3.3 Typical analysis of project costs
As well as understanding the process by which cost estimates are calculated and how they may vary during construction, it is worthwhile having some understanding of how important the different cost elements are, and how sensitive they may be to a range of cost varying factors. The tables following this page provide a general analysis of the typical proportion of total project costs acccounted for by major cost elements.
The tables are not absolute benchmarks but are designed to guide desk officers in their general understanding of the relative significance of different cost elements and cost varying factors.
Table 1 provides estimates, for seven different types of infrastructure projects, of the typical proportion of total project cost that is accounted for by specific categories
of cost. A range is given to show how proportions may vary from project to project.
The matrix in Table 2 gives an indication of the degree to which some of the cost categories may change in response to the influences of the main cost-changing
factors identified. In this table, “Site Preparation” has been listed as a separate element of “Building & Construction” cost. This is because unexpected
problems with ground conditions most frequently impact on the cost of site preparation works.
The ranges given for the different categories making up initial costs, (Table 1), may enable desk officers to judge whether or not particular project submissions
need to be interrogated. If, for example, a project indicates that land purchase costs for a sewage treatment plant amount to 10% or more of total costs, a desk officer should be alerted to ask questions. This is because in typical projects of this nature, land purchase costs do not exceed 1% of total costs.
Again, if a project sponsor indicated that poor ground conditions was the reason that plant and machinery costs turned out to be higher, the desk officer would need to interrogate the project. This is because Table 2 shows that, typically, unforeseen ground conditions are only likely to significantly affect site preparation costs (part of the construction costs). Plant and machinery costs are most unlikely to be affected by this factor.

0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
3.3 Typical analysis of project costs As well as understanding the process by which cost estimates are calculated and how they may vary during construction, it is worthwhile having some understanding of how important the different cost elements are, and how sensitive they may be to a range of cost varying factors. The tables following this page provide a general analysis of the typical proportion of total project costs acccounted for by major cost elements.The tables are not absolute benchmarks but are designed to guide desk officers in their general understanding of the relative significance of different cost elements and cost varying factors.Table 1 provides estimates, for seven different types of infrastructure projects, of the typical proportion of total project cost that is accounted for by specific categoriesof cost. A range is given to show how proportions may vary from project to project.The matrix in Table 2 gives an indication of the degree to which some of the cost categories may change in response to the influences of the main cost-changingfactors identified. In this table, “Site Preparation” has been listed as a separate element of “Building & Construction” cost. This is because unexpectedproblems with ground conditions most frequently impact on the cost of site preparation works.The ranges given for the different categories making up initial costs, (Table 1), may enable desk officers to judge whether or not particular project submissionsneed to be interrogated. If, for example, a project indicates that land purchase costs for a sewage treatment plant amount to 10% or more of total costs, a desk officer should be alerted to ask questions. This is because in typical projects of this nature, land purchase costs do not exceed 1% of total costs.Again, if a project sponsor indicated that poor ground conditions was the reason that plant and machinery costs turned out to be higher, the desk officer would need to interrogate the project. This is because Table 2 shows that, typically, unforeseen ground conditions are only likely to significantly affect site preparation costs (part of the construction costs). Plant and machinery costs are most unlikely to be affected by this factor.
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
3.3 Phân tích tiêu biểu của chi phí dự án
Như cũng như hiểu rõ quá trình mà các dự toán chi phí được tính toán và làm thế nào họ có thể thay đổi trong quá trình xây dựng, nó là đáng giá có một số hiểu biết về tầm quan trọng của các yếu tố chi phí khác nhau, và làm thế nào họ có thể nhạy cảm với một loạt các chi phí khác nhau yếu tố. Các bảng sau đây Trang này cung cấp một phân tích tổng của tỷ lệ điển hình của tổng chi phí dự án acccounted cho bởi các yếu tố chi phí lớn.
Các bảng là điểm chuẩn không tuyệt đối nhưng được thiết kế để hướng dẫn cán bộ bàn trong sự hiểu biết chung của họ về tầm quan trọng tương đối của các yếu tố chi phí khác nhau và yếu tố chi phí khác nhau.
Bảng 1 cung cấp các ước tính, trong bảy loại khác nhau của các dự án cơ sở hạ tầng, các tỷ lệ điển hình của tổng chi phí dự án đó được hạch toán theo danh mục cụ thể
các chi phí. Một loạt được đưa ra cho thấy tỷ lệ như thế nào có thể thay đổi từ dự án để dự án.
Các ma trận trong Bảng 2 đưa ra một dấu hiệu cho thấy mức độ mà một số các loại chi phí có thể thay đổi để đáp ứng với những ảnh hưởng của chi phí thay đổi chính
yếu tố xác định. Trong bảng này, "Site Chuẩn bị" đã được liệt kê như là một yếu tố riêng biệt của "Xây dựng & Xây dựng" chi phí. Điều này là do bất ngờ
vấn đề với điều kiện mặt đất thường xuyên nhất tác động đến chi phí chuẩn bị mặt công trình.
Các phạm vi nhất định đối với các loại khác nhau làm tăng chi phí ban đầu, (Bảng 1), có thể cho phép nhân viên bàn để phán xét ​​hay không đệ trình dự án cụ thể
cần được thẩm vấn. Nếu, ví dụ, một dự án chỉ ra rằng chi phí mua đất cho một lượng nước thải nhà máy xử lý đến 10% hoặc nhiều hơn tổng chi phí, một nhân viên bàn giấy nên báo trước để đặt câu hỏi. Điều này là do các dự án tiêu biểu của thiên nhiên này, chi phí mua đất không vượt quá 1% tổng chi phí.
Một lần nữa, nếu một nhà tài trợ dự án chỉ ra rằng điều kiện đất nghèo là lý do mà chi phí nhà máy và máy móc hóa ra là cao hơn, các nhân viên bàn giấy sẽ cần phải thẩm vấn dự án. Điều này là do Bảng 2 cho thấy, thông thường, điều kiện đất bất ngờ là chỉ có khả năng ảnh hưởng đáng kể chi phí chuẩn bị mặt bằng (một phần của chi phí xây dựng). Chi phí nhà máy và máy móc không có khả năng nhất để bị ảnh hưởng bởi yếu tố này.

đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: