Present Worth, PW(i)The present worth, PW(i), of a cash-flow stream sh dịch - Present Worth, PW(i)The present worth, PW(i), of a cash-flow stream sh Việt làm thế nào để nói

Present Worth, PW(i)The present wor

Present Worth, PW(i)
The present worth, PW(i), of a cash-flow stream shows how much that future stream is worth ("is equivalent to") right now at interest rate, i. The reference time frame for PW(i) is today, or, more precisely, the beginning of the first period (the end of period 0) of the cash-flow stream. Present worth is also called net present value, or NPV. The present worth is the answer to the question, "How much is this cash-flow stream worth today?"

The "present" can be any arbitrary point in time as appropriate for the decision being studied. In 1999, we could have talked about the PW(i) of a cash-flow stream that's planned to begin in 2009 and includes cash-flow instances through 2011.

The formula for calculating the PW(i) of a cash-flow stream is





Where Ft is the net cash-flow instance in period t.

The PW(i) formula essentially uses the single-payment present-worth (P/F,i,n) formula to translate each individual net cash-flow instance to its corresponding end-of-year-0 amount and then sums up all of those amounts. This is exactly the same approach as was used in Table 7.2 in the preceding chapter. Table 8.3 shows how PW(i) can be hand-calculated for Mr. Kinkaid's project. A spreadsheet that automates these calculations can be found at http://www.construx.com/returnonsw/. The table shows that Mr. Kinkaid's project is financially equivalent to his receiving a one-time net income of $4557 today.

Table 8.3. Manual Calculation of PW(i) for Mr. Kinkaid's Project Year
Net Cash Flow
Present-Worth Factor
Present Worth

P/F,9,0

0
–$10,000
(1.000)
–$10,000

P/F,9,1

1
–$850
(0.9174)
–$780

P/F,9,2

2
$650
(0.8417)
$547

P/F,9,3

3
$2900
(0.7722)
$2239

P/F,9,4

4
$8150
(0.7084)
$5774

P/F,9,5

5
$5900
(0.6499)
$3835

P/F,9,6

6
$3650
(0.5963)
$2176

P/F,9,7

7
$1400
(0.5470)
$766

PW(9%) = $4557





Notice that except for year 0 the individual present-worth values are always less than their original cash-flow instance. Some people refer to the process of translating cash-flow instances backward in time as "discounting," and also refer to the interest rate used in the calculations as the "discount rate."

Present worth is the second most widely used basis for comparison. Payback period, below, is the most widely used. The main advantages of PW(i) are that it's relatively simple to compute and it's easy to understand the meaning of the result. Any arbitrary cash-flow stream can be converted to a present worth and compared to any other arbitrary cash-flow stream. Expressed in PW(i) form, any two cash-flow streams can be easily compared.

On the other hand, PW(i) hides some possibly important information about the cash-flow stream. The amounts and the timings of the cash flows are hidden; so even though a given cash-flow stream may have a higher PW(i) than another, its initial investment may be more than the organization can afford. That proposal would be impossible to carry out regardless of how profitable it might be.

SOME ADDITIONAL COMMENTS ON PW(i)
For any given cash-flow stream, there will always be a single value of PW(i) for each unique interest rate. Generally speaking, as the interest rate goes up, the PW(i) of the cash-flow stream goes down. Figure 8.2 shows the PW(i) for Mr. Kinkaid's project over a range of interest rates. Whereas PW(i) calculations are actually meaningful over the range of –1 < i < , only the range 0 i < is important because negative interest rates are virtually impossible in practice—it's highly unlikely that anyone would ever be willing to pay you to borrow his money.


Figure 8.2. PW(i) over a range of i's for Mr. Kinkaid's project





If Mr. Kinkaid's estimates of all the cash flows are accurate, the graph in Figure 8.2 tells him several important things about his proposal. First, given some interest rate, the graph tells him how much profit (or loss if that interest rate is too high) he would get, in present-day terms, from his project. The graph also tells him what range of interest rates his project would be profitable in and in which ones it wouldn't. Finally, the picture tells him the "critical i" where PW(i) = 0. This critical i is discussed later in this chapter in the section "Internal Rate of Return, IRR."

Previous Section < Day Day Up > Next Section

0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
Present Worth, PW(i)
The present worth, PW(i), of a cash-flow stream shows how much that future stream is worth ("is equivalent to") right now at interest rate, i. The reference time frame for PW(i) is today, or, more precisely, the beginning of the first period (the end of period 0) of the cash-flow stream. Present worth is also called net present value, or NPV. The present worth is the answer to the question, "How much is this cash-flow stream worth today?"

The "present" can be any arbitrary point in time as appropriate for the decision being studied. In 1999, we could have talked about the PW(i) of a cash-flow stream that's planned to begin in 2009 and includes cash-flow instances through 2011.

The formula for calculating the PW(i) of a cash-flow stream is





Where Ft is the net cash-flow instance in period t.

The PW(i) formula essentially uses the single-payment present-worth (P/F,i,n) formula to translate each individual net cash-flow instance to its corresponding end-of-year-0 amount and then sums up all of those amounts. This is exactly the same approach as was used in Table 7.2 in the preceding chapter. Table 8.3 shows how PW(i) can be hand-calculated for Mr. Kinkaid's project. A spreadsheet that automates these calculations can be found at http://www.construx.com/returnonsw/. The table shows that Mr. Kinkaid's project is financially equivalent to his receiving a one-time net income of $4557 today.

Table 8.3. Manual Calculation of PW(i) for Mr. Kinkaid's Project Year
Net Cash Flow
Present-Worth Factor
Present Worth

P/F,9,0

0
–$10,000
(1.000)
–$10,000

P/F,9,1

1
–$850
(0.9174)
–$780

P/F,9,2

2
$650
(0.8417)
$547

P/F,9,3

3
$2900
(0.7722)
$2239

P/F,9,4

4
$8150
(0.7084)
$5774

P/F,9,5

5
$5900
(0.6499)
$3835

P/F,9,6

6
$3650
(0.5963)
$2176

P/F,9,7

7
$1400
(0.5470)
$766

PW(9%) = $4557





Notice that except for year 0 the individual present-worth values are always less than their original cash-flow instance. Some people refer to the process of translating cash-flow instances backward in time as "discounting," and also refer to the interest rate used in the calculations as the "discount rate."

Present worth is the second most widely used basis for comparison. Payback period, below, is the most widely used. The main advantages of PW(i) are that it's relatively simple to compute and it's easy to understand the meaning of the result. Any arbitrary cash-flow stream can be converted to a present worth and compared to any other arbitrary cash-flow stream. Expressed in PW(i) form, any two cash-flow streams can be easily compared.

On the other hand, PW(i) hides some possibly important information about the cash-flow stream. The amounts and the timings of the cash flows are hidden; so even though a given cash-flow stream may have a higher PW(i) than another, its initial investment may be more than the organization can afford. That proposal would be impossible to carry out regardless of how profitable it might be.

SOME ADDITIONAL COMMENTS ON PW(i)
For any given cash-flow stream, there will always be a single value of PW(i) for each unique interest rate. Generally speaking, as the interest rate goes up, the PW(i) of the cash-flow stream goes down. Figure 8.2 shows the PW(i) for Mr. Kinkaid's project over a range of interest rates. Whereas PW(i) calculations are actually meaningful over the range of –1 < i < , only the range 0 i < is important because negative interest rates are virtually impossible in practice—it's highly unlikely that anyone would ever be willing to pay you to borrow his money.


Figure 8.2. PW(i) over a range of i's for Mr. Kinkaid's project





If Mr. Kinkaid's estimates of all the cash flows are accurate, the graph in Figure 8.2 tells him several important things about his proposal. First, given some interest rate, the graph tells him how much profit (or loss if that interest rate is too high) he would get, in present-day terms, from his project. The graph also tells him what range of interest rates his project would be profitable in and in which ones it wouldn't. Finally, the picture tells him the "critical i" where PW(i) = 0. This critical i is discussed later in this chapter in the section "Internal Rate of Return, IRR."

Previous Section < Day Day Up > Next Section

đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
Hiện Worth, PW (i)
Các giá trị hiện tại, PW (i), của một dòng tiền mặt lưu cho thấy bao nhiêu cho rằng, luồng tương lai là giá trị ("tương đương với") ngay bây giờ với lãi suất, i. Khung thời gian tham khảo cho PW (i) là ngày hôm nay, hay nói chính xác hơn, sự khởi đầu của giai đoạn đầu tiên (cuối kỳ 0) của dòng tiền chảy. Giá trị hiện tại cũng được gọi là giá trị hiện tại ròng, hoặc NPV. Các giá trị hiện nay là câu trả lời cho câu hỏi, "Bao nhiêu là dòng tiền này dòng giá trị ngày hôm nay?" "Hiện tại" có thể là bất kỳ điểm tùy ý trong thời gian thích hợp cho các quyết định đang được nghiên cứu. Năm 1999, chúng ta có thể nói về PW (i) của một dòng tiền mặt lưu mà là kế hoạch để bắt đầu vào năm 2009 và bao gồm các trường hợp dòng tiền thông qua năm 2011. Các công thức tính PW (i) của một dòng tiền mặt lưu là nơi Ft là trường hợp dòng tiền ròng trong kỳ t. Các PW (i) Công thức cơ bản sử dụng các đơn thanh toán hiện tại-giá trị (P / F, i, n) Công thức để dịch từng trường hợp dòng tiền ròng cá nhân tương ứng của nó kết thúc-của-năm-0 lượng và sau đó tóm tắt tất cả những khoản này. Đây chính là cách tiếp cận tương tự như đã được sử dụng trong Bảng 7.2 trong chương trước. Bảng 8.3 cho thấy cách PW (i) có thể được tính toán bằng tay cho dự án của ông Kinkaid. Một bảng tính tự động hóa những tính toán này có thể được tìm thấy tại http://www.construx.com/returnonsw/. Bảng này cho thấy rằng dự án của ông Kinkaid là tài chính tương đương với nhận mình một thu nhập ròng một lần $ 4557 ngày hôm nay. Bảng 8.3. Tính toán bằng tay của PW (i) cho Dự án năm của ông Kinkaid Net Cash Flow Present-Worth Yếu tố hiện tại = $ 4557 Chú ý rằng ngoại trừ năm 0 các giá trị hiện tại, giá trị cá nhân luôn luôn ít hơn ví dụ dòng tiền ban đầu của họ. Một số người đề cập đến quá trình dịch các trường hợp dòng tiền quay trở lại trong thời gian là "chiết khấu", và cũng tham khảo lãi suất được sử dụng trong các tính toán như "tỷ lệ chiết khấu." giá trị hiện tại là cơ sở được sử dụng nhiều thứ hai để so sánh. Thời gian hoàn vốn, bên dưới, là được sử dụng rộng rãi nhất. Các ưu điểm chính của PW (i) được rằng nó tương đối đơn giản để tính toán và rất dễ dàng để hiểu được ý nghĩa của kết quả. Bất kỳ dòng dòng tiền tùy ý có thể được chuyển đổi thành một giá trị hiện tại và so sánh với bất kỳ tùy ý dòng dòng tiền khác. Thể hiện trong PW (i) hình thức, bất kỳ hai dòng dòng tiền có thể dễ dàng so sánh. Mặt khác, PW (i) che đi một số thông tin có thể quan trọng về dòng tiền mặt lưu. Các số liệu và các timings của dòng tiền là ẩn; nên mặc dù một dòng dòng tiền nhất định có thể có một PW cao (i) hơn người khác, đầu tư ban đầu của nó có thể được nhiều hơn so với các tổ chức có thể đủ khả năng. Đề nghị đó sẽ không thể thực hiện bất kể như thế nào nó có thể mang lại lợi nhuận. MỘT SỐ Ý KIẾN BỔ PW (i) Đối với bất kỳ dòng dòng tiền nhất định, sẽ luôn có một giá trị duy nhất của PW (i) cho mỗi mức lãi suất độc đáo. Nói chung, khi lãi suất tăng lên, các PW (i) của dòng tiền chảy đi xuống. Hình 8.2 cho thấy các PW (i) cho dự án của ông Kinkaid qua một loạt các lãi suất. Trong khi đó, PW (i) tính toán thực sự có ý nghĩa trong phạm vi của -1 <i <, chỉ khoảng 0 <i là quan trọng, bởi vì lãi suất âm là hầu như không thể trong thực hành thì chắc chắn rằng bất cứ ai sẽ bao giờ sẵn sàng trả tiền cho bạn để vay tiền của mình. Hình 8.2. PW (i) trên một phạm vi của tôi là cho dự án của ông Kinkaid Nếu ước tính của tất cả các dòng tiền của ông Kinkaid là chính xác, các đồ thị trong hình 8.2 nói với anh một vài điều quan trọng về đề xuất của ông. Đầu tiên, đưa ra một số lãi suất, đồ thị nói với anh như thế nào nhiều lợi nhuận (hoặc lỗ nếu mức lãi suất quá cao), ông sẽ nhận được, trong điều kiện hiện nay, từ dự án của mình. Các đồ thị cũng nói với anh những gì loạt các mức lãi suất dự án của mình sẽ được lợi nhuận trong và những người thân mà nó sẽ không. Cuối cùng, những hình ảnh nói với anh "i quan trọng", nơi PW (i) = 0. i quan trọng này sẽ được thảo luận sau trong chương này trong phần "nội bộ Tỷ lệ Return, IRR." Phần trước <Day Day Up> Phần tiếp theo




































































































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2024 I Love Translation. All reserved.

E-mail: