Scheduled working time:
Specialized worker 75.00$/h; 50 h
Worker 50.00$/h; 100 h
Expected usage of material:
Equipment rental 5,000$
Construction commodities 3,000$
Contractor’s overhead 30%
Contract value = (75.00∗50 + 50.00∗100) + (5,000 + 3,000)∗1.3 = 19,150$