PROJECT TITLE: Ho Chi Minh City Urban Railway Construction Project
Ben Thanh - Suoi Tien Section (Line 1)
Construction Package 2 : Civil(Elevated & Depot)
Method Statement of Bored Pile Construction


REVISION STATUS
REV. No. DATE DESCRIPTION REMARKS







PREPARED BY CHECKED BY APPROVED BY
NAME
SIGNATURE
DATE


TABLE OF CONTENTS

1 INTRODUCTION 4
1.1 GENERAL 4
1.2 WORK SCOPE 4
2 CONSTRUCTION PROCEDURE 4
2.1 WORK FLOW-CHART 4
2.2 WORK PROCEDURE 6
(1) Preparation Works 6
(2) Setting center point of the bored piles 7
(3) Assembling Guide frame 8
(4) Setting of the temporary casing 8
(5) Drilling work 9
(6) 1st Cleaning bottom of the holes & Change Bentonite 12
(7) Reinforcement fabrication and Installation of the rebar cage 12
(8) Setting of Tremie Pipe and Re-cleaning (2nd Time Clearing) of Borehole 14
(9) Casting concrete 15
(10) Removal of Temporary Casing 17
3 RESOURCES TO BE USED 18
3.1 EQUIPMENT TO BE USED 18
3.2 ORGANIZATION 19
4 CONTINGENCY AND SOLUTION 20
4.1 CONTINGENCY OF DRILLING WORK 20
4.2 CONTINGENCY OF SUCCESSIVE WORK 21
5 QUALITY CONTROL 21
5.1 QUALITY CONTROL 21
5.2 ORGANIZATION / STAFF 21
5.3 PILOT PILE INSPECTION AND TEST 22
5.4 TOLERANCE OR RANGES 25
5.5 INSPECTION AND TEST PERSONNEL 25
5.6 LABORATORY 25
5.7 QUALITY CONTROL PLAN FOR BORED PILING WORKS 26
6 HEALTH, SAFETY AND ENVIRONMENT 27
6.1 HSE TRAINING 27
6.2 PPE 27
6.3 TOOL BOX MEETING (TBM) 27
6.4 HSE INSPECTION 27
6.5 SAFETY CONTROL MEASURES 28
(1) Crane and Heavy Equipment Control 28
(2) Electrical Works 28
(3) Fire Fighting Equipment and Fire Prevention 28
6.6 ENVIRONMENTAL CONTROL MEASURES 28
(1) Water Pollution Control 28
(2) Protection of Air Quality 29
(3) Noise Control 29
(4) Others 29
7 EMERGENCY RESPONSE CHART 31

































1 INTRODUCTION

1.1 GENERAL

The objective of this method statement is to describe the construction methodology and procedure for piling work for pilot pile of HCMC Metro Project. 6 Bored piles are to be provided as pilot pile.

The bored pile construction technique to construct independent circular cast insitu reinforced piles from the designed depth to the designed cut-off level.

Required site management controls for cast-in-place concrete piling works by using Earth Drilling Machine (Auger Drilling Method). The sizes of the piles to be covered by this method statement are diameter 1500mm, 1200mm & 1000 mm.


1.2 WORK SCOPE

This method statement includes below scope of works.

- Drilling works : D=1,500mm, 1200mm & 1000 mm.

- Installation of Rebar Cage

- Casting Concrete


Temporary steel casing of +50~100mm size of the bored pile will be installed. The boring works will carry out until the designated toe level. Borehole is filled with Bentonite once the boring works commenced.

Upon completion of the boring works, the reinforcement cage will be lowered into the borehole. Perform cleaning borehole before the installing of reinforcement cage, the casting of the bored piles will then take place.

Bored piles with different diameters and lengths will be constructed in accordance to the construction drawings.


2 CONSTRUCTION PROCEDURE

2.1 WORK FLOW-CHART

The work sequence of the pile construction is depicted by the following flow-chart.
































































The following diagram shows the continuous sequence of bored piling works






















Fig.1 Sequence of Bored Piling Works



2.2 WORK PROCEDURE

The detail work procedure is described as follows.

