JGCS approved SWMS & JSA, check list s and necessary surveys to be carried out before
work commences.
• The work description should be a clear statement of a planned activity, location, and
equipment to be used.
• Broad scopes of work of a general nature are not acceptable, and shall be rejected by the
Permit Issuer.
• JGCS approved Safe Work Method Statement i s required for all activities , critical and not
critical describing potential hazard and its mitigation .
• Where additional PTW or supporting Certificates are required, t he serial numbers will be
NSRP Complex Project
Employer Doc. No.
Rev. 2
Title: PTW(Permit to Work) Procedure
Contractor Doc. No.
S-000 -1654-0200 V
Page 11 of 40
noted and will be attached with the PTW application form.
• JGCS approved JSA’s shall be attached to all PTW’s and checked that they address the
tasks hazards mentioned before being authorized by the Permit Issuer.
• Where the impact of any works cross into another area of responsibility, this shall be