EXAMPLE APPLICATION
Input
This example illustrates the use of the space scheduling algorithm to assess the feasibility of the schedule for a concrete foundation project and then to adjust this schedule to comply with site space limitations. This example is small, clue to page length limitations, but is clearly illustrates the method. The activity network shown in Fig. 3(a) describes construction of the north and east foundation walls of a building. The trenching and excavation work preceding the foundation walls' construction are completed and are not shown in the network.
Is Fig. 4(a) site dimensions are 22 X 12 units. No Dimensions are given to these units as they are irrelevant to the problem-solving method. The north trench is 2 units wide and 20 units long and runs along the northern site limit. The west trench is 2 units wide and 12 units long and runs along the west side. The east side of the site is fenced. The south side is only partially fenced with a reserved area of 4 by 3 located at 12 units from the southeast comer of the site, which serves as site access during this phase of construction.
Trenches, fence lines, and site access are modeled as Profile D resources—on-site for the duration of construction of this foundation wall. They arc stationary and have a fixed, user- defined position on-site |Fig. 4(a)]. Since the duration of this construction phase is not known at the time the independent resources are input, the user can assign an arbitrarily large number to TB to guarantee that the resource will be on-site for the entire project duration. The resource levels for each activity and data defining the resources in each level are input by the user (Tables 1 and 2). For the sake of brevity, only two resource levels are defined per activity.
Resources with fixed shape and dimensions (e.g., the pipe layer and the concrete batch plant) and resources used by more than one activity that remain idle on-site in-between uses (e.g., the lumber shop and the welding shop) are modeled using Profile C. Other dependent resources that get consumed in the construction process (e.g., aggregates, cement, rebar, pipe) are modeled using Profile A and Profile B, depending on whether the total quantity of the resource is brought to the site in one, or multiple, deliveries.
The relocation of the lumber shop and the concrete plant are restricted in this example. These resources may be relo- catable, but they are modeled here as stationary (i.e.. they cannot be relocated in different PTFs) to illustrate how positioning stationary resources may constrain the positions of other resources in subsequent layouts in a forward-pass approach.