(1) Preparation Works

Prior to the commencement of the Cast-in-place concrete piling works, the site will be cleared and leveled to stand the weight of Bored Piling Machine without any obstacles at the surface of the ground. And if it is not sufficient enough to stand the weight of Bored Piling Machine, steel plate will be placed to serve as equipment working platform.
Bentonite mixing tank will be installed for easy maintenance of the tank including connection of pipe or hose to supply bentonite for the bored pile location. It will be checked from time to time for the bentonite slurry for possible spillage as per environmental requirement.
Typical setting layout of equipment and facilities for bentonite solution are shown below.













































* This layout could be changed according to site condition

Fig.2 Setting layout of equipment and facilities



(2) Setting center point of the bored piles

Positioning drilling pit is based on the design documents, positioning benchmarks and piling arrangement layout for specifying positions of pile’s centre in compliance with the designs. Specifying the position of the pile’s centre is performed by 02 geodetic theodolite or electronic theodolite. Consulting engineers shall inspect and take acceptance of positioning after completion

In addition, subsidiary benchmarks shall be set up by steel piles for direction of pile’s center and the pile’s centre shall be checked again upon sinking temporary well casing. These positions shall be protected and maintained until sinking and completing inspection of the well casing.












Fig.3 Setting center of Bored pile

(3) Assembling Guide frame

Assembling guide frame will be prepared before Setting of the temporary casing.

(4) Setting of the temporary casing

Bored pile construction will be commenced from setting out pile location, pre-drill and install temporary casing. The length of the casing will be considered and justified based on the soil condition and underground water level for maintaining the stability of the pile excavation against collapse. The top of temporary casing will be extended about 1.0meter above the ground level.

In installation of temporary casing, the verticality and stability of it will be checked and non-movement during drilling. Inner diameter of casing pipe will be little larger at least 5 ~ 10cm than borehole diameter. The casing will be plumbed and checked for eccentricity against reference pegs, or it will be checked with survey equipment at the top of the casing with the same elevation aside from the location frame installed above ground level.

Fig.4 Installation of temporary casing

(5) Drilling work

The design length of piles will be designed by the Designer. During drilling excavation, all holes for cast-in-place concrete pile should be excavated to the design length. Excavated holes will be protected from collapse by the provision of using bentonite and temporary steel pipe casing.




Fig.5 Casing




Fig.6 Casing


a) Bentonite slurry

During drilling excavation of borehole, the soil will be protected from collapse by the provision of using bentonite slurry and temporary steel pipe casing. Prior to drilling works, the stabilization liquid as the bentonite suspension will be prepared and tested to meet the criteria which will be proposed before commencement..

Bentonite will be mixed thoroughly with clean fresh water to make a suspension which will maintain the stability of the pile excavation for the period of casting concrete and complete construction. Dry powder Bentonite is mixed with clean water according to required ratio by mixing machine and stored in the tanks which will supply to bored hole. The drilling fluid properties will be measured taking samples before concreting. The density of freshly mixed bentonite suspension will be measured as a check on the quality of the suspension being formed.


b) Setting up of Bentonite Plant

The following are the various stages of works in the setting up of site facilities:


Setting up

 Setting up of bentonite plant facilities.
 Preparation and levelling of ground.
 Installation of bentonite silos
 Installation of desander unit.
 Layout of bentonite and water piping systems.
 Pre-mixing of bentonite slurry on site.


c) Bentonite Slurry Mix Design

Basic functions of bentonite is to act as a stabilizing agent for the borehole.
In soil with high clay content, the bentonite slurry becomes very thick during excavation due to the suspended clay particles. The thick slurry becomes difficult to pump for desanding. To avoid this problem, a polymer / sodium bi-carbonate is added to the slurry.



d) Testing Bentonite Slurry

Bentonite Slurry Test – Initial

The following tests will be conducted on bentonite slurry at initial and during excavation, results will be submitted.
1. Viscosity test - test on site

2. Sand Content – test on site

3. Density test - test on site

4. pH meter test - test on site

Bentonite Slurry Test - Prior to concreting but after desanding.

The following tests will be conducted on bentonite slurry after completion of desanding.
1. Viscosity test - test on site

2. Sand Content – test on site

3. Density test - test on site

3. pH meter test - test on site

The drilling fluid properties shall be measured taking samples at different depths before concreting. All checking of bentonite slurry shall be carried out complying with the criteria proposal. The measuring device shall be calibrated to read to within 0.01gm/ml.


