DIVISION 2
SITE CLEARING

TABLE OF CONTENTS



02100 – Site Clearing ……………………………………………………............……………………………... 2

02200 – Demolition and Removal of Existing Structures and Obstructions……… 6












SECTION 02100
SITE CLEARING

TABLE OF CONTENTS

1. Description 3
2. Construction Requirements 3
2.1 General 3
2.2 Clearing and Grubbing and Tree Removal 3
2.3 Topsoil Stripping 4
2.4 Protection of Areas Designated to Remain 4
2.5 Disposal of Cleared Material 4
3. Measurement and Payment 5
3.1 Method of Measurement 5
3.2 Basis of Payment..............................…………………………………………………...5
SECTION 02100 - SITE CLEARING
1. DESCRIPTION
This work consists of clearing, grubbing, removal of top soil, and removal and disposal of all vegetation and debris within the project limits, excepting those objects designated to remain in place or to be removed in accordance with other sections of these Specifications.
This work also includes the preservation from injury or defacement of all vegetation and objects designated to remain.
2. CONSTRUCTION REQUIREMENTS
2.1 GENERAL
The Engineer will establish the limits of work and designate all trees, shrubs, plants and other things to remain. The Contractor shall protect and preserve all items designated to remain.
2.2 CLEARING AND GRUBBING AND TREE REMOVAL
(a) All surface objects and all trees, timber, rotten wood, stumps, roots, snags, brush, other vegetation, rubbish, and other protruding obstructions, not designated to remain, shall be cleared and/or grubbed, including disposal as required. Only trees of diameter greater than 200mm measured 1.0 metre above ground level will be paid for separately under pay item 02100-2 “Removal of Existing Trees(dia.>200mm)”. Trees and brushes smaller than this will be dealt with under pay item 02100-1 “Clearing and Grubbing”.
(b) In areas under roadway embankments, from which top soil or unsuitable materials are to be removed or which are designated to be compacted, all stumps and roots shall be removed to a depth at least 20 cm below the original ground surface and at least 50 cm below the bottom of the designed lowest pavement layer or the finished subgrade level.
(c) In roadway cut areas, all stumps and roots shall be removed to a depth of not less than 30 cm below the finished subgrade level.
(d) Clearing and grubbing of pits, channel changes, and ditches shall be made only to the depth necessitated by the excavation within those areas.
(e) Voids left after removal of roots shall be filled with suitable material and compacted to the density of the surrounding material.
2.3 TOPSOIL STRIPPING
(a) In areas under roadway embankments or where designated by the Engineer, the Contractor shall remove the topsoil and dispose it of as directed by the Engineer.
(b) In general the removal of topsoil shall include only the removal of soil which is sufficiently fertile to encourage or sustain the growth of vegetation.
(c) Removal of topsoil over any designated area shall be to the depth of 20cm below the original ground and at least 30cm under the bottom of the lowest road foundation layer. This excavated soil shall be stockpiled separately from other excavated material.
(d) Where topsoil is to be used for dressing of the slopes of embankment or other areas as directed by the Engineer or as indicated on the drawings, the work of topsoil stripping will be deemed to include stockpiling of topsoil when necessary as well as removal, placing and spreading of topsoil in areas designated by the Engineer. After spreading, the topsoil shall be raked to form a smooth surface free from weeds, roots, sods and large stones.
2.4 PROTECTION OF AREAS DESIGNATED TO REMAIN
In areas designated by the Engineer, the Contractor shall be responsible for the protection and routine maintenance of existing shrubs, trees and grassed areas. On completion of the Works these areas shall be returned to the Employer in the same condition as before and any damage due directly or indirectly to the Contractor's operations shall be made good at the Contractor’s own expenses.
2.5 DISPOSAL OF CLEARED MATERIAL
(a) The Contractor shall have the right to use un-saleable timber (or saleable timber when permission is granted in writing by the appropriate government agency or authority) for his own purposes in connection with the Contract; always provided that he has ascertained and complied with the requirements of the relevant government agency or authority.
(b) Saleable timber shall be neatly stored in an approved accessible place within or near the right-of-way as directed and shall be trimmed and stacked in accordance with the requirements of the relevant government agency.
(c) All other timber, except timber to be used, and all brush, stumps, roots, logs, and other refuse from the clearing and grubbing operation shall be disposed of at locations provided by the Contractor.
(d) The roadway and adjacent areas shall be left with a neat and finished appearance. No accumulation of debris shall remain on or adjacent to the right-of-way.
3. MEASUREMENT AND PAYMENT
3.1 METHOD OF MEASUREMENT
(a) Clearing and grubbing, topsoil stripping and protection of designated areas, will be together be considered as Clearing and Grubbing, and will be paid for by the square metre based on measurement results at the site and the area approved by the Engineer. Tree removal and protection of trees designated to remain in place will be considered as Removal of Existing Trees and will be paid for by number of trees removed of minimum diameter 200 mm as accepted by the Engineer. Removal, protection of tree of diameter less than 200mm shall not be paid for separately.
(b) Clearing and grubbing and tree removal and protection in disposal sites, material sites, borrow pit sites, haul roads and temporary construction areas shall not be paid for when such sites are outside the areas designated for clearing and grubbing. The Contractor is permitted to exercise his own option as whether to use such disposal sites or borrow pit sites.
3.2 BASIS OF PAYMENT
The work measured as provided above shall be paid for based on the appropriate unit price shown in the Bill of Quantity. The payment shall be full compensation for furnishing all labour, materials, tools, equipment, compacted to the density of the surrounding material and incidental necessary to do the work and for doing Site Clearing (Clearing and Grubbing including removal, topsoil stripping and other necessary works), Removal of Existing Trees in the designated areas and backfilling with suitable material and compacted to the density of the surrounding material as locations directed by the Engineer. Payment shall include costs for removal and disposal of the resulting materials.
Pay Item No. Name Unit of Measurement
02100-1 Clearing and Grubbing square metre
02100-2 Removal of Existing Trees(dia.>200mm) each


SECTION 02200
DEMOLITION AND REMOVAL OF EXISTING STRUCTURES
AND OBSTRUCTIONS

TABLE OF CONTENTS

1. Description 7
1.1 Submittals 7
2. Construction Requirements 8
2.1 General 8
2.2 Removal of Buildings and Other Structures (Bridge, Culvert) 10
2.3 Removal of Curbs 10
2.4 Removal of Pavements, Footpaths, etc. 11
2.5 Removal of Traffic Signs 11
3. Measurement and Payment 11
3.1 Method of Measurement…………………………………………………………… ..11
3.2 Basis of Payment 11






SECTION 02200 - DEMOLITION AND REMOVAL OF
EXISTING STRUCTURES AND OBSTRUCTIONS

1. DESCRIPTION
Demolition and Removal of Existing Structures consist of the removal, wholly or in part, and satisfactory disposal of blocks of masonry of an individual size greater than 1 cubic meter, of all buildings, hedges, fences, structures, pavements regardless of their nature (asphalt, concrete, etc.), curbs, and any other obstructions which are not designated or permitted to remain. Demolition includes the salvage of designated materials and proper backfilling (in accordance with specification requirements) of any and all trenches, holes and pits resulting from demolition and removal work.
Right-of-way acquisition may not be completed in all areas at the start-up of the construction period and the Contractor shall schedule the work associated with this Specification Section accordingly.
Obstructions or other items that are designated for removal and disposal elsewhere in the Contract Documents shall be dealt with in accordance with the relevant stipulated requirements.
1.1 SUBMITTALS
The Contractor shall prepare and submit to the Engineer, for respective approval prior to starting the work, the following:
(a) Shop Drawings (as stake drawings) in accordance with the provisions of Specification Section 01200 “Contractor’s Drawings”, including detailed information regarding the drainage structures, curbs, pavements, etc. to be demolished and removed in accordance with the provisions and indications of this Specification Section.
(b) Complete details of the method, equipment and schedule to perform the demolition and removal work pertinent to this item.
(c) Inventory of the materials that could be recovered from demolition work, stockpiling of suitable material from stripping that the Contractor intends to use for other items.
(d) Detailed drawings showing the areas for disposal of the material from this item, or for stockpiling of the recovered material if it is planned to be used for other items.
2. CONSTRUCTION REQUIREMENTS
2.1 GENERAL
Demolition and Removal of Existing Structures shall be executed by the Contractor within and adjacent to roadways and on Land acquisition Border mark (GPMB), as shown on the Drawings or as directed by the Engineer.
(a) The Engineer may instruct that materials recovered from demolition work shall remain the property of the Employer unless specifically provided otherwise in the Contract Documents.
(b) All designated saleable material shall be removed, withou
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
DIVISION 2SITE CLEARING TABLE OF CONTENTS02100 – Site Clearing ……………………………………………………............……………………………... 202200 – Demolition and Removal of Existing Structures and Obstructions……… 6SECTION 02100 SITE CLEARINGTABLE OF CONTENTS1. Description 32. Construction Requirements 32.1 General 32.2 Clearing and Grubbing and Tree Removal 32.3 Topsoil Stripping 42.4 Protection of Areas Designated to Remain 42.5 Disposal of Cleared Material 43. Measurement and Payment 53.1 Method of Measurement 53.2 Basis of Payment..............................…………………………………………………...5 SECTION 02100 - SITE CLEARING1. DESCRIPTIONThis work consists of clearing, grubbing, removal of top soil, and removal and disposal of all vegetation and debris within the project limits, excepting those objects designated to remain in place or to be removed in accordance with other sections of these Specifications.This work also includes the preservation from injury or defacement of all vegetation and objects designated to remain.2. CONSTRUCTION REQUIREMENTS2.1 GENERALThe Engineer will establish the limits of work and designate all trees, shrubs, plants and other things to remain. The Contractor shall protect and preserve all items designated to remain.2.2 CLEARING AND GRUBBING AND TREE REMOVAL(a) All surface objects and all trees, timber, rotten wood, stumps, roots, snags, brush, other vegetation, rubbish, and other protruding obstructions, not designated to remain, shall be cleared and/or grubbed, including disposal as required. Only trees of diameter greater than 200mm measured 1.0 metre above ground level will be paid for separately under pay item 02100-2 “Removal of Existing Trees(dia.>200mm)”. Trees and brushes smaller than this will be dealt with under pay item 02100-1 “Clearing and Grubbing”. (b) In areas under roadway embankments, from which top soil or unsuitable materials are to be removed or which are designated to be compacted, all stumps and roots shall be removed to a depth at least 20 cm below the original ground surface and at least 50 cm below the bottom of the designed lowest pavement layer or the finished subgrade level.(c) In roadway cut areas, all stumps and roots shall be removed to a depth of not less than 30 cm below the finished subgrade level.(d) Clearing and grubbing of pits, channel changes, and ditches shall be made only to the depth necessitated by the excavation within those areas.(e) Voids left after removal of roots shall be filled with suitable material and compacted to the density of the surrounding material.2.3 TOPSOIL STRIPPING(a) In areas under roadway embankments or where designated by the Engineer, the Contractor shall remove the topsoil and dispose it of as directed by the Engineer.(b) In general the removal of topsoil shall include only the removal of soil which is sufficiently fertile to encourage or sustain the growth of vegetation.(c) Removal of topsoil over any designated area shall be to the depth of 20cm below the original ground and at least 30cm under the bottom of the lowest road foundation layer. This excavated soil shall be stockpiled separately from other excavated material.(d) Where topsoil is to be used for dressing of the slopes of embankment or other areas as directed by the Engineer or as indicated on the drawings, the work of topsoil stripping will be deemed to include stockpiling of topsoil when necessary as well as removal, placing and spreading of topsoil in areas designated by the Engineer. After spreading, the topsoil shall be raked to form a smooth surface free from weeds, roots, sods and large stones.2.4 PROTECTION OF AREAS DESIGNATED TO REMAINIn areas designated by the Engineer, the Contractor shall be responsible for the protection and routine maintenance of existing shrubs, trees and grassed areas. On completion of the Works these areas shall be returned to the Employer in the same condition as before and any damage due directly or indirectly to the Contractor's operations shall be made good at the Contractor’s own expenses.2.5 DISPOSAL OF CLEARED MATERIAL(a) The Contractor shall have the right to use un-saleable timber (or saleable timber when permission is granted in writing by the appropriate government agency or authority) for his own purposes in connection with the Contract; always provided that he has ascertained and complied with the requirements of the relevant government agency or authority.(b) Saleable timber shall be neatly stored in an approved accessible place within or near the right-of-way as directed and shall be trimmed and stacked in accordance with the requirements of the relevant government agency.(c) All other timber, except timber to be used, and all brush, stumps, roots, logs, and other refuse from the clearing and grubbing operation shall be disposed of at locations provided by the Contractor.(d) The roadway and adjacent areas shall be left with a neat and finished appearance. No accumulation of debris shall remain on or adjacent to the right-of-way.3. MEASUREMENT AND PAYMENT3.1 METHOD OF MEASUREMENT(a) Clearing and grubbing, topsoil stripping and protection of designated areas, will be together be considered as Clearing and Grubbing, and will be paid for by the square metre based on measurement results at the site and the area approved by the Engineer. Tree removal and protection of trees designated to remain in place will be considered as Removal of Existing Trees and will be paid for by number of trees removed of minimum diameter 200 mm as accepted by the Engineer. Removal, protection of tree of diameter less than 200mm shall not be paid for separately. (b) Clearing and grubbing and tree removal and protection in disposal sites, material sites, borrow pit sites, haul roads and temporary construction areas shall not be paid for when such sites are outside the areas designated for clearing and grubbing. The Contractor is permitted to exercise his own option as whether to use such disposal sites or borrow pit sites.
3.2 BASIS OF PAYMENT
The work measured as provided above shall be paid for based on the appropriate unit price shown in the Bill of Quantity. The payment shall be full compensation for furnishing all labour, materials, tools, equipment, compacted to the density of the surrounding material and incidental necessary to do the work and for doing Site Clearing (Clearing and Grubbing including removal, topsoil stripping and other necessary works), Removal of Existing Trees in the designated areas and backfilling with suitable material and compacted to the density of the surrounding material as locations directed by the Engineer. Payment shall include costs for removal and disposal of the resulting materials.
Pay Item No. Name Unit of Measurement
02100-1 Clearing and Grubbing square metre
02100-2 Removal of Existing Trees(dia.>200mm) each


SECTION 02200
DEMOLITION AND REMOVAL OF EXISTING STRUCTURES
AND OBSTRUCTIONS

TABLE OF CONTENTS

1. Description 7
1.1 Submittals 7
2. Construction Requirements 8
2.1 General 8
2.2 Removal of Buildings and Other Structures (Bridge, Culvert) 10
2.3 Removal of Curbs 10
2.4 Removal of Pavements, Footpaths, etc. 11
2.5 Removal of Traffic Signs 11
3. Measurement and Payment 11
3.1 Method of Measurement…………………………………………………………… ..11
3.2 Basis of Payment 11






SECTION 02200 - DEMOLITION AND REMOVAL OF
EXISTING STRUCTURES AND OBSTRUCTIONS

1. DESCRIPTION
Demolition and Removal of Existing Structures consist of the removal, wholly or in part, and satisfactory disposal of blocks of masonry of an individual size greater than 1 cubic meter, of all buildings, hedges, fences, structures, pavements regardless of their nature (asphalt, concrete, etc.), curbs, and any other obstructions which are not designated or permitted to remain. Demolition includes the salvage of designated materials and proper backfilling (in accordance with specification requirements) of any and all trenches, holes and pits resulting from demolition and removal work.
Right-of-way acquisition may not be completed in all areas at the start-up of the construction period and the Contractor shall schedule the work associated with this Specification Section accordingly.
Obstructions or other items that are designated for removal and disposal elsewhere in the Contract Documents shall be dealt with in accordance with the relevant stipulated requirements.
1.1 SUBMITTALS
The Contractor shall prepare and submit to the Engineer, for respective approval prior to starting the work, the following:
(a) Shop Drawings (as stake drawings) in accordance with the provisions of Specification Section 01200 “Contractor’s Drawings”, including detailed information regarding the drainage structures, curbs, pavements, etc. to be demolished and removed in accordance with the provisions and indications of this Specification Section.
(b) Complete details of the method, equipment and schedule to perform the demolition and removal work pertinent to this item.
(c) Inventory of the materials that could be recovered from demolition work, stockpiling of suitable material from stripping that the Contractor intends to use for other items.
(d) Detailed drawings showing the areas for disposal of the material from this item, or for stockpiling of the recovered material if it is planned to be used for other items.
2. CONSTRUCTION REQUIREMENTS
2.1 GENERAL
Demolition and Removal of Existing Structures shall be executed by the Contractor within and adjacent to roadways and on Land acquisition Border mark (GPMB), as shown on the Drawings or as directed by the Engineer.
(a) The Engineer may instruct that materials recovered from demolition work shall remain the property of the Employer unless specifically provided otherwise in the Contract Documents.
(b) All designated saleable material shall be removed, withou
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
DIVISION 2
SITE CLEARING LỤC 02.100 - Site Clearing 2 02.200 - Phá dỡ và diệt của các cấu trúc hiện có và Vật cản ......... 6 PHẦN 02.100 SITE CLEARING LỤC 1. Mô tả 3 2. Yêu cầu xây dựng 3 2.1 Tổng 3 2.2 Clearing và đào gốc và Tree diệt 3 2.3 đất mặt Tước 4 2.4 Bảo vệ các khu vực dành để Giữ 4 2.5 Xử lý số liệu rà phá 4 3. Đo lường và Thanh toán 5 3.1 Phương pháp đo lường 5 3.2 Cơ sở 02.100 - SITE Clearing 1. MÔ TẢ Công việc này bao gồm thanh toán bù trừ, Đào xới, loại bỏ đất hàng đầu, và loại bỏ và xử lý tất cả các thảm thực vật và các mảnh vỡ trong giới hạn dự án, trừ các đối tượng được chỉ định để duy trì tại chỗ hoặc được loại bỏ theo quy định với các bộ phận khác của các thông số kỹ thuật. Điều này công việc cũng bao gồm việc bảo quản khỏi bị tổn thương hoặc hủy hoại của tất cả các thảm thực vật và các đối tượng được chỉ định để tiếp tục. 2. YÊU CẦU XÂY DỰNG 2.1 CHUNG Các kỹ sư sẽ thiết lập các giới hạn của công việc và chỉ định tất cả các cây, cây bụi, cây và những thứ khác còn lại. Nhà thầu phải bảo vệ và giữ gìn tất cả các mục được chỉ định ở lại. 2.2 bù trừ và Đào xới và TREE REMOVAL (a) Tất cả các đối tượng bề mặt và tất cả các cây, gỗ, gỗ thối, gốc cây, rễ, snags, bàn chải, thảm thực vật khác, rác, và khác nhô ra các chướng ngại vật, không được ở lại, sẽ bị xóa và / hoặc grubbed, bao gồm cả xử lý theo yêu cầu. Chỉ có cây đường kính lớn hơn 200mm đo 1,0 mét so với mặt đất sẽ được thanh toán cho riêng theo mục trả 02.100-2 "diệt của cây hiện tại (dia.> 200mm)". Cây và bàn chải nhỏ hơn này sẽ được giải quyết theo lương mục 02.100-1 "bù trừ và đào gốc". (b) Trong khu vực dưới kè đường bộ, từ đó đất đầu hoặc vật liệu không phù hợp đang được gỡ bỏ hoặc được chỉ định để được đầm, tất cả các gốc cây và rễ phải được loại bỏ để có độ sâu ít nhất là 20 cm dưới mặt đất ban đầu và ít nhất 50 cm dưới đáy của thiết kế lớp mặt đường thấp nhất hoặc mức lớp móng đã hoàn thành. (c) Trong đường cắt khu vực, tất cả các gốc cây và rễ phải được loại bỏ để một chiều sâu của không ít hơn 30 cm dưới mức lớp móng đã hoàn thành. (d) thanh toán bù trừ và Đào xới hố, thay đổi kênh, mương sẽ chỉ được thực hiện đến độ sâu cần thiết cho việc khai quật trong các lĩnh vực. (e ) khoảng trống còn lại sau khi loại bỏ các rễ sẽ đầy vật liệu phù hợp và nén với mật độ của các vật liệu xung quanh. 2.3 đất mặt Tước (a) Tại các khu vực dưới kè đường hoặc nơi được chỉ định bởi các kỹ sư, các nhà thầu phải loại bỏ lớp đất mặt và vứt bỏ nó của sự chỉ dẫn của Kỹ sư. (b) Nói chung việc loại bỏ các lớp đất mặt thì chỉ bao gồm việc loại bỏ đất có đủ màu mỡ để khuyến khích hoặc duy trì sự tăng trưởng của thực vật. (c) Loại bỏ lớp đất mặt trên bất kỳ khu vực được chỉ định sẽ được đến độ sâu 20cm dưới mặt đất ban đầu và ít nhất 30cm dưới đáy của lớp nền đường thấp nhất. Đất đào này sẽ được dự trữ một cách riêng biệt từ nguyên liệu khai quật khác. (d) Trường hợp đất mặt là để được sử dụng cho áo khoác ngoài của sườn kè hoặc các khu vực khác theo hướng dẫn của các kỹ sư hoặc như được chỉ ra trên bản vẽ, công việc của lớp đất mặt tước sẽ được xem là bao gồm dự trữ đất mặt khi cần thiết cũng như loại bỏ, việc đặt và lan rộng của lớp đất mặt trong khu vực do các kỹ sư. Sau khi lan rộng, lớp đất mặt được cào để tạo thành một bề mặt nhẵn miễn phí từ cỏ dại, rễ, sods và đá lớn. 2.4 BẢO VỆ CÁC VÙNG ĐỊNH ĐẾN Hãy ở lại trong khu vực do các kỹ sư, các nhà thầu phải chịu trách nhiệm đối với việc bảo vệ và bảo dưỡng định kỳ của cây bụi, cây cỏ và các khu vực hiện có. Sau khi hoàn thành các công trình các khu vực này sẽ được trả lại cho Chủ đầu tư trong cùng một điều kiện như trước và bất kỳ thiệt hại do trực tiếp hoặc gián tiếp đến hoạt động của nhà thầu phải được thực hiện tốt tại các chi phí của các nhà thầu. 2.5 XỬ LÝ VẬT LIỆU SẠCH (a) Nhà thầu có quyền sử dụng gỗ un-thương phẩm (hoặc gỗ có thể bán được khi có giấy phép bằng văn bản của các cơ quan chính phủ hoặc cơ quan thích hợp) cho mục đích riêng của mình trong mối liên hệ với các hợp đồng; luôn cung cấp cho rằng ông đã xác định và tuân thủ các yêu cầu của các cơ quan chính phủ có liên quan hoặc cơ quan. (b) gỗ Saleable được gọn gàng được lưu trữ trong một nơi có thể truy cập được phê duyệt trong hoặc gần đúng-of-cách là đạo diễn và sẽ được cắt và xếp chồng lên nhau phù hợp với các yêu cầu của các cơ quan chính phủ có liên quan. (c) Tất cả các gỗ khác, trừ gỗ được sử dụng, và tất cả các bàn chải, gốc cây, rễ, nhật ký, và khác từ chối từ thanh toán bù trừ và hoạt động Đào xới được xử lý tại các địa điểm cung cấp của Nhà thầu. (d) Các đường và các khu vực lân cận phải được để lại với một hình gọn gàng và hoàn thành. Không tích tụ các mảnh vụn sẽ được duy trì trên hoặc liền kề bên phải của đường. 3. ĐO LƯỜNG VÀ THANH TOÁN 3.1 PHƯƠNG PHÁP ĐO (a) Bù trừ và Đào xới, đất mặt bóc và bảo vệ các khu vực quy định, sẽ được cùng nhau được coi là thanh toán bù trừ và đào gốc, và sẽ được trả bởi mét vuông dựa trên kết quả đo đạc tại các trang web và các diện tích được phê của Kỹ sư. Loại bỏ và bảo vệ cây định ở lại nơi Tree sẽ được coi là diệt của cây hiện tại và sẽ được trả bởi số cây viết bỏ đường kính tối thiểu 200 mm như được chấp nhận bởi các kỹ sư. Diệt, bảo vệ cây có đường kính nhỏ hơn 200mm thì không phải nộp cho riêng biệt. (b) Bù trừ và Đào xới và loại bỏ và bảo vệ trong các bãi thải, các trang web tài liệu, cây mượn trang web hố, đường đường và các khu vực xây dựng tạm thì không phải nộp cho khi các trang web đó đang ở bên ngoài các khu vực được chỉ định cho thanh toán bù trừ và Đào xới. Nhà thầu được phép thực hiện quyền của mình như việc sử dụng các trang web xử lý như vậy, mượn địa pit. 3.2 CƠ SỞ THANH TOÁN Công việc đo như cung cấp ở trên sẽ được trả cho căn cứ vào đơn giá phù hợp thể hiện trong Tuyên ngôn Nhân Số lượng. Việc thanh toán được bồi thường đầy đủ cho tất cả các trang trí nội thất công, vật liệu, công cụ, thiết bị, đầm để mật độ của các vật liệu xung quanh và ngẫu nhiên cần thiết để làm việc và để làm Site Clearing (Clearing và đào gốc bao gồm loại bỏ, đất mặt tước và công trình cần thiết khác ), diệt của hiện tại Cây xanh trong các khu vực được chỉ định và san lấp bằng vật liệu phù hợp và nén chặt với mật độ của các vật liệu xung quanh các địa điểm như chỉ dẫn của Kỹ sư. Việc thanh toán sẽ bao gồm chi phí cho việc loại bỏ và tiêu hủy các vật liệu kết quả. Trả Hàng số Tên Đơn vị đo lường 02.100-1 Clearing và đào gốc mét vuông 02.100-2 diệt của cây hiện tại (dia.> 200mm) mỗi PHẦN 02.200 phá dỡ và Tách loại HIỆN HỮU cấu và vật cản LỤC 1. Mô tả 7 1.1 submittals 7 2. Yêu cầu xây dựng 8 2.1 chung 8 2.2 Loại bỏ các tòa nhà và các cấu trúc khác (Bridge, Cống) 10 2.3 Loại bỏ các lề đường 10 2.4 Loại bỏ Pavements, đường đi bộ, vv 11 2.5 Loại bỏ các dấu hiệu giao thông 11 3. Đo lường và thanh toán 11 3.1 Phương pháp đo ..................................................................... ..11 3.2 Cơ sở của việc thanh toán 11 PHẦN 02.200 - Phá dỡ nhà và loại bỏ các cấu trúc hiện tại và các vật cản 1 . MÔ TẢ Phá dỡ và diệt của các cấu trúc hiện có bao gồm việc loại bỏ toàn bộ hoặc một phần, và xử lý thỏa đáng của các khối nề của một kích thước cá thể lớn hơn 1 mét khối, trong tất cả các tòa nhà, hàng rào, hàng rào, vật kiến trúc, vỉa hè bất kể bản chất của họ ( nhựa đường, bê tông, vv), lề đường, và bất kỳ vật cản khác mà không được chỉ định hoặc được phép ở lại. Phá dỡ bao gồm các vật liệu tận dụng được và lấp thích hợp (theo yêu cầu đặc điểm kỹ thuật) của bất kỳ và tất cả các chiến hào, lỗ và các hố do phá hủy và loại bỏ việc. Right-of-cách mua lại có thể không được hoàn thành trong tất cả các lĩnh vực tại start- lên của thời gian xây dựng và các nhà thầu phải sắp xếp các công việc liên quan đến mục này Đặc điểm kỹ thuật phù hợp. Vật cản hoặc các mặt hàng khác được dành riêng cho việc loại bỏ và xử lý ở những nơi khác trong tài liệu hợp đồng sẽ bị xử lý theo các yêu cầu quy định có liên quan. 1.1 submittals Các Nhà thầu chuẩn bị và nộp cho các kỹ sư, chính tương ứng trước khi bắt đầu công việc, những điều sau đây: (a) Cửa hàng vẽ (như hình vẽ cổ phần) phù hợp với các quy định của Thông số kỹ thuật Mục 01.200 "bản vẽ của nhà thầu", bao gồm thông tin chi tiết về hệ thống thoát nước công trình, lề đường, vỉa hè, vv để được phá hủy và loại bỏ theo quy định và chỉ dẫn của Mục Đặc điểm kỹ thuật này. (b) chi tiết toàn bộ các phương pháp, thiết bị và lịch để thực hiện việc phá dỡ và loại bỏ công việc thích hợp với mặt hàng này. (c) Hàng tồn kho của các vật liệu có thể được thu hồi từ việc phá dỡ, tàng trữ vật liệu phù hợp từ tước rằng thầu có ý định sử dụng cho các mặt hàng khác. (d) Bản vẽ chi tiết cho thấy các khu vực xử lý đối với các vật liệu từ mặt hàng này, hoặc cho tàng trữ các loại vật liệu phục hồi nếu nó được dự kiến sẽ được sử dụng cho các mặt hàng khác. 2. YÊU CẦU XÂY DỰNG 2.1 CHUNG Phá dỡ và diệt của các cấu trúc hiện tại sẽ được thực hiện bởi các nhà thầu trong và tiếp giáp với đường và trên Land mark mua lại biên giới (GPMB), như thể hiện trên các bản vẽ hoặc theo chỉ dẫn của Kỹ sư. (a) Các kỹ sư có thể hướng dẫn rằng liệu thu hồi từ việc phá dỡ sẽ vẫn là tài sản của Chủ đầu tư trừ khi được quy định khác trong các tài liệu hợp đồng. (b) Tất cả các tài liệu có thể bán được chỉ định sẽ được gỡ bỏ, withou















































































































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: