- Song Da (PVSD) has installed 2638 out of 2647 piles in total and there were 10 piles, which did not meet the design elevation. (Storage 1)- PVC Thai Binh has installed 2061 out of 2570 piles in total and there were 3 piles, which did not meet the design elevation. (Storage 2)- On 23 August 2015, PVSD and PVC-TB temporally stopped because Minh Duc stopped providing pile.- DHV conducted test for 14 piles in Storage 1&2 (following initial designed positions), they are conducting the static load tests for the piles, which were PDA tested before (following TB2PP approval).