These techniques are not actually used in this process, because the schedule itself has not been developed at this point. This is simply a list of tools and techniques that can be used later on in the scheduling processes. 6.1.2.3 MeetingsThese involve people who are responsible for scope management including the project manager, the project sponsor, selected project team members, selected stakeholders, any-one with responsibility for any of the time management processes, and others as needed.6.1.3 Plan Schedule Management: OutputsThis process will create the following output:6.1.3.1 Schedule Management PlanThis is a component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.