Next cycle then proceeds at time 6, right after the finish of B. Accordingly, eligible activities are: J ( continuing from previous cycle ); D ( delayed from previous cycle); and G and F ( successors of B ).After sorting with respect to the late-start values and considering these tasks one by one, G and F could start, while D was delayed .