MEMORANDUM OF UNDERSTANDING ON

The Delivery – Acceptance of services for leveling sand pump to the building site along National Road 1 at Kilometer No. 53, geographically located in Kampong Phnom and Preaek Tonloap Communes, Leuk Daek District, Kandal Province, on land area ……….…………… (…………………………thousand) Hectares and on the project construction contract within the above mentioned city development building site.



No.: …………………… Phnom Penh, January 20th, 2014



This agreement is executed by


Between


- The Company: LY PICH SAMNANG APHIVATH CO., LTD.

- Represented by: Mrs.LY NARY
- Passport No.: ……………………………………………………………………………………………………………………..
- Office address: ……………………………………………………………………………………………………………..……
- Telephone/desk phone: ………………………………………………………………………………………………..…..
-Email:…………………………………………………………………………………………………………………………………
- Name of bank: ……………………………………………………………………………………………………….………….
- Address: …………………………………………………………………………………………………………………………….
- Account name: …………………………………………………………………………………………………..………………
- SWIFT: ………………………………………………………………………………………………………………….……………
- Bank telephone: …………………………………………………………………………………………….…………………..
- Bank fax: …………………………………………………………………………………………………………………………….

The principal, hereinafter referred to as Party “A”



And


- The Company: BANG ZHOU MARINE ENGINEERING CO., LTD



- Represented by: MR.CHEN CHUAN YUNG
- Passport No.: ……………………………………………………………………………………………………………………….
- Office address: ……………………………………………………………………..............
- Telephone/desk phone: ……………………………………………………………………………………………………….
- Email:…………………………………………………………………………………………………………………………………..
- Name of bank: ……………………………………………………………………………………………………………………..
- Address: ……………………………………………………………………………………………………………………………….
- Bank account No.: ………………………………………………………………………………………………………………..
- SWIFT: ………………………………………………………………………………………………………………………………….
- Bank telephone: …………………………………………………………………………………………………………………..
- Bank fax: ………………………………………………………………………………………………………………………………

The contractor, hereinafter referred to as Party “B”



References:
- Letter of Authorization No.: ………………..….. dated ……….………….. of the Council of Ministers,
- Sub-decree No.: ………………… dated ……………………………., 2012, on the Investment Approval,
- Partnership Agreement No.: …………………………………………………………………………………………….
- Record of Inspection of Sand Dredging Machineries is ……………, dated ………………….., 2013
Now therefore, the two Parties hereby agree on the following terms and conditions: Article 1: Purpose of this MOU

1.1. This Agreement sets forth the memorandum of understanding on the delivery- acceptance of services of sand pumping to the reclamation site and for the construction project in the so-called development site. In this agreement,
- Party “A” as the Principal
- Party “B” as the contractor to provide the sand dredging and construction services (canal,
canal bank, road, bridge, housing residents, factory, drainage system…)

1.2. Party “A” agrees to award the contract for provision of services of sand dredging to the reclamation site on …………………(………………………thousand) hectares to conduct the feasibility study of the construction project (canal, edge of the canal, road, bridge, factory and residential buildings…) as well as of the infrastructures existing within the said development project which is geographically located on National Road 1 at kilometer No. 53 in Kandal province’s Kampong Phnom and Preaek Tonloap Communes, Leuk Daek District.

1.3. The two Parties mutually agreed on the service fee for sand pumping to the reclamation site at ……………… USD (………………………………...dollars) per cubic meter with a distance to be



calculated form the dredging site to the end of the reclamation site boundary; the length of which shall be no more than 13km.

1.4. Upon completion of the sand pumping, filling in and leveling of the site to the same level of National Road 1 by Party “B”, Party “B” shall proceed with the feasibility study of the construction project; the duration of which shall be for 20 (Twenty) days. Upon completion of the project feasibility study by Party “B” in collaboration with the agents and qualified engineers named by Party “A”, Party “B” shall present the report of Bill of Quantity (BQQ), samples and technical specifications and engineering materials to Party “A”. And within 9 working days after the submission of the project feasibility study documents to Party “A”, the two Parties shall agree on the date to determine the possibility of study on the construction contractor agreement and the signing of the contract on the following date.
Both Parties shall discuss and adopt the plan stating the followings:
- The payment guaranty
- The phases of payment
- The construction and compliance with the standard for such construction
- The warranty on construction quality
-Technical, material and engineering practice
- The compliance with the law on construction and other laws covering the development in this area.
1.5. The canal rehabilitation and building of edge of the canal shall be commenced during
the sand dredging operation for the reclamation site in order to avoid the sand from flowing into the dug canal site (the project of canal rehabilitation and building of edge of the canal, which is attached as Annex 1 to the contract on sand pumping for the reclamation site).

