SURVEY REQUIREMENTSThe main survey

SURVEY REQUIREMENTS
The main survey requirement will be the preparation of an accurate topographic survey of each potentially unstable area, extending far enough above and below all the earth slopes involved to include all drainage features (such as ditches, ponds, waterways, and rice paddies) which could affect surface runoff cater and/or the subsoil water table in the area under investigation and all features which could affect the loading on or support of the slopes. This may require several cross section surveys at each potentially unstable area. The Contractor will also be required to obtain all available historical data on any past movements or scour of the slopes under investigation, including the relevant dates, location and extent of the movements, the results of all relevant past studies, construction details of any past stabilization works either proposed or actually implemented (such as improved drainage, slope flattening, gabion placement, revetment construction), or potentially destabilizing works that have been implemented (such as pavement grade raising, slope steepening by widening only the top of the embankment or by excavating the toe of the slope, and the addition of the water sources above the slope), and records or reports concerning the effects of any such previously implemented works. In addition, he will be required to obtain all available rainfall and flood records relevant to the investigation area, including information concerning the highest past food levels at the site, flood levels and rate of drop of flood waters at times of past observed slope movements, and the time of year and duration of use of any irrigation canals, fish ponds, or other potential sources of water in the vicinity of the slopes (particularly at times of previously observed slope movements). The Contractor may also be required in some instances to carry out subsoil investigations involving test bore drilling, deep sounding with penetrometers and/or shear vanes, test pit excavations for undisturbed soil sampling, etc.
REPORTING
In addition to the drawings prepared under paragraph 2 above, the Contractor may be required to prepare for each stability investigation area additional separate plan and cross-section drawings as required to support the Engineer's design of remedial measures. All other data and records obtained by the Contractor relevant to the investigation shall be submitted to the Engineer in their full and original form together with the Contractor's summary of relevant facts extracted from the available records.
10. MEASUREMENT AND PAYMENT
Survey and Investigation shall be paid as a Lump sum, the contractor shall prepare the outline of the work and submit the Employer and The Consultant for approval.
Pay Item Description Unit
01020-1 Survey and investigation Lump sum
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
YÊU CẦU VỀ KHẢO SÁTThe main survey requirement will be the preparation of an accurate topographic survey of each potentially unstable area, extending far enough above and below all the earth slopes involved to include all drainage features (such as ditches, ponds, waterways, and rice paddies) which could affect surface runoff cater and/or the subsoil water table in the area under investigation and all features which could affect the loading on or support of the slopes. This may require several cross section surveys at each potentially unstable area. The Contractor will also be required to obtain all available historical data on any past movements or scour of the slopes under investigation, including the relevant dates, location and extent of the movements, the results of all relevant past studies, construction details of any past stabilization works either proposed or actually implemented (such as improved drainage, slope flattening, gabion placement, revetment construction), or potentially destabilizing works that have been implemented (such as pavement grade raising, slope steepening by widening only the top of the embankment or by excavating the toe of the slope, and the addition of the water sources above the slope), and records or reports concerning the effects of any such previously implemented works. In addition, he will be required to obtain all available rainfall and flood records relevant to the investigation area, including