CPCCBC4002A: Assessment 4What you have to doMake any assumptions you n dịch - CPCCBC4002A: Assessment 4What you have to doMake any assumptions you n Việt làm thế nào để nói

CPCCBC4002A: Assessment 4What you h

CPCCBC4002A: Assessment 4
What you have to do
Make any assumptions you need to, but be sure to include them as part of your assessment.
Question
A WHS Management Plan sets out the arrangements to manage work health and safety on a construction project. A WHS Management Plan must be in writing and be easily understood by workers. The level of detail required for a WHS Management Plan will depend on how complex the project is and the risks involved in the work to be carried out. The Principal Contractor is responsible for developing the plan.
For Project 2 – The Strathfield Apartments, as the Principal Contractor, you are required to prepare a WHS Management Plan. As a minimum you are required to prepare the following documentation:
A WHS Policy
The Roles and Responsibilities of persons in control of the site
Hazard identification and risk control
Safe work Method Statements
Information, training, instruction and supervision
Consultation, co-operation and co-ordination
Incident Management
Site Safety Rules
Subcontractor Management
Health and Safety Site Inspections
The Documentation should include: a procedure and any standard forms and registers that are required to manage the documents and procedure. The standard forms required as a minimum are:
A WHS Policy
A Toolbox meeting Record
Site Induction Register
Daily Inspection Sheet
Subcontractor SWMS register
Subcontractor register
PPE Issue and Register
Incident Report
Register of Injuries
Training and Competency Register
You need to determine where these forms would fit into the structure of your WHS Management Plan and put them in their relative sections. For example, A Toolbox meeting record form would likely to be found in the Consultation, co-operation and co-ordination section. You should also include a cover sheet for your plan, a page with your company details and project specifics, a contents page. Your WHS Management plan should also include a page/form to track changes made to your plan for quality control purposes.
Your WHS Management Plan should also be project specific and relate to Project 2 and have your details as the Principal Contractor. Your documents including your standard forms and procedures should have a standard letterhead or logo. See below for an example of a letterhead.

Company Name
ABN and Licence Number
Address
Contact Details (number/email/web page)
Remember, make any assumptions you need to for the preparation of the WHS Plan.
There are many resources on the internet on WHS Management Plans for construction site. A good place to start is the WorkCover website, although dated, the Subby Pack on the WorkCover website may provide you with a good basis for your standard forms and some procedures for you WHS Management Plan.

Assessment checklist
I have:
Completed ALL questions in this assessment.
Included my name, student number, unit number, assessment number
Reviewed and spell checked my document
Saved a copy of the assessment on my own computer
CPCCBC4018A: Assessment 4
What you have to do
For this assessment, read the questions below and answer.
How you will be assessed
The questions in this assessment cover a number of areas within the unit of competency
You will need to show that you are competent across all the areas contained in this assessment.
YOU MUST show all workings where you have done calculations.

