The tendon profile is set-out and marked on the bottom formwork, or other fixed reference along the structure in accordance with the vertical and horizontal profiles specified on the shop drawings. (by Namcong) Each pre-fabricated tendons should be installed at the right position as per the shop drawing by means of manpower. (by Namcong) At the intersection points of horizontal and vertical direction tendons, the arrangement of multi- direction tendons should be checked carefully to make sure that they can meet the right profile. (by Namcong) After the pre-fabricated tendons have been installed at the right position, a plastic sleeve should be inserted to the casting of stressing end anchorage and whole tendon is pushed through casting and side of formwork up to the right length as per the shop drawing