Fig.7 Bentonite Slurry



e) Drilling works

From the ground level to one meter above the toe of the temporary casing will be drilling without stabilization liquid (bentonite). The measurement of the depth of drilling bucket shall be closely monitored when it get near to the toe of the casing.
After putting bentonite into the borehole, drilling work will be continued and the top level of it will be maintained more 2.0m higher than ground water level or 1.0m higher than ground level for prevention of cave-ins or borehole collapses.

Based on the soil profile, drilling rate is adjustable in order to maintain the drilling accuracy.

During the drilling work, the verticality of drill will be checked by plumb with string line or theodolites from two directions in 90 degree. And the depth of borehole will
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
Dự án tiêu đề: dự án xây dựng đường sắt đô thị TP. Hồ Chí MinhBến thành - Suoi Tien phần (tuyến 1)Xây dựng gói 2: Civil(Elevated & Depot)Phương pháp tuyên bố của chán đống xây dựngXEM TRẠNG THÁIRev số NGÀY MÔ TẢ NHẬN XÉT CHUẨN BỊ BẰNG CÁCH KIỂM TRA BỞI SỰ CHẤP THUẬN CỦATên CHỮ KÝ NGÀY BẢNG NỘI DUNG1 GIỚI THIỆU 41.1 TỔNG QUÁT 41.2 PHẠM VI CÔNG VIỆC 42 XÂY DỰNG QUY TRÌNH 42.1 CÔNG VIỆC FLOW-CHART 42.2 CÔNG VIỆC THỦ TỤC 6(1) để chuẩn bị công trình 6(2) thiết lập Trung tâm điểm của cọc 7(3) tập trung hướng dẫn khung 8(4) cài đặt tạm thời vỏ 8Công việc khoan (5) 9(6) 1 hấp dưới cùng của lỗ & thay đổi Bentonite 12(7) tăng cường chế tạo và lắp đặt của cốt thép lồng 12(8) thiết lập của Tremie ống và tái làm sạch (2 thời gian giải phóng) của giếng khoan 14(9) đúc bê tông 15(10) loại bỏ tạm thời vỏ 173 TÀI NGUYÊN PHẢI ĐƯỢC SỬ DỤNG 183.1 THIẾT BỊ PHẢI ĐƯỢC SỬ DỤNG 183.2 TỔ CHỨC 194 PHÒNG HỜ VÀ GIẢI PHÁP 204.1 PHÒNG HỜ CỦA CÔNG VIỆC KHOAN 204.2 CONTINGENCY KẾ TIẾP LÀM VIỆC 21KIỂM SOÁT CHẤT LƯỢNG 5 215.1 KIỂM SOÁT CHẤT LƯỢNG 215.2 TỔ CHỨC / NHÂN VIÊN 215.3 ĐỐNG THÍ ĐIỂM KIỂM TRA VÀ THỬ NGHIỆM 225.4 KHOAN DUNG HOẶC PHẠM VI 255.5 NHÂN VIÊN KIỂM TRA VÀ THỬ NGHIỆM 255.6 PHÒNG THÍ NGHIỆM 255.7 KIỂM SOÁT CHẤT LƯỢNG KẾ HOẠCH CHO CHÁN XI MĂNG ĐẤT HOẠT ĐỘNG 266 Y TẾ, AN TOÀN VÀ MÔI TRƯỜNG 276.1 HSE ĐÀO TẠO 276.2 PPE 276.3 CUỘC HỌP HỘP CÔNG CỤ (TBM) 276.4 KIỂM TRA HSE 276.5 BIỆN PHÁP KIỂM SOÁT AN TOÀN 28Cần cẩu (1) và kiểm soát thiết bị nặng 28(2) điện công trình 28(3) cháy thiết bị và phòng cháy 286.6 CÁC BIỆN PHÁP KIỂM SOÁT MÔI TRƯỜNG 28(1) nước kiểm soát ô nhiễm 28(2) bảo vệ chất lượng không khí 29(3) kiểm soát tiếng ồn 29(4) khác 29BẢNG XẾP HẠNG PHẢN ỨNG KHẨN CẤP 7 311 GIỚI THIỆU1.1 TỔNG Mục tiêu của báo cáo phương pháp này là để mô tả các phương pháp xây dựng và các thủ tục đóng cọc làm việc cho đống thí điểm của dự án tàu điện ngầm TP. Hồ Chí Minh. 6 cọc cọc phải được cung cấp như là phi công đống.Kỹ thuật xây dựng cọc chán để xây dựng độc lập tròn đúc đo gia cố cọc từ đáy được thiết kế để cấp độ được thiết kế cắt.Yêu cầu trang web quản lý điều khiển cho diễn viên tại chỗ bê tông xi măng đất công trình bằng cách sử dụng trái đất máy khoan (họ khoan phương pháp). Các kích thước của các cọc được bao phủ bởi phương pháp tuyên bố này có đường kính 1500mm, 1200mm & 1000 mm. 1.2 PHẠM VI CÔNG VIỆCNội dung phương pháp này bao gồm dưới đây các phạm vi của tác phẩm.-Khoan tác phẩm: D = 1, 500mm, 1200mm & 1000 mm.