Wind turbine construction machinery scheme description
The following scheme is proposed for wind turbine lifting:
TEREX DEMAG cc2800-1 crawler-type crane (660 tons) is used with 100t truck-mounted crane as auxiliary crane.
TEREX DEMAG cc2800-1 crawler-type crane requires hardened pavement with carrying capacity no less than 20t. The 100t truck-mounted crane is used for assembling blades on ground and assisting in lifting.
Table of Main Construction Machinery and Equipment to be Used in the Section
Table of Building and Construction Machinery and Equipment (Wind Turbine Foundation and Road)
NO The device name TYPE number Country of origin The year of manufacture Rated power(KW) Product ability Use
Truck crane 20t 2 China 2010 20t wind turbine foundation
Bulldozer T180 4 China 2006 wind turbine foundation and road
Roller YZ12 3 China 2010 12T wind turbine foundation and road
Roller YZ16 3 China 2008 16T wind turbine foundation and road
Frog rammer HW-201 8 China 2008 4 wind turbine foundation
Digger PC300 4 Japan 2009 118 1.02m3 wind turbine foundation and road
Dump truck 20t 12 China 2012 15T wind turbine foundation and road
Reinforcing steel bending machine GQ40-1 2 China 2012 5kW 6-32mm wind turbine foundation
Reinforcing steel cutting machine GW6-40 2 China 2012 5.5kW 6-40mm wind turbine foundation
Straight thread stripping rib rolling machine AGS-40 1 China 2010 wind turbine foundation
Electric welding machine 3 China 2007 wind turbine foundation
Steel bar straightening machine GS1-14 1 China 2009 8 5T/H wind turbine foundation
Circular saw D-500 1 China 2008 7.5kW wind turbine foundation

General plane layout of construction site
General layout overview
The Project covers the construction of in-plant road, wind turbine foundation, wind turbine installation, booster station, etc. Office, construction site and living area are proposed to be built intensively near the booster station. Please refer to the general drawing for details. Mixing station, steel processing area, woodworking area, material storage area, etc. are set in the construction area for construction, and warehouse, equipment and material storing area, and other installation work construction area are also set.
The construction sites for wind turbine foundation and wind turbine installation are dispersed. In addition to centralized office area, temporary construction site shall be set in the site in the neighborhood in accordance with field installation conditions, and shall be changed with the construction location.
General layout of temporary electricity and water used in the construction site
Conditions of water and land used for construction
The power source for construction shall be led from nearby device.
Water: the Bidder shall supply water by itself. The main water supply pipe on site shall be directly buried.
Water used for construction in other disperse area shall be supplied by water trunk.
Conditions of external communication
Mobile phone and wireless communication are used as means of communication, and wireless walkie-talkie is used for the communication between technicians and quality inspectors inside the construction site to ensure a fast and unimpeded internal and external communication.
General layout of fire protection in construction site
The fire-fighting water pipe relies on the water pipe for construction. Fire hydrants shall be set at main areas of fire prevention and shall be marked with obvious makers. Sufficient fire-fighting implements and fire-fighting equipment shall be provided in the main areas of fire prevention (such as electric and fire welding construction areas and building interior).


0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
Máy móc xây dựng CChapter IV, nhân sự và đất để sử dụng tạm thờiMô tả lược đồ máy móc xây dựng tua bin gióSơ đồ sau đây được đề xuất cho gió tuabin nâng:TEREX DEMAG cc2800-1 thu thập thông tin-loại cẩu (660 tấn) được sử dụng với 100t gắn trên xe tải cẩu là phụ trợ cần cẩu.TEREX DEMAG cc2800-1 thu thập thông tin-loại cẩu đòi hỏi các vỉa hè cứng với khả năng thực hiện không ít hơn 20 t. 100t gắn trên xe tải cẩu được sử dụng để lắp ráp cánh trên đất và hỗ trợ trong việc nâng.Bảng máy móc xây dựng chính và thiết bị được sử dụng trong phầnBàn của xây dựng và xây dựng máy móc và thiết bị (Wind Turbine Foundation và Road)Không có tên thiết bị loại số nước xuất xứ năm sản xuất Rated power(KW) sản phẩm khả năng sử dụng Xe cần trục 20t 2 Trung Quốc 2010 20t gió tuabin quỹ Xe ủi đất T180 4 Trung Quốc năm 2006 gió tuabin quỹ và đường Con lăn YZ12 3 Trung Quốc 2010 12T gió tuabin quỹ và đường Con lăn YZ16 3 Trung Quốc 2008 16T gió tuabin quỹ và đường Ếch rammer nền tảng tua-bin gió HW-201 8 Trung Quốc 2008 4 Đào PC300 4 Nhật bản 2009 118 1.02m3 gió tuabin quỹ và đường Bãi xe tải 20t 12 Trung Quốc 2012 15T gió tuabin quỹ và đường Tăng cường thép uốn máy GQ40-1 2 Trung Quốc 2012 5kW 6-32mm gió tuabin nền tảng Tăng cường thép máy cắt GW6-40 2 Trung Quốc 2012 5.5kW nền tảng tua-bin gió 6-40 mm Thẳng thread tước sườn cán máy AGS-40 1 Trung Quốc 2010 gió tuabin quỹ Electric welding machine 3 China 2007 wind turbine foundation Steel bar straightening machine GS1-14 1 China 2009 8 5T/H wind turbine foundation Circular saw D-500 1 China 2008 7.5kW wind turbine foundationGeneral plane layout of construction siteGeneral layout overviewThe Project covers the construction of in-plant road, wind turbine foundation, wind turbine installation, booster station, etc. Office, construction site and living area are proposed to be built intensively near the booster station. Please refer to the general drawing for details. Mixing station, steel processing area, woodworking area, material storage area, etc. are set in the construction area for construction, and warehouse, equipment and material storing area, and other installation work construction area are also set.The construction sites for wind turbine foundation and wind turbine installation are dispersed. In addition to centralized office area, temporary construction site shall be set in the site in the neighborhood in accordance with field installation conditions, and shall be changed with the construction location. General layout of temporary electricity and water used in the construction siteConditions of water and land used for constructionThe power source for construction shall be led from nearby device.Water: the Bidder shall supply water by itself. The main water supply pipe on site shall be directly buried.Water used for construction in other disperse area shall be supplied by water trunk.Conditions of external communicationMobile phone and wireless communication are used as means of communication, and wireless walkie-talkie is used for the communication between technicians and quality inspectors inside the construction site to ensure a fast and unimpeded internal and external communication.General layout of fire protection in construction siteThe fire-fighting water pipe relies on the water pipe for construction. Fire hydrants shall be set at main areas of fire prevention and shall be marked with obvious makers. Sufficient fire-fighting implements and fire-fighting equipment shall be provided in the main areas of fire prevention (such as electric and fire welding construction areas and building interior).
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
CChapter IV Máy xây dựng, cán bộ và đất tạm thời sử dụng
gió mô tả sơ đồ máy móc xây dựng tuabin
Đề án sau đây được đề xuất tuabin gió nâng:
TEREX DEMAG cc2800-1 bánh xích loại cần cẩu (660 tấn) được sử dụng với cần cẩu 100 tấn đặt trên xe tải như phụ trợ cần cẩu.
TEREX DEMAG cc2800-1 bánh xích loại cẩu đòi hỏi vỉa hè cứng với khả năng vận chuyển không dưới 20t. Các 100T xe tải gắn cẩu được sử dụng để lắp ráp cánh trên mặt đất và hỗ trợ nâng.
