1. For every operation to be scheduled, the system checks whether there is enough remaining available capacity at the date determined. If the operation has sub-operations that are relevant for scheduling, then the system also looks for remaining available capacity for these.You can also specify an overload factor in capacity maintenance. It determines the extent to which remaining available capacity may be overloaded (above and beyond the normal available capacity).2. If there is sufficient available capacity then the system dispatches the operation.3. If there is insufficient capacity available, then the operation is moved to a date when it can be processed without capacity problems. You can specify the search direction in the strategy profile in Customizing. You define the period of time in which the system looks for remaining available capacity (the planning period) in the time profile in Customizing.