- Pinning the 9 casing strings (few feet above EL (+) 4500 temporary deck to be set up with sufficient load for casing drop after explosive cut) by Pinning tool. Slot plate (with central hole = OD of conductor) can be made to make the casing will not drop through deck. - Rig-up and shackles in 2 sides of the pins- Jacking tool is standing by for cut verifications (in case casings don’t drop)- Barge back-off ~ 150-200m, detonation. - Check casings.o Not pullable: jet out inners (firehose down inside wells to wash out any sediments if breached the outside), re-load charge and cut again