-Cài đặt của cốt thép lồng-Đúc bê tôngTạm thời vỏ bọc thép của 50 ~ 100 mm Kích thước của đống chán sẽ được cài đặt. Các tác phẩm nhàm chán sẽ thực hiện cho đến khi cấp khu vực cho phép ngón chân. Giếng khoan được làm đầy với Bentonite một khi các tác phẩm nhàm chán bắt đầu.Sau khi hoàn thành các tác phẩm nhàm chán, tăng cường lồng sẽ được hạ xuống giếng khoan. Thực hiện làm sạch sâu trước khi cài đặt của tăng cường lồng, đúc các cọc sau đó sẽ diễn ra.Bored piles with different diameters and lengths will be constructed in accordance to the construction drawings.2 CONSTRUCTION PROCEDURE2.1 WORK FLOW-CHARTThe work sequence of the pile construction is depicted by the following flow-chart.The following diagram shows the continuous sequence of bored piling worksFig.1 Sequence of Bored Piling Works2.2 WORK PROCEDURE The detail work procedure is described as follows.(1) Preparation WorksPrior to the commencement of the Cast-in-place concrete piling works, the site will be cleared and leveled to stand the weight of Bored Piling Machine without any obstacles at the surface of the ground. And if it is not sufficient enough to stand the weight of Bored Piling Machine, steel plate will be placed to serve as equipment working platform.Bentonite mixing tank will be installed for easy maintenance of the tank including connection of pipe or hose to supply bentonite for the bored pile location. It will be checked from time to time for the bentonite slurry for possible spillage as per environmental requirement. Typical setting layout of equipment and facilities for bentonite solution are shown below. * This layout could be changed according to site conditionFig.2 Setting layout of equipment and facilities(2) Setting center point of the bored pilesPositioning drilling pit is based on the design documents, positioning benchmarks and piling arrangement layout for specifying positions of pile’s centre in compliance with the designs. Specifying the position of the pile’s centre is performed by 02 geodetic theodolite or electronic theodolite. Consulting engineers shall inspect and take acceptance of positioning after completionIn addition, subsidiary benchmarks shall be set up by steel piles for direction of pile’s center and the pile’s centre shall be checked again upon sinking temporary well casing. These positions shall be protected and maintained until sinking and completing inspection of the well casing. Fig.3 Setting center of Bored pile (3) Assembling Guide frameAssembling guide frame will be prepared before Setting of the temporary casing.(4) Setting of the temporary casingBored pile construction will be commenced from setting out pile location, pre-drill and install temporary casing. The length of the casing will be considered and justified based on the soil condition and underground water level for maintaining the stability of the pile excavation against collapse. The top of temporary casing will be extended about 1.0meter above the ground level. In installation of temporary casing, the verticality and stability of it will be checked and non-movement during drilling. Inner diameter of casing pipe will be little larger at least 5 ~ 10cm than borehole diameter. The casing will be plumbed and checked for eccentricity against reference pegs, or it will be checked with survey equipment at the top of the casing with the same elevation aside from the location frame installed above ground level.
Fig.4 Installation of temporary casing

(5) Drilling work

The design length of piles will be designed by the Designer. During drilling excavation, all holes for cast-in-place concrete pile should be excavated to the design length. Excavated holes will be protected from collapse by the provision of using bentonite and temporary steel pipe casing.




