All materials that, in the BOM, appear under one material in collective requirements are planned as collective requirements (inheritance) irrespective of the setting in the material master. Note, that in order for the make-to-order concept to pass several levels in the BOM, we must have inheritance through the BOM explosion. In the above example, if item 100-100 was set to collective, item 100-110 would be treated as make to stock, versus, make to order. In order for 100-110 to be a MTO component, 100-100 would have to be set to individual requirements as well.