a. If party B does not complete progress as scheduled, party B’s penalty should be paid at 5 % of contract’s total value (before tax) per each actual delay date.b. After party A’s advance amount of this contract, if party B has not commenced yet within 02 days from starting date of this contract, party A has the right to cancel/terminate this contract. In this case of party B shall compensate double for the first advance;c. If party B has not implemented this project properly or completed it as scheduled, party A reserves the right to unilaterally terminate this contract. In this case of party B shall pay his all advance back to party A during 30 days from party A’s termination; party B could be not deducted or remove the unfinished projects at the same time.In these cases of items (b) & (c) as mentioned above, party A is entitled to unilaterally select and sign another contractor for carrying this project out continuously.