Fig.5 Casing




Fig.6 Casing


a) Bentonite slurry

During drilling excavation of borehole, the soil will be protected from collapse by the provision of using bentonite slurry and temporary steel pipe casing. Prior to drilling works, the stabilization liquid as the bentonite suspension will be prepared and tested to meet the criteria which will be proposed before commencement..

Bentonite will be mixed thoroughly with clean fresh water to make a suspension which will maintain the stability of the pile excavation for the period of casting concrete and complete construction. Dry powder Bentonite is mixed with clean water according to required ratio by mixing machine and stored in the tanks which will supply to bored hole. The drilling fluid properties will be measured taking samples before concreting. The density of freshly mixed bentonite suspension will be measured as a check on the quality of the suspension being formed.


b) Setting up of Bentonite Plant

The following are the various stages of works in the setting up of site facilities:


Setting up

 Setting up of bentonite plant facilities.
 Preparation and levelling of ground.
 Installation of bentonite silos
 Installation of desander unit.
 Layout of bentonite and water piping systems.
 Pre-mixing of bentonite slurry on site.


c) Bentonite Slurry Mix Design

Basic functions of bentonite is to act as a stabilizing agent for the borehole.
In soil with high clay content, the bentonite slurry becomes very thick during excavation due to the suspended clay particles. The thick slurry becomes difficult to pump for desanding. To avoid this problem, a polymer / sodium bi-carbonate is added to the slurry.



d) Testing Bentonite Slurry

Bentonite Slurry Test – Initial

The following tests will be conducted on bentonite slurry at initial and during excavation, results will be submitted.
1. Viscosity test - test on site

2. Sand Content – test on site

3. Density test - test on site

4. pH meter test - test on site

Bentonite Slurry Test - Prior to concreting but after desanding.

The following tests will be conducted on bentonite slurry after completion of desanding.
1. Viscosity test - test on site

2. Sand Content – test on site

3. Density test - test on site

3. pH meter test - test on site

The drilling fluid properties shall be measured taking samples at different depths before concreting. All checking of bentonite slurry shall be carried out complying with the criteria proposal. The measuring device shall be calibrated to read to within 0.01gm/ml.


Fig.7 Bentonite Slurry



e) Drilling works

From the ground level to one meter above the toe of the temporary casing will be drilling without stabilization liquid (bentonite). The measurement of the depth of drilling bucket shall be closely monitored when it get near to the toe of the casing.
After putting bentonite into the borehole, drilling work will be continued and the top level of it will be maintained more 2.0m higher than ground water level or 1.0m higher than ground level for prevention of cave-ins or borehole collapses.

Based on the soil profile, drilling rate is adjustable in order to maintain the drilling accuracy.

