Critical point below needs a good plan to lead construction to success:- Access way for big size and long equipment when they are delivered to job site and erection location.- Available space with stabilize foundation for unloading and lifting big and high equipment.- Free access way for all vehicles running during equipment installation- Temporary stock yard with stabilize foundation, secure for unloading heavy equipment.- Equipment job method statement and Task risk analysis should be comprehensive review in term of safety and technical points.- Good coordination between civil team and mechanical team, E&A team in term of schedule and quality of foundation in order to avoid lost time when equipment available in jobsite for installation. - Good plan for drain out water when raining comes and commissioning phase.- Construction management documentation such as quality control, safety control, and schedule control should have good prepared and ready in place for using. 1.2 Construction management organization and responsibilities