Regarding the fast track for VT4 project, DHI was told from PMB “Mr. Thanh” as Project Director that DMPP would conduct EPC Works in an more efficiently way than previously done compared to VT2 project under the changed local regulation “Decree No. 15. 2013. ND-CP as attached. For example, if DMPP considered the attached local regulation for VT4 project, there are some advantages during the execution of VT4 project such as simplification of papering works as a part of the fast tract.After getting the information from PMB, We have looked into this matter to find out which kinds of specific advantage shall be applied for VT4 project. However, Doosan only found the limited advantage generally not specifically as minimizing papers works for quality management during engineering, construction and warranty period.