During the drilling work, the verticality of drill will be checked by plumb with string line or theodolites from two directions in 90 degree. And the depth of borehole will
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
Tên dự án: Khu đô thị Thành phố Hồ Chí Minh Dự án xây dựng đường sắt
Bến Thành - Suối Tiên (Line 1)
Xây dựng trọn gói 2: Dân sự (Elevated & Depot)
Method Statement of Bored Pile Xây dựng RÀ SOÁT TÌNH TRẠNG REV. Số NGÀY MÔ TẢ Bình luận CÁO CỦA DẤU CỦA THUẬN CỦA TÊN CHỮ KÝ NGÀY MỤC LỤC 1 Giới thiệu 4 1.1 CHUNG 4 1.2 VIỆC PHẠM VI 4 2 XÂY DỰNG QUY TRÌNH 4 2.1 WORK FLOW-ĐỒ 4 2.2 VIỆC THỦ TỤC 6 (1) Chuẩn bị công trình 6 (2) Thiết lập trung tâm điểm của cọc khoan nhồi 7 (3) Lắp Hướng dẫn khung 8 (4) Setting của vỏ tạm thời 8 (5) Công việc khoan 9 (6) 1 đáy sạch các lỗ & Change Bentonite 12 (7) chế tạo và lắp đặt cốt thép của lồng cốt thép 12 (8) Thiết lập Tremie ống và Re-làm sạch (2 Thời gian thanh toán bù trừ) của giếng khoan 14 (9) đúc bê tông 15 (10) Loại bỏ tạm Vỏ bọc 17 3 NGUYÊN CHO ĐƯỢC SỬ DỤNG 18 3.1 THIẾT BỊ DÙNG 18 3.2 TỔ CHỨC 19 4 dự phòng và GIẢI PHÁP 20 4.1 dự phòng của KHOAN CÔNG 20 4.2 dự phòng của WORK tiếp 21 5 KIỂM SOÁT CHẤT LƯỢNG 21 5.1 CHẤT LƯỢNG KIỂM SOÁT 21 5.2 TỔ CHỨC / NHÂN VIÊN 21 5.3 PILOT KIỂM TRA VÀ THI PILE 22 5.4 chống chịu hoặc dãy 25 5.5 KIỂM TRA VÀ THI NHÂN 25 5.6 Phòng thí nghiệm 25 5.7 CHẤT LƯỢNG KẾ HOẠCH KIỂM SOÁT CHO CỌC KHOAN CÔNG TRÌNH 26 6 HEALTH, SAFETY VÀ MÔI TRƯỜNG 27 6.1 HSE ĐÀO TẠO 27 6.2 PPE 27 6.3 TOOL BOX HỌP (TBM) 27 6.4 HSE KIỂM TRA 27 6.5 KIỂM SOÁT AN TOÀN PHÁP 28 (1) Crane và nặng Thiết bị kiểm soát 28 (2) Công trình điện 28 (3) Thiết bị chữa cháy và phòng chống cháy 28 6.6 CÁC BIỆN PHÁP KIỂM SOÁT MÔI TRƯỜNG 28 (1) Kiểm soát ô nhiễm nước 28 (2) Bảo vệ chất lượng không khí 29 (3) Noise Control 29 (4) Các loại khác 29 7 KHẨN CẤP ỨNG PHÓ ĐỒ 31 1 GIỚI THIỆU CHUNG 1.1 Mục tiêu của báo cáo phương pháp này là để mô tả các phương pháp xây dựng và thủ tục chồng chất công việc thí điểm cho đống dự án Metro TP.HCM. 6 cọc khoan nhồi sẽ được cung cấp như là đống thí điểm. Các kỹ thuật thi công cọc khoan nhồi để xây dựng độc lập tròn cast insitu gia cố cọc từ độ sâu thiết kế để các thiết kế cut-off cấp. Yêu cầu điều khiển quản trị site cho đúc tại chỗ đóng cọc bê tông các công trình bằng sử dụng đất Máy Khoan (Auger Khoan Method). . Các kích thước của cọc để được bao phủ bởi tuyên bố của phương pháp này là đường kính 1500mm, 1200mm và 1000mm 1.2 VIỆC PHẠM VI . Phương pháp này bao gồm tuyên bố dưới đây phạm vi công việc - Khoan hoạt động:. D = 1,500mm, 1200mm và 1000 mm - Lắp đặt Rebar Cage - Đúc bê tông vỏ thép Tạm + 50 ~ 100mm kích thước của cọc khoan nhồi sẽ được cài đặt. Các công trình nhàm chán sẽ thực hiện cho đến khi mức toe định. Lỗ khoan được làm đầy với Bentonite một khi công trình nhàm chán bắt đầu. Sau khi hoàn thành các công trình nhàm chán, lồng cốt thép sẽ được hạ xuống vào trong lỗ khoan. Thực hiện làm sạch lỗ khoan trước khi lắp đặt cốt thép lồng, việc đúc cọc khoan nhồi sẽ diễn ra sau đó. cọc khoan nhồi có đường kính khác nhau và độ dài sẽ được xây dựng phù hợp với các bản vẽ xây dựng. 2 THỦ TỤC XÂY DỰNG 2.1 WORK FLOW-ĐỒ Trình tự công việc của xây dựng cọc được mô tả bởi các dòng chảy biểu đồ sau đây. Sơ đồ dưới đây cho thấy trình tự liên tục của cọc khoan nhồi các công trình Hình 1 trình tự của Bored cọc công trình 2.2 CÔNG TÁC QUY TRÌNH Quy trình làm việc chi tiết được mô tả như sau. (1) Chuẩn bị công trình Trước khi bắt đầu công việc đóng cọc Cast-in-place bê tông, các trang web sẽ bị xóa và san lấp để chịu được trọng lượng của máy khoan nhồi cọc mà không cần bất kỳ chướng ngại vật ở bề mặt của mặt đất. Và nếu nó không phải là đủ, đủ để chịu được trọng lượng của máy khoan nhồi cọc, thép tấm sẽ được đặt để phục vụ như là nền tảng thiết bị làm việc. thùng trộn Bentonite sẽ được cài đặt dễ dàng bảo trì của xe tăng bao gồm cả kết nối của ống hoặc ống để cung cấp cho bentonite các vị trí cọc khoan nhồi. Nó sẽ được kiểm tra từ thời gian để thời gian cho vữa bentonite để có thể đổ ra ngoài theo yêu cầu của môi trường. bố trí thiết lập tiêu biểu của thiết bị và cơ sở vật chất cho dung dịch bentonite được hiển thị dưới đây. * Cách bố trí này có thể được thay đổi tùy theo điều kiện trang web Hình 2 Thiết lập bố trí của thiết bị và cơ sở vật chất (2) Thiết lập trung tâm điểm của cọc khoan nhồi khoan định vị hố được dựa trên các tài liệu thiết kế, tiêu chuẩn định vị và bố trí sắp xếp chồng chất để xác định vị trí của trung tâm đống của phù hợp với thiết kế. Xác định vị trí trọng tâm của cọc được thực hiện bởi 02 máy kinh vĩ trắc địa hoặc máy kinh vĩ điện tử. Kỹ sư tư vấn có trách nhiệm kiểm tra và chịu chấp nhận vị trí sau khi hoàn thành Ngoài ra, tiêu chuẩn con đều phải được thiết lập bằng cọc thép để có chỉ đạo của trung tâm đống và trung tâm của cọc sẽ được kiểm tra lại một lần nữa chìm giếng tạm thời. Các vị trí này phải được bảo vệ và duy trì cho đến khi chìm và hoàn thành các kiểm tra của giếng. trung tâm hình 3 Setting của cọc khoan nhồi (3) Lắp ráp Hướng dẫn khung lắp ráp khung hướng dẫn sẽ được chuẩn bị trước khi lập của vỏ tạm thời. (4) Thiết lập của vỏ tạm thi công cọc khoan nhồi sẽ được bắt đầu từ việc thiết lập ra vị trí cọc, trước khi khoan và lắp đặt vỏ tạm thời. Chiều dài của vỏ sẽ được xem xét và hợp lý dựa trên các điều kiện đất và mực nước ngầm để duy trì sự ổn định của công trình khai quật đống chống lại sự sụp đổ. Phía trên cùng của vỏ tạm thời sẽ được mở rộng về 1.0meter trên mặt đất. Trong cài đặt của vỏ tạm thời, thẳng đứng và ổn định của nó sẽ được kiểm tra và không di chuyển trong quá trình khoan. Đường kính trong của ống vỏ sẽ có rất ít lớn hơn ít nhất 5 ~ 10cm so với đường kính lỗ khoan. Các vỏ sẽ được ống nước và kiểm tra độ lệch tâm so với chốt tham khảo, hoặc nó sẽ được kiểm tra với các thiết bị khảo sát ở phía trên cùng của vỏ có độ cao tương tự ngoài khung vị trí lắp đặt trên mặt đất. Hình 4 Lắp đặt vỏ tạm thời (5 ) Khoan làm việc Chiều dài thiết kế của cọc sẽ được thiết kế bởi các nhà thiết kế. Trong quá trình khoan khai quật, tất cả các lỗ cho cọc bê tông đúc tại chỗ nên được khai quật để chiều dài thiết kế. Lỗ khai quật sẽ được bảo vệ khỏi sự sụp đổ bởi việc cung cấp sử dụng bentonite và vỏ ống thép tạm thời. Fig.5 Vỏ bọc Vỏ bọc hình 6 a) Bentonite bùn Trong khai quật khoan lỗ khoan, đất sẽ được bảo vệ khỏi sự sụp đổ bởi việc cung cấp sử dụng bentonite bùn và vỏ ống thép tạm thời. Trước khi công trình khoan, chất lỏng ổn định như các hệ thống treo bentonite sẽ được chuẩn bị và thử nghiệm để đáp ứng các tiêu chí đó sẽ được đề xuất trước khi bắt .. Bentonite