Question
1. From the readings entered in the table below, complete the reduction of the level run and determine the reduced levels.
Back sight Intermediate
sight Fore sight Rise Fall Reduced
Level Remarks
2.483 28.045 BM4
2.469 0.283 2.200 30.245 CP1
2.100 0.369 30.614 Manhole
0.812 1.288 31.902 Kerb
2.750 0.321 0.491 32.393 CP2
0.755 0.840 1.910 34.303 CP3
0.268 0.469 34.772 Step
0.486 2.522 2.236 32.536 CP4
0.265 2.248 1.762 30.774 CP5
2.501 2.236 28.538 FFL
2.991 0.490 28.048 BM4
9.208 9.205 6.727 6.724 28.048
9.205 28.045
a) What is the misclose of the level run? 0.003
b) Is this acceptable? Why or why not? This is acceptable because a misclose of 3 millimetres is acceptable.
2. The site plan attached below shows a proposed cottage on a typical residential block of land. The proposed cottage is single storey and has a side setback requirement of 900mm (i.e. the wall to boundary dimension for the side boundaries).
The house is shown set 900mm from the eastern boundary.
a) Determine if the western side boundary complies with minimum 900mm setback.
b) Calculate the dimensions of the side boundaries, ‘ad’ and ‘ce’.
Show all your working.
3. The second site plan attached below depicts a 20 x 40m block of land with a 5 x 5m grid shown in dotted lines. The grid is identified west to east with the numerals 1 to 5 and north to south A to I.
The table below gives the ‘spot’ levels taken on the grid points. The levels have been recorded to the nearest 10mm.
A B C D E F G H I
1 0.00 0.08 0.82 1.08 1.36 1.62 1.84 2.06 2.38
2 0.06 0.53 1.06 1.2
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
CPCCBC4002A: Assessment 4What you have to doMake any assumptions you need to, but be sure to include them as part of your assessment.QuestionA WHS Management Plan sets out the arrangements to manage work health and safety on a construction project. A WHS Management Plan must be in writing and be easily understood by workers. The level of detail required for a WHS Management Plan will depend on how complex the project is and the risks involved in the work to be carried out. The Principal Contractor is responsible for developing the plan.For Project 2 – The Strathfield Apartments, as the Principal Contractor, you are required to prepare a WHS Management Plan. As a minimum you are required to prepare the following documentation:A WHS PolicyThe Roles and Responsibilities of persons in control of the siteHazard identification and risk controlSafe work Method StatementsInformation, training, instruction and supervisionConsultation, co-operation and co-ordinationIncident ManagementSite Safety RulesSubcontractor ManagementHealth and Safety Site InspectionsThe Documentation should include: a procedure and any standard forms and registers that are required to manage the documents and procedure. The standard forms required as a minimum are:A WHS PolicyA Toolbox meeting RecordSite Induction RegisterDaily Inspection SheetSubcontractor SWMS registerSubcontractor registerPPE Issue and RegisterIncident ReportRegister of InjuriesTraining and Competency RegisterYou need to determine where these forms would fit into the structure of your WHS Management Plan and put them in their relative sections. For example, A Toolbox meeting record form would likely to be found in the Consultation, co-operation and co-ordination section. You should also include a cover sheet for your plan, a page with your company details and project specifics, a contents page. Your WHS Management plan should also include a page/form to track changes made to your plan for quality control purposes.Your WHS Management Plan should also be project specific and relate to Project 2 and have your details as the Principal Contractor. Your documents including your standard forms and procedures should have a standard letterhead or logo. See below for an example of a letterhead. Company NameABN and Licence NumberAddressContact Details (number/email/web page)Remember, make any assumptions you need to for the preparation of the WHS Plan. There are many resources on the internet on WHS Management Plans for construction site. A good place to start is the WorkCover website, although dated, the Subby Pack on the WorkCover website may provide you with a good basis for your standard forms and some procedures for you WHS Management Plan.Assessment checklist I have:Completed ALL questions in this assessment.Included my name, student number, unit number, assessment numberReviewed and spell checked my documentSaved a copy of the assessment on my own computerCPCCBC4018A: Assessment 4What you have to doFor this assessment, read the questions below and answer.How you will be assessedThe questions in this assessment cover a number of areas within the unit of competencyYou will need to show that you are competent across all the areas contained in this assessment. YOU MUST show all workings where you have done calculations. Question1. From the readings entered in the table below, complete the reduction of the level run and determine the reduced levels.Back sight Intermediatesight Fore sight Rise Fall ReducedLevel Remarks2.483 28.045 BM42.469 0.283 2.200 30.245 CP1 2.100 0.369 30.614 Manhole 0.812 1.288 31.902 Kerb2.750 0.321 0.491 32.393 CP20.755 0.840 1.910 34.303 CP3 0.268 0.469 34.772 Step0.486 2.522 2.236 32.536 CP40.265 2.248 1.762 30.774 CP5 2.501 2.236 28.538 FFL 2.991 0.490 28.048 BM49.208 9.205 6.727 6.724 28.048 9.205 28.045 a) What is the misclose of the level run? 0.003b) Is this acceptable? Why or why not? This is acceptable because a misclose of 3 millimetres is acceptable.2. The site plan attached below shows a proposed cottage on a typical residential block of land. The proposed cottage is single storey and has a side setback requirement of 900mm (i.e. the wall to boundary dimension for the side boundaries).The house is shown set 900mm from the eastern boundary.a) Determine if the western side boundary complies with minimum 900mm setback.b) Calculate the dimensions of the side boundaries, ‘ad’ and ‘ce’.Show all your working.3. The second site plan attached below depicts a 20 x 40m block of land with a 5 x 5m grid shown in dotted lines. The grid is identified west to east with the numerals 1 to 5 and north to south A to I.The table below gives the ‘spot’ levels taken on the grid points. The levels have been recorded to the nearest 10mm. A B C D E F G H I1 0.00 0.08 0.82 1.08 1.36 1.62 1.84 2.06 2.382 0.06 0.53 1.06 1.2
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
CPCCBC4002A: Đánh giá 4
Những gì bạn phải làm
Thực hiện bất kỳ giả định bạn cần, nhưng hãy chắc chắn bao gồm họ như là một phần của việc đánh giá của bạn.
Câu hỏi
Một kế hoạch quản lý WHS đưa ra các thỏa thuận để quản lý sức khỏe và an toàn làm việc trên một dự án xây dựng. Một kế hoạch quản lý WHS phải bằng văn bản và được dễ hiểu bởi người lao động. Mức độ chi tiết cần thiết cho một kế hoạch quản lý WHS sẽ phụ thuộc vào độ phức tạp dự án là và những rủi ro liên quan đến công việc sẽ được thực hiện. Nhà thầu chính là trách nhiệm xây dựng kế hoạch.
Đối với Dự án 2 - Các Strathfield căn hộ là nhà thầu chính, bạn được yêu cầu chuẩn bị một kế hoạch quản lý WHS. Tối thiểu bạn được yêu cầu để chuẩn bị các tài liệu sau đây:
Một chính sách WHS
Vai trò và trách nhiệm của người kiểm soát các trang web
xác định mối nguy và kiểm soát rủi ro
an toàn Báo cáo Phương pháp làm việc
thông tin, đào tạo, hướng dẫn và giám sát
tư vấn, hợp tác và đồng phối
Quản lý sự cố
an toàn trang web Rules
Nhà thầu phụ Quản lý
sức khỏe và an toàn Kiểm tra trang web
các tài liệu cần có: một thủ tục và bất kỳ hình thức tiêu chuẩn và đăng ký được yêu cầu để quản lý các tài liệu và thủ tục. Các hình thức tiêu chuẩn yêu cầu tối thiểu là:
Một chính sách WHS
họp Một Toolbox Ghi
Site cảm ứng Đăng ký
kiểm tra hàng ngày Bảng
SWMS thầu phụ đăng ký
thầu phụ đăng ký
phát hành PPE và ký
Incident Báo cáo
đăng ký các chấn thương
đào tạo và năng lực ký
, bạn cần xác định nơi các hình thức sẽ phù hợp với cấu trúc của kế hoạch quản lý WHS bạn và đặt chúng trong các phần tương đối của chúng. Ví dụ, một hình thức kỷ lục họp Toolbox sẽ có khả năng được tìm thấy trong phần tư vấn, hợp tác và phối hợp. Bạn cũng nên bao gồm cả trang bìa cho kế hoạch của bạn, một trang với chi tiết công ty của bạn và chi tiết cụ thể của dự án, một trang nội dung. Kế hoạch quản lý WHS của bạn cũng nên bao gồm một trang / form để theo dõi những thay đổi kế hoạch của bạn cho mục đích kiểm soát chất lượng.
Kế hoạch quản lý WHS bạn cũng đã có dự án cụ thể và liên quan đến dự án 2 và có thông tin chi tiết của bạn như là nhà thầu chính. Tài liệu của bạn bao gồm cả hình thức và thủ tục chuẩn của bạn phải có một giấy tiêu chuẩn hoặc logo. Xem dưới đây cho một ví dụ về một giấy. Tên công ty ABN và Số Giấy phép Địa chỉ Chi tiết liên lạc (số / email / trang web) Hãy nhớ rằng, thực hiện bất kỳ giả định bạn cần cho việc chuẩn bị các kế hoạch WHS. Có nhiều nguồn trên internet trên Quản lý WHS hoạch cho công trường xây dựng. Một nơi tốt để bắt đầu là các trang web WorkCover, mặc dù ngày, các Subby Gói trên trang web WorkCover có thể cung cấp cho bạn một cơ sở tốt cho các hình thức tiêu chuẩn của bạn và một số thủ tục cho bạn kế hoạch quản lý WHS. Danh sách kiểm tra đánh giá tôi đã: hoàn thành tất cả các câu hỏi trong này . đánh giá bao gồm tên của tôi, số học sinh, số đơn vị, số lượng đánh giá đánh giá và chính tả kiểm tra tài liệu của tôi lưu một bản sao của đánh giá trên máy tính của riêng tôi CPCCBC4018A: đánh giá 4 những gì bạn phải làm cho đánh giá này, đọc các câu hỏi dưới đây và trả lời. làm thế nào bạn sẽ được đánh giá các câu hỏi trong đánh giá này cover một số khu vực trong các đơn vị của lực bạn sẽ cần phải chứng minh rằng bạn có thẩm quyền trên tất cả các khu vực chứa trong đánh giá này. bẠN pHẢI hiển thị tất cả hoạt động mà bạn đã thực hiện các phép tính. câu hỏi 1. Từ các bài đọc đã nhập trong bảng dưới đây, hoàn thành việc giảm thời gian cấp và xác định mức giảm. Sao Trung cấp cảnh cảnh Fore cảnh Rise Fall Giảm Cấp Bình luận 2,483 28,045 BM4 2,469 0,283 2,200 30,245 CP1 2,100 0,369 30,614 cống 0,812 1,288 31,902 Kerb 2,750 0,321 0,491 32,393 CP2 0,755 0,840 1,910 34,303 CP3 0,268 0,469 34,772 Bước 0,486 2,522 2,236 32,536 CP4 0,265 2,248 1,762 30,774 CP5 2,501 2,236 28,538 FFL 2,991 0,490 28,048 BM4 9,208 9,205 6,727 6,724 28,048 9,205 28,045 a) misclose của chạy độ là gì? 0,003 b) Đây có phải là chấp nhận được? Tại sao hoặc tại sao không? Đây là chấp nhận được vì một misclose của 3 mm là chấp nhận được. 2. Các kế hoạch trang web đính kèm dưới đây cho thấy một tiểu đề xuất trên một khối dân cư tiêu biểu của đất. Ngôi nhà được đề xuất là tầng duy nhất và có một yêu cầu bên lùi của 900mm (tức là các bức tường để chiều biên cho ranh giới bên). Ngôi nhà được hiển thị thiết lập 900mm từ ranh giới phía đông. A) Xác định ranh giới phía tây tuân thủ 900mm tối thiểu thất bại. b) Tính toán kích thước của các ranh giới phía, 'quảng cáo' và 'ce'. Hiện tất cả làm việc của bạn. 3. Các kế hoạch trang web thứ hai đính kèm dưới đây mô tả một khối 40m x 20 đất với một lưới 5m 5 x thể hiện trong đường chấm. Lưới điện được xác định phía tây sang đông với các chữ số 1-5 và phía bắc đến phía nam A đến I. Bảng dưới đây cung cấp cho các cấp độ 'tại chỗ' đưa vào các điểm lưới. Các cấp đã được ghi vào 10mm gần nhất. Abcdefghi 1 0.00 0.08 0,82 1,08 1,36 1,62 1,84 2,06 2,38 2 0,06 0,53 1,06 1,2



















































đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.

Copyright ©2025 I Love Translation. All reserved.

E-mail: