MINUTES OF MEETING
OCC Regular Project Meeting
Provision if infrastructure data for initialisation
PMU acknowledges the fact that data provided by VNR so far are not in line with the TOR and the requirements of the OCC system.
Missing data for Package 2:
- Consistent type data for wagons
- Control digit for all wagons
- Infrastructure data
Infrastructure data have been received and forwarded to SMA for review. For the wagon data, Mr. Alexander will contract the VNR responsible.
MS3: Installation test lab, renovation
Renovation and upgrading rooms for NOCC and ROCC
The remaining renovation items will be carried out for Package 2
MS5: Software customisation & configuration
5a: Package 1
Configuration and delivery of Package 1 including documentation
As-build documents have been submitted. PMU feedback is pending. RCIC signature is pending for a subset of the documents.
MS6: OBU delivery
OBU delivery
The contractor shipped 14 new OBUs to Vietnam to replace the defected ones.
However, customs clearance is prevented by an open tax issue on the side of PMU.
ITD procurement team proposed another option. This will be clarified with Ms. Hoang Anh
MS7a: Training Package I
Status: Heavily delayed. The Employer issued a Change Request to involve the Railways Vocational School (RSV). The final decision on the cost estimation and the updated training concept is pending.
For user examination and certification the following roles shall be considered only: drivers, station masters, and section control.
MOT requires a MON on the budget. PMU will forward the draft for review.
MS8: Commissioning & Go Live
Creation of Maintenance Concept & Manual
The contractor submitted the document. The language of the 3rd party documents (by CISCO, HP, DELL, etc.) cannot be changed due to legal implications.
PMU will help to explain this to the authorities if needed. IVU shall submit 3 hardcopies of the VN document.
Rearrangement of existing telephone system
Hasitec is working to combine the Cost Estimation of Hanoi and Danang. Since the coordination and agreement on the additional costs between all Involved stakeholders (Hasitec, IVU, PMU, MOT) is expected to become a difficult and time consuming process, PMU will work toward initiating a tendering process to implement this change outside of the currently running project.
Installation of 379 OBU’s
Status: 332 OBU installation were accepted during SAT. The contractor is requested to finalize the installation of all remaining devices (Including 14 replaced OBU and the D20E problem).
For the D20E, VNA officially refused the approved solution to conect the OBU to the battery and proposes a 220 VAC power source instead, IVU shall issue a response letter to clarify the scope of the change request.
8a: Commissioning & Go Live Package I
Functional test by Super User
PMU is working together with VNR on the acceptance and commissioning approval of Package 1. The pre-commissioning statement (issued 31.5.2013) and report by the contractor have been received without objections. The testing is ongoing.
Other Items
Additional data centre air conditions (AC)
The additional AC have been installed. PMU requested the following additional information
1. Current situation and proposal (as mentioned at point 5 and 6 of the site record);
2. Installation solution (drawing of the new proposed position), the impact on the current power cable;
3. The general cost estimation.
Tax refund – Export of 1 defective OBU's
The export is blocked by a tax issue. PMU issued an according official letter to customs, However, so far the issue has not been solved.
ITD procurement team proposed another option. This will be clarified with Ms. Hoang Anh
EUR payment No.2
All hardcopies are in Hanoi now. The submission is planned within this week.
EUR payment No.3
The document preparation for payment no. 3 shall be started.
Next Meeting
Next Regular Project Meeting:
August 09, 2016
Blue Jeans is used for online meetings. Please follow the link in the invitation.
Sebastian will be absent (Jul 28 – Aug 12). Meeting will be held by Ms. Claudia
0/5000
Từ: -
Sang: -
Kết quả (Việt) 1: [Sao chép]
Sao chép!
MINUTES OF MEETINGOCC Regular Project MeetingProvision if infrastructure data for initialisationPMU acknowledges the fact that data provided by VNR so far are not in line with the TOR and the requirements of the OCC system.Missing data for Package 2:- Consistent type data for wagons- Control digit for all wagons- Infrastructure dataInfrastructure data have been received and forwarded to SMA for review. For the wagon data, Mr. Alexander will contract the VNR responsible.MS3: Installation test lab, renovationRenovation and upgrading rooms for NOCC and ROCCThe remaining renovation items will be carried out for Package 2MS5: Software customisation & configuration5a: Package 1Configuration and delivery of Package 1 including documentationAs-build documents have been submitted. PMU feedback is pending. RCIC signature is pending for a subset of the documents.MS6: OBU deliveryOBU deliveryThe contractor shipped 14 new OBUs to Vietnam to replace the defected ones.However, customs clearance is prevented by an open tax issue on the side of PMU.ITD procurement team proposed another option. This will be clarified with Ms. Hoang AnhMS7a: Training Package IStatus: Heavily delayed. The Employer issued a Change Request to involve the Railways Vocational School (RSV). The final decision on the cost estimation and the updated training concept is pending.For user examination and certification the following roles shall be considered only: drivers, station masters, and section control.MOT requires a MON on the budget. PMU will forward the draft for review.
MS8: Commissioning & Go Live
Creation of Maintenance Concept & Manual
The contractor submitted the document. The language of the 3rd party documents (by CISCO, HP, DELL, etc.) cannot be changed due to legal implications.
PMU will help to explain this to the authorities if needed. IVU shall submit 3 hardcopies of the VN document.
Rearrangement of existing telephone system
Hasitec is working to combine the Cost Estimation of Hanoi and Danang. Since the coordination and agreement on the additional costs between all Involved stakeholders (Hasitec, IVU, PMU, MOT) is expected to become a difficult and time consuming process, PMU will work toward initiating a tendering process to implement this change outside of the currently running project.
Installation of 379 OBU’s
Status: 332 OBU installation were accepted during SAT. The contractor is requested to finalize the installation of all remaining devices (Including 14 replaced OBU and the D20E problem).
For the D20E, VNA officially refused the approved solution to conect the OBU to the battery and proposes a 220 VAC power source instead, IVU shall issue a response letter to clarify the scope of the change request.
8a: Commissioning & Go Live Package I
Functional test by Super User
PMU is working together with VNR on the acceptance and commissioning approval of Package 1. The pre-commissioning statement (issued 31.5.2013) and report by the contractor have been received without objections. The testing is ongoing.
Other Items
Additional data centre air conditions (AC)
The additional AC have been installed. PMU requested the following additional information
1. Current situation and proposal (as mentioned at point 5 and 6 of the site record);
2. Installation solution (drawing of the new proposed position), the impact on the current power cable;
3. The general cost estimation.
Tax refund – Export of 1 defective OBU's
The export is blocked by a tax issue. PMU issued an according official letter to customs, However, so far the issue has not been solved.
ITD procurement team proposed another option. This will be clarified with Ms. Hoang Anh
EUR payment No.2
All hardcopies are in Hanoi now. The submission is planned within this week.
EUR payment No.3
The document preparation for payment no. 3 shall be started.
Next Meeting
Next Regular Project Meeting:
August 09, 2016
Blue Jeans is used for online meetings. Please follow the link in the invitation.
Sebastian will be absent (Jul 28 – Aug 12). Meeting will be held by Ms. Claudia
đang được dịch, vui lòng đợi..
Kết quả (Việt) 2:[Sao chép]
Sao chép!
BIÊN BẢN HỌP
OCC thường xuyên họp Dự án
Cung cấp nếu dữ liệu của cơ sở hạ tầng cho khởi
PMU thừa nhận một thực tế rằng các dữ liệu được cung cấp bởi VNR cho đến nay là không phù hợp với các điều khoản tham chiếu và các yêu cầu của hệ thống OCC.
Thiếu dữ liệu cho Gói 2:
- kiểu dữ liệu nhất quán cho toa xe
- điều khiển số cho tất cả các toa xe
- Cơ sở hạ tầng dữ liệu
dữ liệu Cơ sở hạ tầng đã được nhận và chuyển tiếp đến SMA để xem xét. Đối với các dữ liệu toa xe, ông Alexander sẽ ký hợp đồng với VNR có trách nhiệm.
MS3: phòng thí nghiệm thử nghiệm lắp đặt, cải tạo
Cải tạo và nâng cấp phòng cho NOCC và ROCC
Các hạng mục cải tạo còn lại sẽ được thực hiện cho trọn gói 2
MS5: Phần mềm tùy biến và cấu hình
5a: Gói 1
cấu hình và cung cấp các gói 1 bao gồm tài liệu
giấy tờ As-xây dựng đã được gửi. PMU phản hồi được cấp phát. Chữ ký RCIC là cấp phát một tập hợp con của các tài liệu.
MS6: OBU giao hàng
giao OBU
Nhà thầu vận chuyển 14 mới OBUs đến Việt Nam để thay thế những người đào thoát.
Tuy nhiên, thủ tục hải quan được ngăn chặn bởi một vấn đề thuế mở ở phía bên của Ban QLDA.
ITD mua sắm nhóm đề xuất lựa chọn khác. Điều này sẽ được làm rõ với bà Hoàng Anh
MS7a: Đào tạo trọn gói tôi
Status: nặng nề chậm. Chủ đầu tư đã đưa ra một yêu cầu thay đổi liên quan đến đường sắt Trường dạy nghề (RSV). Quyết định cuối cùng về việc lập dự toán chi phí và các khái niệm đào tạo cập nhật được cấp phát.
Đối với người sử dụng kiểm tra và chứng nhận các vai trò sau chỉ được xem xét:. Trình điều khiển, thạc sĩ trạm, và kiểm soát phần
MOT đòi hỏi một MON về ngân sách. Ban QLDA sẽ chuyển tiếp các dự thảo để xem xét.
MS8: Vận hành & Go Live
Tạo Bảo trì Concept & Manual
Nhà thầu đệ trình các tài liệu. Ngôn ngữ của các tài liệu bên thứ 3 (CISCO, HP, DELL, vv) không thể bị thay đổi do tác động pháp lý.
Ban QLDA sẽ giúp đỡ để giải thích điều này với chính quyền nếu cần thiết. UIV nộp 3 in giấy của tài liệu VN.
Sắp xếp lại hệ thống điện thoại hiện có
Hasitec đang làm việc để kết hợp các ước tính chi phí của Hà Nội và Đà Nẵng. Kể từ sự phối hợp và thống nhất về các chi phí bổ sung giữa tất cả các bên liên quan Tham Gia (Hasitec, UIV, Ban QLDA, Bộ Thương mại) dự kiến sẽ trở thành một quá trình tốn khó khăn và thời gian, Ban QLDA sẽ làm việc hướng tới bắt đầu một quá trình đấu thầu để thực hiện thay đổi này bên ngoài hiện đang chạy dự án.
lắp đặt 379 OBU của
Status: 332 lắp đặt OBU đã được chấp nhận trong SAT. Các nhà thầu được yêu cầu để hoàn thành việc cài đặt của tất cả các thiết bị còn lại (Bao gồm 14 thay OBU và vấn đề D20E).
Đối với D20E, VNA đã chính thức từ chối giải pháp đã được phê duyệt để Conect các OBU để pin và đề xuất một nguồn điện 220 VAC thay vào đó, UIV ban hành một thư trả lời để làm rõ phạm vi các yêu cầu thay đổi.
8a: vận hành & Go Live gói tôi
Chức năng kiểm tra bởi Super User
PMU được làm việc cùng với VNR về việc tiếp nhận và vận hành chính của gói 1. những tuyên bố trước vận hành (ban hành 2013/05/31) và báo cáo của các nhà thầu đã nhận được mà không phản đối. Các thử nghiệm đang diễn ra.
Mục khác
bổ sung các điều kiện không khí trung tâm dữ liệu (AC)
AC bổ sung đã được cài đặt. Ban QLDA yêu cầu thêm các thông tin sau
1. Tình hình và đề xuất hiện tại (như đã đề cập tại điểm 5 và 6 kỷ lục tại chỗ);
2. Giải pháp lắp đặt (bản vẽ của các vị trí đề xuất mới), tác động vào các dây cáp điện hiện hành;
3. . Chi phí chung dự toán
hoàn thuế - Xuất khẩu 1 khiếm khuyết OBU của
Việc xuất khẩu bị chặn bởi một vấn đề thuế. Ban QLDA ban hành công văn theo phong tục, Tuy nhiên, cho đến nay vấn đề này vẫn chưa được giải quyết.
Nhóm mua sắm ITD đề xuất lựa chọn khác. Điều này sẽ được làm rõ với bà Hoàng Anh
EUR số 2 thanh toán
tất cả các bản in ở Hà Nội bây giờ. Việc trình được lên kế hoạch trong tuần. Này
số 3 trả EUR
Việc chuẩn bị tài liệu cho không thanh toán. 3 được bắt đầu.
Tiếp theo Hội nghị
Tiếp theo Hội nghị dự án định kỳ:
09 tháng 8 năm 2016
Blue Jeans được sử dụng cho các cuộc họp trực tuyến. Hãy làm theo các liên kết trong thư mời.
Sebastian sẽ vắng mặt (28 Tháng Bảy - 12 Tháng Tám). Hội nghị sẽ được tổ chức bởi bà Claudia
đang được dịch, vui lòng đợi..
 
Các ngôn ngữ khác
Hỗ trợ công cụ dịch thuật: Albania, Amharic, Anh, Armenia, Azerbaijan, Ba Lan, Ba Tư, Bantu, Basque, Belarus, Bengal, Bosnia, Bulgaria, Bồ Đào Nha, Catalan, Cebuano, Chichewa, Corsi, Creole (Haiti), Croatia, Do Thái, Estonia, Filipino, Frisia, Gael Scotland, Galicia, George, Gujarat, Hausa, Hawaii, Hindi, Hmong, Hungary, Hy Lạp, Hà Lan, Hà Lan (Nam Phi), Hàn, Iceland, Igbo, Ireland, Java, Kannada, Kazakh, Khmer, Kinyarwanda, Klingon, Kurd, Kyrgyz, Latinh, Latvia, Litva, Luxembourg, Lào, Macedonia, Malagasy, Malayalam, Malta, Maori, Marathi, Myanmar, Mã Lai, Mông Cổ, Na Uy, Nepal, Nga, Nhật, Odia (Oriya), Pashto, Pháp, Phát hiện ngôn ngữ, Phần Lan, Punjab, Quốc tế ngữ, Rumani, Samoa, Serbia, Sesotho, Shona, Sindhi, Sinhala, Slovak, Slovenia, Somali, Sunda, Swahili, Séc, Tajik, Tamil, Tatar, Telugu, Thái, Thổ Nhĩ Kỳ, Thụy Điển, Tiếng Indonesia, Tiếng Ý, Trung, Trung (Phồn thể), Turkmen, Tây Ban Nha, Ukraina, Urdu, Uyghur, Uzbek, Việt, Xứ Wales, Yiddish, Yoruba, Zulu, Đan Mạch, Đức, Ả Rập, dịch ngôn ngữ.