1.6. Party “B” shall conduct a field study on the sand mining site and the site to which the dredging machineries are to be transported, inspect the site where the pipeline is to be installed and conduct the evaluation before the report is to be finally submitted to Party “A”.

Article 2: Development Project Site, duration of the project study and evaluation

2.1. Site: The development project is located on along National Road 1 at Kilometer No. 53, geographically located in Kampong Phnom and Preaek Tonloap Communes, Leuk Daek District, Kandal Province.

2.2. Duration of the Study: Party “B” shall complete the project study within a period of 20 (Twenty) days following the confirmation in approval by Party “B” of Party “A”’s source of capital.

In case Party “B” reasonably believes it cannot complete the project study within the schedule set above, Party “A” shall be notified in order to negotiate on the delay of the study for any appropriate period and to give time for Party “A” to decide on the extension of the project study as proposed by Party “B”.

2.3. Fees for the project study: The service fees shall cover the followings:
o The study on the sand pumping site
o The study on the canal rehabilitation project
o The study on edge of the canal building project



o The study on the road construction and establishing gardens along the canal project
o The study on bridge construction project
o The study on drainage-sewage system and waste water treatment plant project

Party “B” shall cover the costs for study on any project chosen by Party “B”.


Article 3: Responsibilities of Party “A”

3.1. To present to Party “B” any legal documents concerning the development project;

3.2. To provide cooperation and coordination for Party “B” during the project study period
covered under this agreement;

3.3. To be liable for due and timely payment according to the schedule set in the sand pumping contract and construction contractor agreement, respectively;

3.4. To furnish the regional map pointing out the development project site and construction plan as specified in the project.

Article 4: Responsibilities of Party “B”

4.1. To conduct study for each project as instructed by Party “A”,

4.2. To study the project and prepare report on the study progress for Party “A”,

4.3. To issue the list of equipments, machineries and staffs to Party “A”,

4.4. To issue confirmation of the financial capacity of contract for sand Party “A”, which is a must, upon the signing of contract for sand pumping to the reclamation site and/ or of the construction contractor agreement,

4.5. To be responsible for ensuring both the quality and safety meets the international standard during the construction.

ARTICLE 5 : The Capital 's Party " A "

5.1. The Capital 's the " A " grade for party " B " shall be checked through the list of account development project of CJCD City Development Co., Ltd. one hour before the signing of Memorandum of Agreement (MOA) for contractors leveling sand pump and construction.


ARTICLE 6 : Capital sources secured for the leveling sand pump and constructions of the “B"

6.1. Capital sources secured for the leveling sand pump:

Party " B " is not elevated amount of items to ensure the leveling sand pump but party " B " to make sure of the possibility and potential of the construct
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
COMMUNITY DEVELOPMENT CAM-JAP Yukio SUZUKI COMPANY DEVELOPMENT LIMITED CJCD CITY --- ---  MEMORANDUM DATE The delivery-acceptance of services for leveling sand pump to the Construction sites along the National Road 1 at km 53, geographically located in Kampong Phnom and Preaek Tonloap town, district Leuk Daek District, Kandal province, in an area ... (... thousands) Ha and Contract on construction projects in the city mentioned developers build the site. No .: ........................ Phnom Penh, January 20, 2014 This agreement was made ​​by mid -Company: LY Pich Samnang APHIVATH CO., LTD. -Great By: Mrs.LY airport nary - Passport No .: Address: ... -Telephone electricity Name of bank: Address: Account name: SWIFT: phone line: ... - Bank Fax: Director, hereinafter referred to as "A" and -Corporate: hydro chu technical BANG CO., LTD -Great represented by: Mr. CHEN YUNG CHUAN - Passport No .: Address: ... -Telephone phone / desk: ... -- Name of bank: ……………………………………………………………………………………………………………………..- Address: ……………………………………………………………………………………………………………………………….-Tài khoản ngân hàng số:...- SWIFT: ………………………………………………………………………………………………………………………………….-Ngân hàng điện thoại:...- Bank fax: ………………………………………………………………………………………………………………………………Các nhà thầu, sau đây gọi tắt là bên "B"Tài liệu tham khảo:-Thư ủy quyền số:... ngày... Hội đồng bộ trưởng,-Tiểu nghị định số:... ngày..., 2012, phê chuẩn đầu tư,-Quan hệ đối tác hợp đồng số:...-Hồ sơ kiểm tra của cát nạo vét máy móc là..., ngày..., 2013Bây giờ, do đó, hai bên hướng đồng ý về các điều khoản sau đây và điều kiện: điều 1: mục đích của biên bản ghi nhớ này1.1. thỏa thuận này nêu ra bản ghi nhớ ngày giao hàng chấp nhận các dịch vụ của cát bơm để cải tạo trang web và cho các dự án xây dựng cái gọi là phát triển trang web. Trong thỏa thuận này,-Bên "A" là hiệu trưởng-Bên "B" là các nhà thầu cung cấp các cát nạo vét và xây dựng Dịch vụ (kênh đào,Kênh ngân hàng, road, bridge, cư dân nhà ở, nhà máy, Hệ thống thoát nước...)1.2. bên "A" đồng ý trao hợp đồng cung cấp dịch vụ nạo vét để các trang web cải tạo trên cát... (... nghìn) ha để tiến hành nghiên cứu tính khả thi của dự án xây dựng (kênh, cạnh của kênh đào, đường, cầu, nhà máy và nhà ở...) cũng như của các cơ sở hạ tầng sẵn có trong sự phát triển cho biết dự án mà về mặt địa lý nằm trên Quốc Road 1 tại km số 53 trong tỉnh Kandal Kampong Phnom và Preaek Tonloap xã, Leuk Daek huyện.1.3. những hai bên cùng đồng ý theo chi phí dịch vụ cho cát bơm vào các trang web cải tạo lúc... USD (... đô la) mỗi mét khối với một khoảng cách phải tính toán hình thức trang web dredging đến đầu của ranh giới trang web cải tạo; chiều dài của mà phải không nhiều hơn 13km.1.4. sau khi hoàn thành cát bơm, điền vào và San lấp mặt bằng của các trang web để cùng một mức độ quốc gia Road 1 bên "B", bên "B" sẽ chỉ tiến hành nghiên cứu tính khả thi của dự án xây dựng; thời gian mà chỉ cho 20 (hai mươi) ngày. Sau khi hoàn thành dự án nghiên cứu tính khả thi của các bên "B" in hợp tác với các đại lý và kỹ sư có trình độ được đặt theo tên của bên "A" bên "B" sẽ chỉ trình bày các báo cáo của Bill số lượng (BQQ), mẫu và thông số kỹ thuật và kỹ thuật vật liệu để bên "A". Và trong 9 ngày làm việc sau khi nộp tài liệu nghiên cứu tính khả thi của dự án để bên "A", hai bên sẽ chỉ đồng ý vào ngày để quyết các khả năng nghiên cứu về các nhà thầu xây dựng và phải ký thỏa thuận về hợp đồng sau ngày.Cả hai bên sẽ chỉ chấp nhận kế hoạch thảo luận và nêu rõ các sau: -Các khoản thanh toán bảo lãnh -Các giai đoạn thanh toán -Xây dựng và tuân thủ các tiêu chuẩn cho các ' xây dựng -Bảo hành về chất lượng xây dựng -Kỹ thuật, vật liệu và kỹ thuật thực hành -Phù hợp với pháp luật xây dựng trên và pháp luật khác trong lĩnh vực này, bao gồm sự phát triển. 