Notation:
Activity description
duration; total float resources
6. Setup concrete batch plant area
7. Place concrete for north and east wall
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
VÍ DỤ ỨNG DỤNG Đầu vàoVí dụ này minh hoạ việc sử dụng không gian lập kế hoạch các thuật toán để đánh giá khả năng lịch trình cho một dự án nền tảng cụ thể và sau đó để điều chỉnh này tiến độ thực hiện theo trang web space giới hạn. Ví dụ này là nhỏ, đầu mối để trang dài hạn chế, nhưng rõ ràng là minh họa các phương pháp. Mạng lưới hoạt động hiển thị trong hình 3(a) Mô tả xây dựng phía Bắc và đông quỹ bức tường của một tòa nhà. Trenching và khai quật làm việc ngay trước các bức tường quỹ xây dựng được hoàn thành và không được hiển thị trong mạng.Là hình 4(a) trang web kích thước là 22 X 12 đơn vị. Kích thước không được trao cho các đơn vị như họ không liên quan đến phương pháp giải quyết vấn đề. Rãnh Bắc là 2 đơn vị rộng và 20 đơn vị dài và chạy dọc theo giới hạn phía bắc trang web. Rãnh Tây là 2 đơn vị rộng và 12 đơn vị dài và chạy dọc theo phía tây. Phía đông của trang web là oa trư. Phía nam là chỉ một phần rào với một khu vực dành riêng của 4 bởi 3 nằm ở 12 đơn vị từ chuyển đến đông nam của trang web, mà phục vụ như truy cập trang web trong giai đoạn này của xây dựng.Trenches, fence lines, and site access are modeled as Profile D resources—on-site for the duration of construction of this foundation wall. They arc stationary and have a fixed, user- defined position on-site |Fig. 4(a)]. Since the duration of this construction phase is not known at the time the independent resources are input, the user can assign an arbitrarily large number to TB to guarantee that the resource will be on-site for the entire project duration. The resource levels for each activity and data defining the resources in each level are input by the user (Tables 1 and 2). For the sake of brevity, only two resource levels are defined per activity.Resources with fixed shape and dimensions (e.g., the pipe layer and the concrete batch plant) and resources used by more than one activity that remain idle on-site in-between uses (e.g., the lumber shop and the welding shop) are modeled using Profile C. Other dependent resources that get consumed in the construction process (e.g., aggregates, cement, rebar, pipe) are modeled using Profile A and Profile B, depending on whether the total quantity of the resource is brought to the site in one, or multiple, deliveries.The relocation of the lumber shop and the concrete plant are restricted in this example. These resources may be relo- catable, but they are modeled here as stationary (i.e.. they cannot be relocated in different PTFs) to illustrate how positioning stationary resources may constrain the positions of other resources in subsequent layouts in a forward-pass approach. Notation:Activity descriptionduration; total float resources6. Setup concrete batch plant area7. Place concrete for north and east wall
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
VÍ DỤ ÁP DỤNG
Input
Ví dụ này minh họa việc sử dụng các thuật toán lập lịch không gian để đánh giá tính khả thi của kế hoạch cho một dự án nền tảng cụ thể và sau đó để điều chỉnh lịch trình này thực hiện đúng những hạn chế không gian trang web. Đây là ví dụ nhỏ, đầu mối để hạn chế chiều dài trang, nhưng rõ ràng là minh họa phương pháp này. Mạng lưới hoạt động thể hiện trong hình. 3 (a) mô tả xây dựng các bức tường phía bắc và phía đông nền tảng của một tòa nhà. Việc đào rãnh và khai quật làm việc trước xây dựng các bức tường nền tảng 'được hoàn thành và không được hiển thị trong mạng.
Là hình. 4 (a) kích thước trang là 22 X 12 đơn vị. Không Kích thước được trao cho các đơn vị này khi họ không liên quan đến các phương pháp giải quyết vấn đề. Các rãnh phía bắc là 2 đơn vị rộng và dài 20 đơn vị và chạy dọc theo giới hạn trang phía Bắc. Phía tây hào là 2 đơn vị rộng và dài 12 đơn vị và chạy dọc theo phía tây. Phía đông của trang web là rào. Phía nam là chỉ có một phần hàng rào với một khu vực dành riêng của 4 bởi 3 tọa lạc tại 12 đơn vị từ comer phía đông nam của trang web, trong đó phục vụ như truy cập trang web trong giai đoạn này xây dựng.
Trenches, đường hàng rào, và truy cập trang web được mô hình hóa như hồ sơ D tài nguyên-on-site trong thời gian xây dựng các bức tường nền tảng này. Họ arc văn phòng phẩm và có một vị trí cố định, do người sử dụng định nghĩa trên trang web | Hình. 4 (a)]. Kể từ thời gian của giai đoạn xây dựng này không được biết vào thời điểm tài nguyên độc lập là đầu vào, người dùng có thể chỉ định một số tùy tiện lớn để lao để đảm bảo rằng các nguồn tài nguyên sẽ được trên trang web cho toàn bộ thời gian của dự án. Các mức tài nguyên cho từng hoạt động và dữ liệu xác định các nguồn lực trong mỗi cấp độ là đầu vào bởi người sử dụng (Bảng 1 và 2). Vì lợi ích của ngắn gọn, chỉ có hai mức tài nguyên được định nghĩa cho mỗi hoạt động.
nguyên với hình dạng và kích thước cố định (ví dụ, lớp đường ống và các trạm trộn bê tông) và các nguồn lực được sử dụng bởi nhiều hơn một hoạt động mà vẫn nhàn rỗi tại chỗ ở giữa sử dụng (ví dụ, các cửa hàng gỗ và các cửa hàng hàn) được mô phỏng bằng các hồ sơ C. phụ thuộc tài nguyên khác mà có được tiêu thụ trong quá trình xây dựng (ví dụ, cốt liệu, xi ​​măng, thép xây dựng, ống) đều được mô phỏng bằng các hồ sơ A và B hồ sơ, tùy thuộc vào dù tổng số lượng tài nguyên được đưa đến trang web trong một, hoặc nhiều, giao hàng.
Việc di dời các cửa hàng gỗ và các nhà máy bê tông đang bị giới hạn trong ví dụ này. Những tài nguyên này có thể catable relo-, nhưng họ được mô phỏng ở đây như văn phòng phẩm (tức là. Họ không thể di dời trong PTFs khác nhau) để minh họa cách định vị các tài nguyên văn phòng phẩm có thể hạn chế các vị trí của các nguồn lực khác trong bố trí tiếp theo trong một cách tiếp cận về phía trước vượt qua. Notation : Mô tả Hoạt động thời gian; tổng nguồn float 6. Thiết lập hàng loạt bê tông diện tích cây trồng 7. Đặt bê tông cho phía bắc và phía đông tường






đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2025 I Love Translation. All reserved.

E-mail: