Dear Nhung-san,
I will discuss with Furuya about total 2-days delay.
I think 2-days delay itself is OK, but as we have to finish installation within November, your site team will be more tough.
So, I think if you can make ex-factory date earlier for the other types (ex.WIM, PA, WB,,,,),
It may be good for your site team.
And TVJV has two priorities.
1) FIDS schedule cannot be delayed. This is the highest priority.
2) In all MA and SA type, MA.a14 has the highest priority, because MA.a14 will be installed inside of BHS conveyer, and BHS has to be covered.
So, I propose to make MA.a14 earlier than MA.a10-13.
Please see attachment.
Rev.13.1 is your proposed schedule.
Rev.13.2 is my proposal.
If you accept my proposal, I will talk to Furuya and Kawase.
Regards,
Kuni