information concerning the highest past food levels at the site, flood levels and rate of drop of flood waters at times of past observed slope movements, and the time of year and duration of use of any irrigation canals, fish ponds, or other potential sources of water in the vicinity of the slopes (particularly at times of previously observed slope movements). The Contractor may also be required in some instances to carry out subsoil investigations involving test bore drilling, deep sounding with penetrometers and/or shear vanes, test pit excavations for undisturbed soil sampling, etc.REPORTINGIn addition to the drawings prepared under paragraph 2 above, the Contractor may be required to prepare for each stability investigation area additional separate plan and cross-section drawings as required to support the Engineer's design of remedial measures. All other data and records obtained by the Contractor relevant to the investigation shall be submitted to the Engineer in their full and original form together with the Contractor's summary of relevant facts extracted from the available records.10. MEASUREMENT AND PAYMENTSurvey and Investigation shall be paid as a Lump sum, the contractor shall prepare the outline of the work and submit the Employer and The Consultant for approval.Pay Item Description Unit01020-1 Survey and investigation Lump sum
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
YÊU CẦU ĐIỀU TRA
Yêu cầu khảo sát chính sẽ là việc chuẩn bị khảo sát địa hình chính xác của mỗi khu vực có tiềm năng không ổn định, mở rộng đủ xa trên và dưới tất cả các sườn trái đất có liên quan bao gồm tất cả các tính năng hệ thống thoát nước (chẳng hạn như mương, ao, sông, và cánh đồng lúa) mà có thể ảnh hưởng đến bề mặt dòng chảy phục vụ và / hoặc mực nước ngầm dưới lòng đất tại khu vực điều tra và tất cả các tính năng mà có thể ảnh hưởng đến việc tải về hoặc hỗ trợ leo dốc. Điều này có thể yêu cầu một số cuộc điều tra cắt ngang tại mỗi khu vực có tiềm năng không ổn định. Nhà thầu cũng sẽ được yêu cầu để có được tất cả các dữ liệu lịch sử có sẵn trên bất kỳ chuyển động trong quá khứ hay lau các sườn núi bị điều tra, bao gồm cả những ngày có liên quan, vị trí và mức độ của các phong trào, các kết quả của tất cả các nghiên cứu trước đây có liên quan, chi tiết xây dựng của bất kỳ ổn định trong quá khứ công trình hoặc đề xuất hoặc thực hiện (chẳng hạn như cải thiện hệ thống thoát nước, độ dốc phẳng, vị trí rọ đá, xây dựng kè), hoặc công trình có khả năng gây mất ổn định đã được thực hiện (như chăn vỉa hè lớp, độ dốc dốc bằng cách mở rộng chỉ các đỉnh kè hoặc bằng cách khai quật thực các ngón chân của sườn dốc, và việc bổ sung các nguồn nước trên dốc), và hồ sơ hoặc báo cáo về ảnh hưởng của bất kỳ công trình được thực hiện trước đó. Ngoài ra, ông sẽ được yêu cầu để có được tất cả lượng mưa có sẵn và hồ sơ lũ có liên quan đến khu vực điều tra, bao gồm cả thông tin liên quan đến các cấp thực phẩm trong quá khứ cao nhất tại trang web, mực nước lũ và tỷ lệ giọt nước lũ tại những thời điểm trong quá khứ quan sát động tác dốc, và thời gian của năm và thời hạn sử dụng của bất kỳ kênh mương, ao cá, hoặc các nguồn tiềm năng khác của nước trong vùng lân cận của những sườn núi (đặc biệt là vào những thời điểm của các phong trào dốc quan sát trước đây). Nhà thầu cũng có thể được yêu cầu trong một số trường hợp để thực hiện các cuộc điều tra liên quan đến lòng đất kiểm tra lỗ khoan, sâu nghe với penetrometers và / hoặc cánh quạt cắt, khai quật kiểm tra hố để lấy mẫu đất nguyên, vv
BÁO CÁO
Ngoài các bản vẽ chuẩn bị theo khoản 2 nêu trên , nhà thầu có thể được yêu cầu chuẩn bị cho mỗi sự ổn định khu vực điều tra bổ sung kế hoạch riêng và mặt cắt ngang bản vẽ theo yêu cầu để hỗ trợ thiết kế của kỹ sư của các biện pháp khắc phục hậu quả. Tất cả các dữ liệu và hồ sơ khác thu được từ các nhà thầu có liên quan đến việc điều tra phải được gửi cho các kỹ sư trong hình thức đầy đủ và ban đầu của họ cùng với bản tóm tắt của Nhà thầu các sự kiện có liên quan được chiết xuất từ các hồ sơ có sẵn.
10. ĐO VÀ THANH TOÁN
Khảo sát và điều tra sẽ được trả một khoản tiền một lần, nhà thầu phải chuẩn bị đề cương của công việc và trình Chủ đầu tư và Tư vấn chính.
Trả Mục Mô tả Đơn vị
khảo sát 01.020-1 và điều tra một lần tổng hợp
đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2025 I Love Translation. All reserved.

E-mail: