I have asked numerous time for completion. You promise me by 25th February and then next week, next week. I will give you up till 12th March to completely hand over your work. What have not done, or up to our standard Zenith will finish the works our self and will deduct from the balance of the contract.
Below are the list need your immediate attention :
1) Entrance door, Repaint
2) Skirting not complete and paint, some are not up to standard
3) Gutter not complete
4) Wood columns not smooth
5) grout not up to standard
6) Natural stone must re-install
7) Turkish sink install
8) power point behind mirror must move
9) missing mosaic tiles
10) Toilet in Thai massage not straight
11) wall are cracks
12) WC Stainless steel gutters, Exhaust fan,
13) cover for hot water system