• Borrow pits for embankment material will be investigated and prepared all necessary documents to submit the Engineer for approval including taking soil sample at borrows pit and testing in laboratory and the like.• The Contractor will mobilize Equipment and Materials to site.• The compaction will be carried out using proposed equipment and method statement approved by the Engineer.• Before starting embankment work on site, the Contractor will establish control point system to support for embankment works. Existing ground will be surveyed by The Contractor and confirmed by The Engineer in writing.• Temporary access shall be made following the correct sequencing of work execution.• The workers will be briefed about safety matters.• Communication on Site will be conducted via mobile phones and walkie-talkies.