Current issuesBesides the issue of late fabric arrival due to inherent problem of fabric quality, there are planning weaknesses as below:Knit Fabric Team only makes Fabric arrival plan and communicate this with merchandisers. However, this plan is still not properly updated on the server. One of reasons is that some merchandisers do not check information of fabric arrival on the server and prefer informed via email or verbally. Checking plan and in-WH plan have not been made properly and systematically. There are often interruptions and conflicts in prioritising for checking fabrics due to lack of proper cutting and on-line plans. Moreover, coordination between Mr Hai and Ms Hortense for checking priorities is still a concern due to conflict of interest. Thus, although the Woven Team has checking and in-WH plan updated on a register, these plans are less accurate.