ISSUE PACKING SPEC. WITH UPDATED.
WE SHOULD PREPARE MATERIAL AS SCHEDULE.
WE USE 2 KINDS PACKING BOX.
DEAR ALL
PLANNING SCHEDULE FOR NEW GE PUMP PARTS.
1) PRESENT ISSUES SETTLEMENT : UNTIL 17TH, July 14, 2016
ARM VALVE : GE WILL FINISH ENDURANCE TEST WILL BE FINISHED UNTIL TODAY.
UNTIL NOW, NOT ISSUE.
IMPELLER : INJECTION IS TRYING FINAL
ALL MOST STABLE SAFE AND OK.
TOMORROW, RD WILL CHECK AGAIN AND REPORT TO SS MOTOR/GE.
2) PILOT PRODUCTION : 3,000 UNITS
WILL START AROUNF 25TH, JULY AND SS MOTOR WILL SHIP ON 5TH, AUGUST.
IT IS BY AIR CARGO.
IT IS FOR COMPENSATION OF LOST LEAD TIME.
3) MASS PRODUCTION
WILL START 20TH, AUGUST.
PREPARING
1) PACKING MATERIAL
2) RELATED QUALITY SPEC. STANDARD WITH INSPECTION METHOD
3) MATERIAL SCHEDULE TO BE REVIEWED AND UPDATED(PPG30% IS PROCEED 3 LOT AND OTHERS 2 MATERIAL IS 2 LOT)
4) QAV FOR INJECTION PROCESS
(WITH INSPECTION FACILITIES)
THANKS AND I WILL HAVE MEETING WITH RELATED BOD AND INJECTION
OH
THOẠI OI
SỐ ĐÓNG SPEC. . VỚI CẬP NHẬT
CHÚNG TÔI NÊN CHUẨN BỊ VẬT TƯ AS LỊCH.
CHÚNG TÔI SỬ DỤNG 2 LOẠI ĐÓNG HỘP. DEAR ALL LỤC KẾ HOẠCH CHO PHỤ BƠM MỚI GE. 1) HIỆN CÁC VẤN ĐỀ GIẢI QUYẾT: ĐẾN 17TH, 14 Tháng Bảy 2016 ARM VAN: GE SẼ FINISH ENDURANCE NGHIỆM SẼ THÀNH ĐẾN HÔM NAY. ĐẾN VỚI DOANH NGHIỆP, KHÔNG CẤP. Bánh công tác: TIÊM ĐƯỢC CỐ GẮNG CUỐI CÙNG . TẤT CẢ ỔN ĐỊNH NHẤT AN TOÀN VÀ OK TOMORROW, RD SẼ KIỂM TRA LẠI VÀ BÁO CÁO VỚI SS MOTOR / GE. 2) PILOT SẢN XUẤT: 3000 ĐƠN VỊ SẼ BẮT ĐẦU AROUNF 25TH, JULY VÀ SS MOTOR SẼ SHIP VỀ 5TH, tháng tám. ĐÓ LÀ CỦA AIR CARGO. ĐÓ LÀ CHO QUYỀN LỢI CỦA BỊ MẤT THỜI GIAN LEAD. 3) MASS SẢN SẼ BẮT ĐẦU 20TH, tháng tám. CHUẨN BỊ 1) PACKING LIỆU 2) LIÊN QUAN CHẤT LƯỢNG SPEC. TIÊU CHUẨN VỚI THANH TRA PHƯƠNG PHÁP 3) VẬT LỊCH ĐƯỢC xét và cập nhật (PPG30% LÀ PROCEED 3 LOT VÀ KHÁC 2 VẬT LIỆU LÀ 2 LOT) 4) QAV CHO QUÁ TRÌNH PHUN (VỚI THANH TRA CƠ SỞ) THANKS VÀ TÔI SẼ CÓ CUỘC HỌP VỚI HĐQT LIÊN QUAN VÀ TIÊM OH