Time Schedule" in the proposed CONTRACT DOCUMENTS indicates the overall project schedule and the key dates thereof. The general schedules are as follows.
1) The BIDDER should complete the design document of Landscaping and get the approval of Owner within 21 days after the BIDDER received the Letter of Acceptance from the CHENGDA.
2) The site area will be hand over to CONTRACTOR by 3-4 times according the actual conditions, and the CONTRACTOR will complete corresponding landscaping construction works within 30days after received the site area.
3) The first site area is estimated to hand over to contractor on September 30, 2016.
The last site area is estimated to hand over to contractor on January 15, 2017.
Hereby the estimated construction period is from October 1, 2016 to Feb 15, 2017.