(i) The Contractor stops work for more than twenty0eight (28 days when no stoppage of the work is show on the current program without any authorization by the Engineer;(j) The Contractor fails to correct a defect within a reasonable period of time determined by the Engineer;(k) The Contractor has delayed the completion of the Works by 100 days for which the maximum amount of liquidated damages can be paid;(l) The Client and the Contractor may at any time terminate the contract by giving notice to the other party if either of party becomes bankrupt or otherwise insolvent;(m) The Contractor, in the judgment of the Client has engaged in corrupt or fraudulent practices, as defined in GCC Clause 3, in competing for or in executing the contract; and(n) A payment certified by the Engineer is not paid by the Project Owner to the Contractor within ninety (90) days of the date of the Engineer’s certificate.