As per the aforementioned letter, the Contractor Daelim has requested subcontractor BRE17 to speed up work progress for construction drawing designing and complete this item on the end of October 2015. However, the design subcontractor – Britec withdrew from the Project, Bridge Enterprise 17 has tried to seek a new design subcontractor and sign the contract to expedite work progress, the design work will cost nearly twice as much as the original design cost. Bridge Enterprise 17 will try to meet the work progress of design as required by Contractor Daelim and finish it on the end of October 2015. Nevertheless, with some difficult construction position and site plan have not been cleared such as 2nd Ring Road Bridge, Nhue Bridge, We would like to delay the completion these items until December 2015 (Please see the attached work progress for construction drawing submission).In fact, the work progress of design made basis of the non-existent interface problem with other packages and failures of technical design that both the Contractor Daelim and the Subcontractor BRE17 are not able to dispose it. Thus, the work progress can be able to adjust according to the unity of the all parties.We respectfully suggest that Contractor Daelim to consider and approve this work progress for construction drawing design.We are looking forward to your cooperation.
đang được dịch, vui lòng đợi..