sẽ được trộn đều với nước sạch để thực hiện một hệ thống treo mà sẽ duy trì sự ổn định của cọc khai quật giai đoạn đúc bê tông và xây dựng hoàn chỉnh. Bột Bentonite được trộn với nước sạch theo tỷ lệ yêu cầu của máy trộn và lưu trữ trong các bể chứa mà sẽ cung cấp cho các lỗ khoan. Các tính chất dung dịch khoan sẽ được đo lấy mẫu trước khi đổ bê tông. Mật độ của hệ thống treo bentonite tươi hỗn hợp sẽ được đo như là một kiểm tra về chất lượng của việc đình chỉ được hình thành. b) Thành lập Bentonite nhà máy Sau đây là các giai đoạn khác nhau của công trình trong việc thiết lập các cơ sở vật chất trang web: Thiết lập  lập các cơ sở nhà máy bentonite.  Chuẩn bị và san lấp mặt bằng của mặt đất.  Lắp đặt silo bentonite  Lắp đặt đơn vị desander.  Giao diện của hệ thống đường ống nước và bentonite.  Pre-trộn bùn bentonite trên trang web. c) Bentonite Slurry Mix Thiết kế các chức năng cơ bản bentonit là hoạt động như một đại lý ổn định cho các lỗ khoan. Trong đất có hàm lượng sét cao, bùn bentonite trở nên rất dày trong quá trình đào do các hạt đất sét treo. Bùn dày trở nên khó khăn để bơm cho desanding. Để tránh vấn đề này, một polymer / sodium bi-carbonate được thêm vào bùn. d) Thử nghiệm Bentonite Slurry Bentonite Slurry Test - Initial Các xét nghiệm sau đây sẽ được thực hiện trên bùn bentonite tại ban đầu và trong quá trình khai quật, kết quả sẽ được gửi. 1. Độ nhớt kiểm tra - thử nghiệm trên trang 2. Sand Content - thử nghiệm trên trang 3. Mật độ kiểm tra - thử nghiệm trên trang 4. pH kiểm tra đồng hồ đo - thử nghiệm trên trang Bentonite Slurry Test -. Trước khi đổ bê tông nhưng sau desanding Các xét nghiệm sau đây sẽ được thực hiện trên bùn bentonite sau khi hoàn thành desanding. 1. Độ nhớt kiểm tra - thử nghiệm trên trang 2. Sand Content - thử nghiệm trên trang 3. Mật độ kiểm tra - thử nghiệm trên trang 3. pH kiểm tra đồng hồ đo - kiểm tra trên trang web Các tính chất dung dịch khoan phải được đo mẫu lấy ở độ sâu khác nhau trước khi đổ bê tông. Tất cả việc kiểm tra của bùn bentonite được thực hiện tuân thủ các tiêu chí đề nghị. Các thiết bị đo phải được kiểm định để đọc trong 0.01gm / ml. Hình 7 Bentonite Slurry e) Khoan làm việc Từ mặt đất đến một mét trên các ngón chân của vỏ tạm thời sẽ được khoan mà không ổn định chất lỏng (bentonite). Việc đo độ sâu của gầu khoan phải được theo dõi chặt chẽ khi nó nhận được gần để các ngón chân của vỏ. Sau khi đưa bentonite vào hố khoan, công việc khoan sẽ được tiếp tục và các cấp cao nhất của nó sẽ được duy trì hơn 2,0m so với mặt đất mực nước hoặc 1.0m cao hơn mặt đất để ngăn ngừa hang-ins hoặc sụp đổ lỗ khoan. Căn cứ vào hồ sơ đất, tỷ lệ khoan có thể điều chỉnh để duy trì tính chính xác khoan. Trong thời gian công tác khoan, khoan thẳng đứng sẽ được kiểm tra bởi plumb với dòng chuỗi hoặc kinh vĩ từ hai hướng ở 90 độ. Và chiều sâu của ý chí lỗ khoan











































































































































































































































































































































































































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.