Mục Main Máy xây dựng và Thiết bị được sử dụng trong các mục
Table của Xây dựng và Xây dựng Máy móc và thiết bị (Wind Turbine Foundation và Road)
NO Tên thiết bị TYPE số quốc gia xuất xứ Năm sản xuất Công suất (KW) khả năng sử dụng sản phẩm
xe tải cẩu 20t 2 Trung Quốc năm 2010 móng turbine gió 20t
Bulldozer T180 4 Trung Quốc năm 2006 móng turbine gió và đường
lăn YZ12 3 Trung Quốc 2010 móng tuabin 12T gió và đường
lăn YZ16 3 Trung Quốc 2008 16T móng turbine gió và đường
Frog đầm HW-201 8 Trung Quốc năm 2008 móng turbine gió 4
Digger PC300 4 Nhật Bản năm 2009 móng tuabin 118 1.02m3 gió và đường
xe tải Dump 20t 12 Trung Quốc 2012 15T gió móng tuabin và đường bộ
máy thép Củng cố uốn GQ40-1 2 Trung Quốc năm 2012 5kW 6-32mm móng turbine gió
máy cắt thép Tăng cường GW6-40 2 Trung Quốc năm 2012 5.5kW 6-40mm móng turbine gió
tước máy cán sườn đề Straight AGS-40 1 Trung Quốc năm 2010 gió móng tuabin
hàn điện máy 3 Trung Quốc 2007 móng turbine gió
thanh thép thẳng máy GS1-14 1 Trung Quốc móng tuabin 2009 8 5T / H gió
Thông tư thấy D-500 1 China 2008 móng tuabin 7.5kW gió bố trí máy bay chung của công trường xây dựng chung tổng quan bố trí Dự án bao gồm việc xây dựng trong nhà máy đường, nền móng turbine gió, lắp đặt tuabin gió, trạm tăng áp, vv Văn phòng, công trường xây dựng và khu vực sinh sống được đề xuất xây dựng sâu gần trạm tăng áp. Vui lòng tham khảo bản vẽ chung của chi tiết. Trộn ga, khu vực chế biến thép, khu vực chế biến gỗ, khu vực lưu trữ tài liệu, vv được đặt trong khu vực xây dựng để xây dựng, kho bãi, trang thiết bị và vật liệu khu vực lưu trữ và khu vực xây dựng công trình lắp đặt khác cũng được thiết lập. Các địa điểm xây dựng cho tua bin gió móng và lắp đặt tuabin gió được phân tán. Ngoài khu vực văn phòng tập trung, trang web xây dựng tạm được quy định trong các trang web trong các khu phố phù hợp với điều kiện lắp đặt sân, và phải được thay đổi với các địa điểm xây dựng. bố trí chung của điện tạm thời và nước được sử dụng trong các trang web xây dựng Điều kiện của nước và đất sử dụng để xây dựng các nguồn điện cho xây dựng phải được dẫn dắt từ gần thiết bị. nước: Nhà thầu phải cung cấp nước của chính nó. Các đường ống cấp nước chính trên trang web sẽ được chôn trực tiếp. Nước dùng cho xây dựng tại khu vực phân tán khác được cung cấp bởi thân cây nước. Điều kiện giao tiếp bên ngoài điện thoại di động và truyền thông không dây được sử dụng như phương tiện truyền thông, và không dây walkie-talkie được sử dụng cho thông tin liên lạc giữa các kỹ thuật viên và thanh tra chất lượng bên trong công trường xây dựng để đảm bảo thông tin liên lạc nội bộ và bên ngoài nhanh chóng và không bị cản trở. bố trí chung phòng cháy chữa cháy tại công trường xây dựng Ống dẫn nước chữa cháy dựa trên các đường ống nước cho xây dựng. Lấy nước chữa cháy phải được đặt ở khu vực chính về phòng cháy và phải được đánh dấu với các nhà hoạch định rõ ràng. Dụng cụ chữa cháy đầy đủ và thiết bị phòng cháy chữa cháy được cung cấp trong các lĩnh vực chính về phòng cháy (chẳng hạn như các khu vực xây dựng điện và hàn lửa và nội thất xây dựng).
















đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: