ FLAT STORAGE
- Change the door near receiving trench. (revised follow drawing 23.April.2015)
- Level of Flat storage's ground slab has slope 2% - equivalent (+250). (revised follow drawing 23.April.2015)
- Section & reinforcement of column follow tender drawing. (revised follow drawing 23.April.2015)
- Section & reinforcement of ground beam follow tender drawing. (revised follow drawing 23.April.2015)
- Foundation at axis X14 follow revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
3/ MILL TOWER
- Tower's pile follow revised drawing (16.April.2015). (revised and added D350 piles in mill tower's trench follow drawing 23.April.2015)
- Not use door at level -4.020m. (revised follow drawing 23.April.2015)
- Dimension of mill tower's foundation follow revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
- Detail & structure of mill tower Anco will revise and send back. (revised follow drawing 23.April.2015)
4/ WORKER WC
- Add revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
5/ DRAINAGE
- Storm drainage pipe in back side D400 change to D600. (revised follow drawing 23.April.2015)
6/ SCALE
- Add construction drawing (include structure, amount and length of piles). (revised follow drawing 23.April.2015)
7/ OFFICE
- Add detail drawing of slab. (revised follow drawing 23.April.2015)
8/ Canteen
- Add detail drawing of slab. (revised follow drawing 23.April.2015)
9/ INTERNAL ROAD
- Revise structure drawing of road same the consensus at meeting on 13.April.2015. (revised follow drawing 23.April.2015)
Please review and implement some issues TVT mentioned above & publish the official drawing as soon as possible to TVT send to you a quotation for this variation order.


Thanks & best regards.
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
Dear All

TVT had received information about the drawing (23.April.2015) from Mr.Duy & depend on this updated drawing, TVT comments some issues:

1/ F.G WAREHOUSE
- Change receiving trench cap. (revised & added D350 piles follow drawing 23.April.2015)
- Implement detail of boiler house and coal storage.(not update detail to drawing 23.April.2015).
2/ FLAT STORAGE
- Change the door near receiving trench. (revised follow drawing 23.April.2015)
- Level of Flat storage's ground slab has slope 2% - equivalent (+250). (revised follow drawing 23.April.2015)
- Section & reinforcement of column follow tender drawing. (revised follow drawing 23.April.2015)
- Section & reinforcement of ground beam follow tender drawing. (revised follow drawing 23.April.2015)
- Foundation at axis X14 follow revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
3/ MILL TOWER
- Tower's pile follow revised drawing (16.April.2015). (revised and added D350 piles in mill tower's trench follow drawing 23.April.2015)
- Not use door at level -4.020m. (revised follow drawing 23.April.2015)
- Dimension of mill tower's foundation follow revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
- Detail & structure of mill tower Anco will revise and send back. (revised follow drawing 23.April.2015)
4/ WORKER WC
- Add revised drawing (16.April.2015). (revised follow drawing 23.April.2015)
5/ DRAINAGE
- Storm drainage pipe in back side D400 change to D600. (revised follow drawing 23.April.2015)
6/ SCALE
- Add construction drawing (include structure, amount and length of piles). (revised follow drawing 23.April.2015)
7/ OFFICE
- Add detail drawing of slab. (revised follow drawing 23.April.2015)
8/ Canteen
- Add detail drawing of slab. (revised follow drawing 23.April.2015)
9/ INTERNAL ROAD
- Revise structure drawing of road same the consensus at meeting on 13.April.2015. (revised follow drawing 23.April.2015)
Please review and implement some issues TVT mentioned above & publish the official drawing as soon as possible to TVT send to you a quotation for this variation order.


Thanks & best regards.
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
Dear All TVT đã nhận được thông tin về các bản vẽ (23.April.2015) từ Mr.Duy & phụ thuộc vào bản vẽ cập nhật này, TVT bình luận một số vấn đề: 1 / FG KHO - Thay đổi nhận nắp rãnh. (Sửa đổi và bổ sung cọc D350 tuân theo bản vẽ 23.April.2015) - Thực hiện các chi tiết của lò hơi và chứa than (không cập nhật chi tiết để vẽ 23.April.2015).. 2 / FLAT BẢO QUẢN - Thay đổi gần cửa nhận rãnh. (Được sửa đổi theo bản vẽ 23.April.2015) - Mức độ mặt đất phiến lưu trữ của Flat có độ dốc 2% - tương đương (250). (Được sửa đổi theo bản vẽ 23.April.2015) - Mục & củng cố các cột tiếp theo vẽ thầu. (Được sửa đổi theo bản vẽ 23.April.2015) - Mục & tăng cường dầm mặt đất vẽ sau đấu thầu. (Được sửa đổi theo bản vẽ 23.April.2015) - Foundation tại trục X14 tuân theo sửa đổi bản vẽ (16.April.2015). (Được sửa đổi theo bản vẽ 23.April.2015) 3 / MILL TOWER - đống Tháp tuân theo điều chỉnh bản vẽ (16.April.2015). (Sửa đổi và bổ sung cọc D350 trong mương nhà máy của tháp theo bản vẽ 23.April.2015) - Không sử dụng cửa ở mức -4.020m. (Được sửa đổi theo bản vẽ 23.April.2015) - Kích thước của móng nhà máy của tháp làm theo sửa đổi bản vẽ (16.April.2015). (Được sửa đổi theo bản vẽ 23.April.2015) - Chi tiết và cấu trúc của tháp nhà máy Anco sẽ rà soát lại và gửi lại. (Được sửa đổi theo bản vẽ 23.April.2015) 4 / CÔNG NHÂN WC - Thêm sửa đổi bản vẽ (16.April.2015). (Được sửa đổi theo bản vẽ 23.April.2015) 5 / THOÁT NƯỚC - Storm đường ống thoát nước ở phía sau thay đổi bên D400 đến D600. (Được sửa đổi theo bản vẽ 23.April.2015) 6 / THANG - Thêm xây dựng bản vẽ (bao gồm cơ cấu, số lượng và chiều dài của cọc). (Được sửa đổi theo bản vẽ 23.April.2015) 7 / VĂN PHÒNG - Thêm bản vẽ chi tiết của tấm. (Được sửa đổi theo bản vẽ 23.April.2015) 8 / Canteen - Thêm bản vẽ chi tiết của tấm. (Được sửa đổi theo bản vẽ 23.April.2015) 9 / NỘI ROAD - Bản vẽ kết cấu Sửa đổi của cùng một con đường sự đồng thuận tại cuộc họp về 13.April.2015. (Được sửa đổi theo bản vẽ 23.April.2015) Vui lòng xem lại và thực hiện một số vấn đề TVT nêu trên và in các bản vẽ chính thức càng sớm càng tốt để TVT gửi cho bạn một báo giá cho sự thay đổi này để. Thanks & best regards.
































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: