-- For the erection of steel structure, 78 tons was erected last week; with the accumulated work volume was 5524 tons. - The accumulated concrete amount was poured for Decking 757m3.
-- For the erection of steel structure, 78 tons was erected last week; with theaccumulated work volume was 5524 tons.- The accumulated concrete amount was poured for Decking 757m3.
- Đối với việc lắp đặt kết cấu thép, 78 tấn đã được dựng lên với tuần trước; với khối lượng công việc tích lũy là 5524 tấn. - Số tiền tích lũy được bê tông được đổ cho Tấm tường quây che 757m3.