ADMINISTRATIVE CLOSUREThe project or phase, after either achieving its objectives or being terminated for other reasons, requires closure. Administrative closure consists of documenting project results to formalize acceptance of the product of the project by the sponsor, or customer. It includes collecting project records; ensuring that they reflect final specifications; analyzing project success, effectiveness, and lessons learned; and archiving such information for future use.Administrative closure activities should not be delayed until project comple- tion. Each phase of the project should be properly closed to ensure that impor- tant and useful information is not lost. In addition, employee skills in the staff pool database should be updated to reflect new skills and proficiency increases.