1. The Project Integration Management knowledge area is made up of which of the following processes?
A. Initiation, Project Plan Development, and Integrated Change Control
B. Project Plan Development, Project Plan Execution, and Integrated Change Control
C. Project Plan Development, Initiation, and Scope Planning
D. Initiation, Scope Planning, and Integrated Change Control
2. When a project is being performed under contract, the product description is provided by which of the following?
A. The buyer
B. The project sponsor
C. The project manager
D. The contractor
3. You are the project manager for Fun Days vacation packages. Your new project assignment is to head up the Fun Days resort opening in Austin, Texas. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and control-ling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in?
A. Project Scope
B. Project Quality
C. Project Integration
D. Project Time
4. The Project Human Resource Management knowledge area contains which of the following processes?
A. Staff Acquisition, Team Development, and Resource Planning
B. Staff Acquisition, Team Development, and Performance Reporting
C. Organizational Planning, Staff Acquisition, and Team Development
D. Organization Planning, Team Development, and Resource Planning
5. Your company is going to introduce a new service called Phone Home. This service will allow you to speak the name of the person you want to call into your cellular phone. To call home, you would simply speak the word home into the phone, and it will dial that number for you. Your company is taking advantage of the progress that has been made recently with voice recognition software. Initial projections show that market demand is very high for this product. This project came about as a result of which of the following?
A. Marketing demand
B. Customer request
C. Business need
D. Technological advance
6. You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to con-vert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following?
A. Technological advance
B. Business need
C. Customer request
D. Legal requirement
7. What are the inputs to the Initiation process?
A. Product description, strategic plan, project selection criteria, and historical information
B. Product description, strategic plan, project overview document, and historical information
C. Strategic plan, project overview document, feasibility study, and historical information
D. Product description, strategic plan, constraints, and assumptions
8. You work for a large manufacturing plant. You’re working on a new project for an overseas product release. This is the company’s first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true?
A. The new machine, the concentrated formula, and the smaller pack-age are each project constraints.
B. The new machine, the concentrated formula, and the smaller pack-age description must be incorporated into the product description document.
C. The new machine, the concentrated formula, and the smaller pack-age are each project assumptions.
D. The new machine, the concentrated formula, and the smaller pack-age are each considered deliverables.
9. You work for a large manufacturing plant. You’re in the Initiation pro-cess of a new project for an overseas product release. This is the com-pany’s first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails pro-ducing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take?
A. The project manager should document the project’s goals and known deliverables in a high-level overview document and recom-mend the project proceed.
B. The project manager should document the project’s goals and known deliverables in a high-level overview document and assume the project is a go.
C. The project manager should document the project’s goals and known deliverables in a high-level overview document and recom-mend a feasibility study be performed.
D. The project manager should document the project’s goals and known deliverables in a high-level overview document and deliver it to the stakeholders.
10. What are the Initiation process outputs?
A. Project charter, identification and assignment of project manager, constraints, and project overview documents
B. Project charter, project overview, feasibility study, and constraints
C. Project charter, identification and assignment of project manager, constraints, and assumptions
D. Identification and assignment of project manager, project over-view, constraints, and assumptions
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
1. khu vực kiến thức quản lý hội nhập dự án được tạo thành từ mà các quy trình sau đây?A. khởi xướng, dự án kế hoạch phát triển và thay đổi tích hợp kiểm soátDự án sinh kế hoạch phát triển, dự án kế hoạch thực hiện, và sự thay đổi tích hợp kiểm soátC. dự án kế hoạch phát triển, bắt đầu, và phạm vi quy hoạchMất bắt đầu, phạm vi quy hoạch và kiểm soát sự thay đổi tích hợp2. khi một dự án đang được thực hiện theo hợp đồng, mô tả sản phẩm được cung cấp bởi mà sau đây?A. người muaB. tài trợ dự ánC. Giám đốc dự ánD. các nhà thầu3. bạn là người quản lý dự án cho niềm vui ngày nghỉ dưỡng. Chuyển nhượng dự án mới của bạn là để đầu lên khu nghỉ mát niềm vui ngày mở ở Austin, Texas. Bạn đang ước tính thời lượng của các dự án kế hoạch hoạt động, đặt ra lịch trình dự án, và giám sát và điều khiển linh độ lệch từ lịch trình. Bạn đang làm việc tại đó trong lĩnh vực kiến thức quản lý dự án?A. dự án phạm viChất lượng sinh dự ánC. dự án hội nhậpMất dự án thời gian4. khu vực kiến thức quản lý nguồn nhân lực dự án này chứa mà các quy trình sau đây?Mua lại A. nhân viên, đội phát triển, và lập kế hoạch tài nguyênNhân viên phục vụ sinh mua lại, nhóm phát triển, và hiệu suất báo cáoC. kế hoạch tổ chức, nhân viên Mua lại và phát triển độiMất tổ chức lập kế hoạch, nhóm phát triển, và lập kế hoạch tài nguyên5. Your company is going to introduce a new service called Phone Home. This service will allow you to speak the name of the person you want to call into your cellular phone. To call home, you would simply speak the word home into the phone, and it will dial that number for you. Your company is taking advantage of the progress that has been made recently with voice recognition software. Initial projections show that market demand is very high for this product. This project came about as a result of which of the following?A. Marketing demandB. Customer requestC. Business needD. Technological advance6. You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to con-vert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following?A. Technological advanceB. Business needC. Customer requestD. Legal requirement7. What are the inputs to the Initiation process?A. Product description, strategic plan, project selection criteria, and historical informationB. Product description, strategic plan, project overview document, and historical informationC. Strategic plan, project overview document, feasibility study, and historical informationD. Product description, strategic plan, constraints, and assumptions8. You work for a large manufacturing plant. You’re working on a new project for an overseas product release. This is the company’s first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true?A. The new machine, the concentrated formula, and the smaller pack-age are each project constraints.B. The new machine, the concentrated formula, and the smaller pack-age description must be incorporated into the product description document.C. The new machine, the concentrated formula, and the smaller pack-age are each project assumptions.D. The new machine, the concentrated formula, and the smaller pack-age are each considered deliverables.9. You work for a large manufacturing plant. You’re in the Initiation pro-cess of a new project for an overseas product release. This is the com-pany’s first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails pro-ducing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take?A. The project manager should document the project’s goals and known deliverables in a high-level overview document and recom-mend the project proceed.B. The project manager should document the project’s goals and known deliverables in a high-level overview document and assume the project is a go.C. The project manager should document the project’s goals and known deliverables in a high-level overview document and recom-mend a feasibility study be performed.D. The project manager should document the project’s goals and known deliverables in a high-level overview document and deliver it to the stakeholders.10. What are the Initiation process outputs?A. Project charter, identification and assignment of project manager, constraints, and project overview documentsB. Project charter, project overview, feasibility study, and constraintsC. Project charter, identification and assignment of project manager, constraints, and assumptionsD. Identification and assignment of project manager, project over-view, constraints, and assumptions
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
1. Khu vực kiến thức Quản lý dự án tích hợp được tạo thành trong đó các quá trình sau đây?
A. Initiation, phát triển kế hoạch dự án, và tích hợp kiểm soát thay đổi
B. Phát triển dự án Kế hoạch, Thực hiện kế hoạch dự án, và tích hợp kiểm soát thay đổi
C. Phát triển dự án Plan, Initiation, và phạm vi quy hoạch
D. Initiation, Kế hoạch Phạm vi, tích hợp và kiểm soát thay đổi
2. Khi một dự án đang được thực hiện theo hợp đồng, mô tả sản phẩm được cung cấp bởi nào sau đây?
A. Người mua
B. Các nhà tài trợ dự án
C. Người quản lý dự án
D. Các nhà thầu
3. Bạn là người quản lý dự án đối với các gói kỳ nghỉ Fun Days. Chuyển nhượng dự án mới của bạn là để đi lên Fun Ngày resort khai mạc tại Austin, Texas. Bạn đang ước tính thời gian của các hoạt động kế hoạch dự án, vạch ra các kế hoạch dự án, giám sát và kiểm soát độ lệch-ling từ lịch sự. Mà các kiến thức quản lý các khu dự án bạn đang làm việc tại?
A. Dự án Phạm vi
B. Chất lượng dự án
C. Dự án tích hợp
D. Dự án Time
4. Khu vực kiến thức quản lý tài nguyên dự án Nhân chứa trong đó các quá trình sau đây?
A. Nhân viên thu, phát triển Team, và Resource Planning
B. Nhân viên thu, phát triển Team, và báo cáo hoạt
C. Kế hoạch tổ chức, cán bộ thu và phát triển đội
D. Kế hoạch tổ chức, phát triển Team, và hoạch định tài nguyên
5. Công ty của bạn là sẽ giới thiệu một dịch vụ mới gọi là điện thoại nhà. Dịch vụ này sẽ cho phép bạn nói tên của người mà bạn muốn gọi vào điện thoại di động của bạn. Để gọi điện về nhà, bạn chỉ cần nói từ nhà vào điện thoại, và nó sẽ quay số đó cho bạn. Công ty của bạn đang tận dụng những tiến bộ đã được thực hiện gần đây với phần mềm nhận dạng giọng nói. Dự ban đầu cho thấy nhu cầu thị trường là rất cao cho sản phẩm này. Dự án này xuất hiện như là một kết quả của nào sau đây?
A. Tiếp thị nhu cầu
B. Khách hàng yêu cầu
C. Doanh nghiệp cần
D. Tiến bộ công nghệ
6. Bạn là một người quản lý dự án cho bộ phận công nghệ thông tin của một công ty phát thanh truyền hình truyền hình vệ tinh địa phương. Mùa xuân này, các giám đốc thông tin cho công ty của bạn đã cho bạn những dự án để con-vert và nâng cấp tất cả các máy tính trong các bộ phận để phát hành mới nhất của một ứng dụng máy tính để bàn cụ thể. Trước khi chuyển đổi này, tất cả các cách thức của phần mềm máy tính để bàn tồn tại trên máy trong toàn công ty và đã gây ra nhiều vấn đề với việc chia sẻ tập tin và thông tin trong toàn công ty. Rất nhiều giờ không hiệu quả đã được chi gõ thông tin vào một số định dạng. Dự án này xuất hiện như là một kết quả của nào sau đây?
A. Công nghệ trước
B. Doanh nghiệp cần
C. Khách hàng yêu cầu
D. Yêu cầu pháp lý
7. Các yếu tố đầu vào cho quá trình Initiation là gì?
A. Mô tả sản phẩm, kế hoạch chiến lược, tiêu chí lựa chọn dự án, và thông tin lịch sử
B. Mô tả sản phẩm, kế hoạch chiến lược, tài liệu tổng quan về dự án, và thông tin lịch sử
C. Kế hoạch chiến lược, tài liệu tổng quan về dự án, nghiên cứu khả thi, và thông tin lịch sử
D. Mô tả sản phẩm, kế hoạch chiến lược, khó khăn, và giả định
8. Bạn làm việc cho một nhà máy sản xuất lớn. Bạn đang làm việc trên một dự án mới cho một bản phát hành sản phẩm ở nước ngoài. Đây là kinh nghiệm đầu tiên của công ty tại các thị trường nước ngoài, và họ hy vọng sẽ làm cho một giật gân lớn với sự ra đời của sản phẩm này. Dự án đòi hỏi phải sản xuất sản phẩm của bạn trong một công thức tập trung và đóng gói nó trong các thùng chứa nhỏ hơn so với các sản phẩm Mỹ sử dụng. Một máy mới là cần thiết để pha trộn các tập đầu tiên của các thành phần trong công thức tập trung. Điều nào sau đây là đúng?
A. Máy mới, công thức tập trung, và các gói trong độ tuổi nhỏ hơn là mỗi khó khăn của dự án.
B. Máy mới, công thức tập trung, và các mô tả gói nhỏ tuổi phải được đưa vào các tài liệu mô tả sản phẩm.
C. Máy mới, công thức tập trung, và các gói trong độ tuổi nhỏ hơn là giả định mỗi dự án.
D. Máy mới, công thức tập trung, và các gói trong độ tuổi nhỏ hơn là mỗi phân phôi coi.
9. Bạn làm việc cho một nhà máy sản xuất lớn. Bạn đang ở trong Initiation pro-cess của một dự án mới cho một bản phát hành sản phẩm ở nước ngoài. Đây là kinh nghiệm đầu tiên com-pany tại các thị trường nước ngoài, và họ hy vọng sẽ làm cho một giật gân lớn với sự ra đời của sản phẩm này. Dự án đòi hỏi pro-ducing sản phẩm của bạn trong một công thức tập trung và đóng gói nó trong các thùng chứa nhỏ hơn so với các sản phẩm Mỹ sử dụng. Một máy mới là cần thiết để pha trộn các tập đầu tiên của các thành phần trong công thức tập trung. Mà các hành động sau đây nên người quản lý dự án nào?
A. Người quản lý dự án nên ghi chép các mục tiêu của dự án và phân phôi được biết đến trong một tài liệu tổng quan cấp cao và được khuyến cáo-hàn gắn dự án tiến hành.
B. Người quản lý dự án nên ghi chép các mục tiêu của dự án và phân phôi được biết đến trong một tài liệu tổng quan cao cấp và giả định dự án là một đi.
C. Người quản lý dự án nên ghi chép các mục tiêu của dự án và phân phôi được biết đến trong một tài liệu tổng quan cấp cao và được khuyến cáo-hàn gắn một nghiên cứu khả thi được thực hiện.
D. Người quản lý dự án nên ghi chép các mục tiêu của dự án và phân phôi được biết đến trong một tài liệu tổng quan cao cấp và cung cấp cho các bên liên quan.
10. Kết quả đầu ra quá trình Initiation là gì?
A. Điều lệ của dự án, xác định và phân công của quản lý dự án, khó khăn, và tổng quan về dự án văn bản
B. Điều lệ dự án, tổng quan về dự án, nghiên cứu khả thi, và những hạn chế
C. Điều lệ của dự án, xác định và phân công của quản lý dự án, khó khăn, và giả định
D. Xác định và phân công của quản lý dự án, dự án trên-view, khó khăn, và giả định
đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2025 I Love Translation. All reserved.

E-mail: