11. The purpose of the Initiation process is to:A. Formally recognize  dịch - 11. The purpose of the Initiation process is to:A. Formally recognize  Việt làm thế nào để nói

11. The purpose of the Initiation p

11. The purpose of the Initiation process is to:
A. Formally recognize the existence of a project or project phase
B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technologi-cal advances, or legal requirements
C. Formally recognize the stakeholders of the project and identify them in the project charter
D. Formally recognize the project sponsor and document his or her project goals
12. Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the orga-nization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project?
A. The strategic plan, because you’ll want to make sure the project reflects the overall strategic direction of the organization.
B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is sim-ilar in nature.
C. The product description, which would describe all the details of the run/walk program.
D. Historical information from the recent blood drive project.
13. Which of the following is true regarding product descriptions?
A. The product description is an output of the Initiation process. It describes the characteristics of the product or service.
B. The product description is an output of the Initiation process. It describes the characteristics of the product or service and contains less detail in the early phases of the project.
C. The product description is an input of the Initiation process. It describes the characteristics of the product or service and contains a lot of detail in the early phases of the project.
D. The product description is an input of the Initiation process. It describes the characteristics of the product or service.
14. Deliverables can be described as:
A. The purpose for undertaking the project
B. The verifiable results of products or services that must be produced to consider the project complete
C. The specifications regarding the goals of the project that must be produced to consider the project complete
D. The measurable outcomes of the project goals
15. You are a project manager working on a new software product your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late Sep-tember and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project?
A. Budget
B. Quality
C. Time
D. Schedule
16. You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She’s looking to you to make this documen-tary the best that’s ever been produced in the history of this com-pany. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photogra-pher in the company is currently working on another assignment. Which of the following is true?
A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible.
B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects.
C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made.
D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She’s given you free rein to use whatever resources needed to get the job done.
17. What limits the options of the project team?
A. Technology
B. Constraints
C. Deliverables
D. Assumptions
18. Your project depends on a key deliverable from a vendor you’ve used several times before with great success. You’re counting on the deliv-ery to arrive on June 1. This is an example of:
A. Constraint
B. Objective
C. Assumption
D. Goal
19. Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true?
A. This project came about due to customer request, and the primary constraint is time.
B. This project came about due to market demand, and the primary constraint is time.
C. This project came about due to market demand, and the primary constraint is quality.
D. This project came about due to customer request, and the primary constraint is quality.
20. Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has continued to increase over the past 18 months. The phone system is approaching the maximum load limits and needs to be upgraded. You’ve been assigned to head up the upgrade project. Based on the company’s experience with the vendor who worked on the last phone upgrade project, you’re confident they’ll be able to assist you with this project as well. Which of the following is true?
A. You’ve made an assumption about vendor availability and exper-tise. The project came about due to a business need.
B. Vendor availability and expertise are constraints. The project came about due to a business need.
C. You’ve made an assumption about vendor availability and exper-tise. The project came about due to a marketing demand.
D. Vendor availability and expertise are constraints. The project came about due to a marketing demand.
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
11. The purpose of the Initiation process is to:A. Formally recognize the existence of a project or project phaseB. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technologi-cal advances, or legal requirementsC. Formally recognize the stakeholders of the project and identify them in the project charterD. Formally recognize the project sponsor and document his or her project goals12. Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the orga-nization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project?A. The strategic plan, because you’ll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is sim-ilar in nature.C. The product description, which would describe all the details of the run/walk program.D. Historical information from the recent blood drive project.13. Which of the following is true regarding product descriptions?A. The product description is an output of the Initiation process. It describes the characteristics of the product or service.B. The product description is an output of the Initiation process. It describes the characteristics of the product or service and contains less detail in the early phases of the project.C. The product description is an input of the Initiation process. It describes the characteristics of the product or service and contains a lot of detail in the early phases of the project.D. The product description is an input of the Initiation process. It describes the characteristics of the product or service.14. Deliverables can be described as:A. The purpose for undertaking the projectB. The verifiable results of products or services that must be produced to consider the project completeC. The specifications regarding the goals of the project that must be produced to consider the project completeD. The measurable outcomes of the project goals15. You are a project manager working on a new software product your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late Sep-tember and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project?A. BudgetB. QualityC. TimeD. Schedule16. You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She’s looking to you to make this documen-tary the best that’s ever been produced in the history of this com-pany. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photogra-pher in the company is currently working on another assignment. Which of the following is true?A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible.B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made.D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She’s given you free rein to use whatever resources needed to get the job done.17. What limits the options of the project team? A. Technology B. ConstraintsC. DeliverablesD. Assumptions18. Your project depends on a key deliverable from a vendor you’ve used several times before with great success. You’re counting on the deliv-ery to arrive on June 1. This is an example of:A. ConstraintB. ObjectiveC. AssumptionD. Goal19. Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true?A. This project came about due to customer request, and the primary constraint is time.B. This project came about due to market demand, and the primary constraint is time.C. This project came about due to market demand, and the primary constraint is quality.D. This project came about due to customer request, and the primary constraint is quality.20. Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has continued to increase over the past 18 months. The phone system is approaching the maximum load limits and needs to be upgraded. You’ve been assigned to head up the upgrade project. Based on the company’s experience with the vendor who worked on the last phone upgrade project, you’re confident they’ll be able to assist you with this project as well. Which of the following is true?A. You’ve made an assumption about vendor availability and exper-tise. The project came about due to a business need.B. Vendor availability and expertise are constraints. The project came about due to a business need.C. You’ve made an assumption about vendor availability and exper-tise. The project came about due to a marketing demand.D. Vendor availability and expertise are constraints. The project came about due to a marketing demand.
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
11. Mục đích của quá trình Initiation là:
A. Chính thức công nhận sự tồn tại của một dự án, dự án giai đoạn
B. Chính thức công nhận sự cần thiết đó đã mang về dự án được tiếp thị nó nhu cầu, yêu cầu của khách hàng, nhu cầu kinh doanh, tiến technologi-cal, hoặc các yêu cầu pháp lý
C. Chính thức công nhận các bên liên quan của dự án và xác định chúng trong các điều lệ dự án
D. Chính thức công nhận tài trợ dự án và tài liệu mục tiêu của mình, dự án của mình
12. Tổ chức phi lợi nhuận của bạn đang chuẩn bị để tổ chức đầu tiên của năm 5K chạy / đi bộ trong công viên thành phố. Bạn đã làm việc trên một dự án tương tự cho Orga-nization hai năm trước khi nó đồng tổ chức chạy 10K qua Overland Pass. Mà trong quá trình đầu vào Initiation có thể hữu ích cho bạn về dự án mới của bạn?
A. Kế hoạch chiến lược, bởi vì bạn sẽ muốn chắc chắn rằng dự án phản ánh định hướng chiến lược tổng thể của tổ chức.
B. Thông tin lịch sử về các dự án 10K chạy. Bạn có thể có thể thu thập thông tin dự án hữu ích kể từ khi dự án mới này là sim-ilar trong tự nhiên.
C. Các mô tả sản phẩm, trong đó sẽ mô tả tất cả các chi tiết của chạy / đi bộ chương trình.
D. Thông tin lịch sử từ các dự án động hiến máu gần đây.
13. Điều nào sau đây là đúng sự thật liên quan đến giới thiệu sản phẩm?
A. Các mô tả sản phẩm là kết quả của quá trình Initiation. Nó mô tả các đặc tính của sản phẩm hoặc dịch vụ.
B. Các mô tả sản phẩm là kết quả của quá trình Initiation. Nó mô tả các đặc tính của sản phẩm hoặc dịch vụ và có ít chi tiết hơn trong các giai đoạn đầu của dự án.
C. Các mô tả sản phẩm là một đầu vào của quá trình Initiation. Nó mô tả các đặc tính của sản phẩm hoặc dịch vụ và có rất nhiều chi tiết trong giai đoạn đầu của dự án.
D. Các mô tả sản phẩm là một đầu vào của quá trình Initiation. Nó mô tả các đặc tính của sản phẩm hoặc dịch vụ.
14. Phân phôi có thể được mô tả như là:
A. Mục đích của việc thực hiện các dự án
B. Các kết quả kiểm chứng của sản phẩm hoặc dịch vụ phải được sản xuất để xem xét dự án hoàn chỉnh
C. Các thông số kỹ thuật liên quan đến các mục tiêu của dự án phải được sản xuất để xem xét dự án hoàn chỉnh
D. Các kết quả đo lường được các mục tiêu dự án
15. Bạn là một người quản lý dự án làm việc trên một sản phẩm phần mềm mới của công ty bạn có kế hoạch đưa ra thị trường cho các doanh nghiệp. Các nhà tài trợ dự án nói với bạn rằng dự án phải được hoàn thành vào Tháng Chín 1. Công ty có kế hoạch giới thiệu các sản phẩm phần mềm mới tại một hội chợ thương mại vào cuối tháng chín-tember và do đó cần các dự án hoàn thành trong thời gian cho các chương trình thương mại. Tuy nhiên, các nhà tài trợ cũng đã nói với bạn rằng ngân sách được cố định ở mức $ 85,000 và không thể tăng ngay cả $ 10 do cắt giảm ngân sách tổng thể năm nay. Bạn phải hoàn thành các dự án trong khung thời gian nhất định và ngân sách. Điều nào sau đây là trở ngại chính cho dự án này?
A. Ngân sách
B. Chất lượng
C. Thời gian
D. Biểu
16. Bạn là một người quản lý dự án cho một công ty điện ảnh tài liệu. Trong ánh sáng của một bi kịch quốc gia gần đây, Chủ tịch công ty muốn có được một bộ phim tài liệu mới về các nỗ lực cứu hộ của các nhân viên cứu hỏa anh hùng để không khí càng sớm càng tốt. Cô ấy đang tìm cách để bạn thực hiện điều này documen-tary các tuyệt nhất từng được sản xuất trong lịch sử này com-pany. Cô đảm bảo cho bạn tự do hoàn toàn để sử dụng bất cứ tài nguyên mà bạn cần để có được dự án này được thực hiện một cách nhanh chóng. Tuy nhiên, các photogra-pher tốt nhất trong các công ty hiện đang làm việc trên giao khác. Điều nào sau đây là đúng?
A. Các hạn chế chính là thời gian bởi vì tổng thống muốn bộ phim được thực hiện một cách nhanh chóng. Cô ấy nói với bạn để có được nó vào không khí càng sớm càng tốt.
B. Tài nguyên là các ràng buộc chính. Mặc dù Tổng thống đã đưa cho bạn tự do hoàn toàn về việc sử dụng tài nguyên, bạn giả sử cô ấy không có nghĩa là những người chủ động giao cho các dự án.
C. Lịch trình là trở ngại chính. Mặc dù Tổng thống đã đưa cho bạn tự do hoàn toàn về việc sử dụng tài nguyên, bạn giả sử cô ấy không có nghĩa là những người chủ động giao cho các dự án. Các nhiếp ảnh gia sẽ không được hoàn thành trong ba tuần nữa về phân công hiện tại của mình, do đó điều chỉnh lịch trình sẽ phải được thực hiện.
D. Các hạn chế chính là chất lượng do chủ tịch muốn này là bộ phim hay nhất từng được sản xuất bởi công ty này. Cô ấy đưa cho bạn tự do hoàn toàn để sử dụng bất cứ nguồn lực cần thiết để hoàn thành công việc.
17. Điều gì hạn chế các lựa chọn của nhóm dự án?
A. Công nghệ
B. Hạn chế
C. Phân phôi
D. Giả định
18. Dự án của bạn phụ thuộc vào có bước tiến quan trọng từ một nhà cung cấp mà bạn đã sử dụng một vài lần trước khi thành công tốt đẹp. Bạn đang đếm trên deliv-ery đến vào tháng 1. Đây là một ví dụ của:
A. Hạn chế
B. Mục tiêu
C. Assumption
D. Mục tiêu
19. Halloween đang đến gần nhanh. Nghiên cứu thị trường cho thấy gà con màu vàng và màu hồng ít kẹo marshmallow bunny là kẹo bán chạy nhất tại thời Phục, vượt qua tất cả các loại bánh kẹo. Điều này thúc đẩy các công ty để giới thiệu một phiên bản mới của kẹo marshmallow với chủ đề Halloween trong mùa giải này. Điều nào sau đây là đúng?
A. Dự án này đã về do yêu cầu của khách hàng, và các hạn chế chính là thời gian.
B. Dự án này đã về do nhu cầu thị trường, và các hạn chế chính là thời gian.
C. Dự án này đã về do nhu cầu thị trường, và các hạn chế chính là chất lượng.
D. Dự án này đã về do yêu cầu của khách hàng, và các hạn chế chính là chất lượng.
20. Công ty của bạn cung cấp dịch vụ trả lời cho một số nhà bán lẻ Danh mục chính. Số lượng các cuộc gọi đi vào các trung tâm dịch vụ mỗi tháng tiếp tục tăng trong vòng 18 tháng qua. Các hệ thống điện thoại đang đến gần giới hạn tải trọng tối đa và cần được nâng cấp. Bạn đã được phân công để đi lên các dự án nâng cấp. Dựa trên kinh nghiệm của công ty với các nhà cung cấp, người làm việc trên các dự án nâng cấp điện thoại cuối cùng, bạn đang tự tin rằng họ sẽ có thể giúp bạn với dự án này là tốt. Điều nào sau đây là đúng?
A. Bạn đã thực hiện một giả định về nhà cung cấp sẵn sàng và exper-tise. Dự án đã về do nhu cầu kinh doanh.
B. Nhà cung cấp sẵn có và chuyên môn hạn chế. Dự án đã về do nhu cầu kinh doanh.
C. Bạn đã thực hiện một giả định về nhà cung cấp sẵn sàng và exper-tise. Dự án đã về do nhu cầu thị trường.
D. Nhà cung cấp sẵn có và chuyên môn hạn chế. Dự án đã về do nhu cầu thị trường.
đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.