1.5. kênh phục hồi chức năng và xây dựng của các cạnh của các kênh sẽ chỉ là chính thức đi vào khithe sand dredging operation for the reclamation site to avoid the sand print order from flowing Into the dug canal site (the project of canal Rehabilitation and building of the edge of the canal, mà is attached as Annex 1 to the contract on pumping sand for the reclamation site). 1.6. Party "B" shall only CONDUCT a field study on the sand mining site and the site to đó dredging are to be transported Machineries, inspect the site where the pipeline is to be installed and the evaluation CONDUCT trước report is to be finally submitted to Party "A". Article 2: Project Site Development, the duration of the project study and evaluation 2.1. Site: The development project is located on National Road 1 at Kilometer along No. 53, geographically located in Kampong Phnom and Preaek Tonloap Communes, Leuk Daek District District, Kandal Province. 2.2. Duration of the Study: Party "B" shall only complete the project a period of 20 study trong (Twenty) days sau print the confirmation approval by Party "B" of Party "A" 's source of capital. In case Party "B" reasonably Believes it can not complete the project study trong schedule set above, Party "A" shall only be Notified print order to negotiate on the delay of the study for any the appropriate period and to give time for Party "A" to decide on the extension of the project study as proposed by Party "B". 2.3. Fees for the project study: The service fees shall only cover the followings: o The study on the sand pumping site o The study on the canal Rehabilitation project o The study on edge of the canal building project o The study on the road construction and lập gardens along the canal project o The study on bridge construction project o The study on drainage-sewage system and waste water treatment plant project Party "B" shall only cover the Costs for study on any project Chosen by Party "B". Article 3: Responsibilities of Party "A" 3.1. To present to Party "B" Concerning any legal documents the development project; 3.2. Cooperation and Coordination for cung To Party "B" khi the project study period Covered under this agreement; 3.3. To be liable for vì and Timely payment theo schedule set in the sand pumping and construction contractor contract agreement, respectively; 3.4. To furnish the regional map pointing out the development project site and construction plan in the project as rõ. Article 4: Responsibilities of Party "B" 4.1. To study for each project CONDUCT as instructed by Party "A", 4.2. To study the project and prepare the report on the study progress for Party "A", 4.3. To issue the list of equipments, Machineries and staffs to Party "A", 4.4. To issue confirmation of the Financial Capacity of contract for sand Party "A", mà is a must, upon the signing of contract for sand pumping to the reclamation site and / or of the construction contractor agreement, 4.5. To be responsible for the quality and safety Ensuring cả meets the international standard the construction khi. ARTICLE 5: The Capital 's Party "A" 5.1. The Capital 's the "A" grade for party "B" shall only be checked through the list of account development project of CJCD City Development Co., Ltd. One hour is before the signing of Memorandum of Agreement (MOA) for leveling sand pump and construction Contractors. ARTICLE 6: Capital sources secured for the leveling sand pump and constructions of the "B" 6.1. Capital sources secured for the leveling sand pump: Party "B" is not elevated amount of items to Ensure the leveling sand pump but party "B" to make sure of the Possibility and Potential of the construct
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!




CAM-JAP SUZUKI Yukio COMMUNITY DEVELOPMENT
CJCD CITY DEVELOPMENT, LTD. ---- ----  MEMORANDUM ON The Delivery - Acceptance of services for leveling sand pump to the page construction site along Highway 1 at Kilometer 53. No, geographically located in Kampong Phnom commune and Preaek Tonloap, Leuk Daek District, Kandal province, in the area .......... ..... .......... (.............................. thousand) hectares and the project. construction contracts in the construction development of the city mentioned above No.: ........................ Phnom Penh, day January 20, 2014 the agreement was implemented by mid - Company: .. LY Pich Samnang APHIVATH CO, LTD - Represented by: Mrs.LY nary - Passport No.: Office Address: Telephone / mobile Goal: Bank Name: Address: Name: SWIFT: Bank Telephone: Bank Fax: Principal, hereinafter referred to as the "A" and - the company :. ZHOU BANG MARINE ENGINEERING CO, LTD - Representative: MR.CHEN CHUAN Yung - Passport No.: Office address: ........................ .................................................. .... .............. - Phones / table: Bank Name: Address: Bank account No.: SWIFT: Bank Telephone: Fax Bank: contractors, hereinafter referred to as the "B" Reference: -. Authorization Letter No.: .................. .. ... .. ......... .......... Day .. .. of the Council of Ministers, - Sub-Decree No.: ..................... Date ........... ......................, 2012, on the approval of investment ,. - Partnership Agreement No.: Record of Sand Dredging Inspector Machines Equipment is ..............., ..................... .. day, 2013 So now, two parties agree on the terms and conditions: Article 1: The purpose of this MOU 1.1. This Agreement sets out the memorandum on service delivery- acceptance pumping sand into rehabilitation sites and for projects Construction projects in the so-called development site. In this agreement, - The "A" as Principal - The "B" is the contractor to supply the dredging of sand and construction services (canals, shore canals, bridges, roads, residential houses, factories, water supply and drainage systems ...) 1.2. The "A" agreed the contract service provider dredging sand to renovating the site. .................... (........................... thousands) ha to conduct feasibility studies of construction projects (ditches, canals, roads, bridges, factories and residential buildings ...) as well as the existing infrastructure in the development projects that it is geographically located on Highway 1 at km 53 in the Kampong Kandal and Phnom commune Tonloap Preaek, Leuk Daek District. 1.3. Both parties mutually agreed on service fee for pumping sand on the page .................. web renovated in USD (.......................... .......... ... dollars) per cubic meter with a distance is calculated form the dredging site until the site boundary renovated; the length of which must not exceed 13km . 1.4. After completion of the injection of sand, fill and leveling of the site to the National Highway 1 Party "B", Party "B" to conduct a feasibility study of construction projects; during that period will be for 20 (twenty) days. After completion of the project feasibility study of the Party "B" in cooperation with agents and engineers qualified to be named by the Party "A" Party "B" will present the report of the Bill of Quantity (BQQ), templates and specifications and technical materials Party "A". And within 9 working days after the submission of research papers feasibility project for the "A", the two sides will agree on the date for determining the ability of the agreements research building contractors and contracting on the day after. The two sides will discuss and adopt plan stating the following: - The guarantee of payment - payment Phases - The construction and adherence to building standards so - The warranty on the construction quality -Technical, animals technical and practical data - Observance of construction law and other legislation including the development in this field. 1.5. The rehabilitation of the channel and build the edges of the channel will be kicked off in the evacuation operation dredge sand for reclamation site to prevent sand flowing into the site of the canal (canal renovation project and build the canal edge, which is attached in Annex 1 of the contract for the site sand pump reclamation). 1.6. The "B" will conduct a field study on sand mining areas and sites where machinery dredge is being transported, check the site where the pipeline will installed and evaluated before the final report was submitted to the Party "A". Article 2: Project Web Site Development, time study and evaluation of projects 2.1. Site: Projects Development is located on Highway 1 along at Kilometer 53, located in Kampong Phnom geographical and social Preaek Tonloap, Leuk Daek District, Kandal province. 2.2. Time study: The "B" to complete the research project within 20 (twenty) days after confirmation by the Party in the "B" of the Party "A" of the capital. In the event that the "B" reasonably believes that it can not complete the research project plan established above, the Party "A" will be announced to negotiate about the delay of the study for any length of time appropriate to the time for the Party "A" to decide on the term research project at the request of the Party "B". 2.3. The fee for the research project: The cost of services will include the following: o The research on site pumping sand o Studies renovation project at the channel 's edge o Studies on canal construction projects o Research road construction and establish gardens along the canal project o The study of bridge construction projects o Research the sewerage system and wastewater-plant projects sewage Party "B" include the costs for study of any project selected by the Party "B". Article 3: Responsibilities of Party "A" 3.1. In order to present the Party "B" any legal documents related to the project development; 3.2. To provide for cooperation and coordination with the Party "B" during study projects covered under this agreement; 3.3. Responsible for timely payments according to the schedule specified in the contract agreement pump sand and building contractors, respectively; 3.4. To provide area maps pointed out the sites and construction project development plan as defined in the project. Article 4: Responsibilities of the "B" 4.1. In order to conduct research for each project under the guidance of the Party " A " 4.2. In order to study the project and prepare a report on the progress of the research for the Party "A", 4.3. Issuing lists of equipment, machinery and staff to the "A", 4.4. Issued confirmation of financial capacity of contract for sand Party "A", which is right, after signing the contract to pump sand to renovating the site and / or agreement of the builders, 4.5 . Responsible for ensuring both quality and safety to meet international standards in the construction process. Article 5: The Party Capital 's "A" 5.1. The capital of the "A" level to the "B "will be checked through a list of development projects account CJCD City Development Co., Ltd. an hour before signing the Memorandum of Agreement (MOA) to contractors leveling sand pump. and construction Article 6: The capital guaranteed for the pump sand leveling and works of "B". 6.1 The capital guaranteed for pump leveling sand: The "B" is not high number of items to ensure leveling sand pump but the "B" to ensure the capability and potential of the building



























































































































































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2025 I Love Translation. All reserved.

E-mail: